Incoming-Outgoing Devices
Coating
Acceptance without Bakeout
Pumping Speed
Acceptance with Bakeout
Leak Check
Safety im Labor
|
| Incoming-Outgoing Devices |
Not logged in |
 |
|
|
Message ID: 100
Entry time: Thu Nov 19 10:15:23 2020
|
| Author: |
Cristina |
| Category: |
Coating |
| Subject: |
Parts for Cryring |
| Expected: |
|
| Current Status: |
|
| New Expected Date: |
|
| Date Received: |
Beginning October 20 |
| Status: |
DONE |
| Visual Inspection: |
Accepted |
| Test Started: |
16.11.20 |
| Setup: |
Horizontal Coating Setup |
| Test Ended: |
17.11.20 |
| Result: |
Accepted |
| Outgoing Date: |
26.11.20 |
| Taken by: |
David (Cryring) |
|
|
| There are some parts which were not coated: 2 bellows (the Cryring people still did not receive them from the company) and a T-piece, which was brought to the cleaning on the 20 of October and it is not yet ready. |