17
|
Wed May 15 01:11:45 2024 |
David, Asahi, Shahab, Chris, Ruijiu | General | Time optimisation |
DAQ stopped at 01:11 to optimise data taking cycle of RSAs.
Changed data writing time from 2s -> 1.8s. |
19
|
Wed May 15 02:07:02 2024 |
Chris G, Asahi Y | General | No beam to ESR |
Injection to ESR stopped around 02:04:45.
Will continue to write data in hope that beam returns shortly. |
Attachment 1: 2024-05-15_02-08-05-614.png
|
|
20
|
Wed May 15 02:12:59 2024 |
Chris G, Asahi Y | General | Beam returned to ESR |
Injection to ESR restarted around 02:12:15 |
Attachment 1: 2024-05-15_02-14-16-471.png
|
|
22
|
Wed May 15 09:35:08 2024 |
Beatriz, Min | General | No beam |
At 9:32 we lost the beam. They have to work in the Unilac and there will be no beam for 45 minutes. |
23
|
Wed May 15 10:58:32 2024 |
Beatriz, Min | General | Beam returned to ESR |
Beam recovery at around 10:52:30. Sergey and Yuri still tuning the mass resolution. |
27
|
Wed May 15 13:39:10 2024 |
Beatriz, Min | General | ESR setting |
From 13:37 ESR will be changed again. Now back to the primary beam, it will be attempted to measure the orbit of the beam. |
28
|
Wed May 15 16:55:10 2024 |
Jeroen, Johan | General | Tuning ESR scraper. Isomer resolved. |
4:50 Scraper tuned to produce Gaussian beam profile for 98Mo. Isomer now clearly resolved.
Plan to take data for 98Mo fragment for 12 hours. Measurements from 4:59 are now aligned so that the Molybdenum fragment is centered in the RSA acquisition. |
30
|
Wed May 15 17:45:09 2024 |
Jeroen, Johan | General | No beam to ESR |
Beam lost from SIS18 at 17:41:41. |
31
|
Wed May 15 17:47:34 2024 |
Jeroen, Johan, Shahab | General | New Trigger Setup |
We changed the trigger setup, see attachment |
Attachment 1: 2024-05-15_18-06-54-910.png
|
|
59
|
Thu May 16 18:55:38 2024 |
Ide, Hubbard | General | new timing cycle |
new timing cycle of 6.7s |
68
|
Fri May 17 16:34:43 2024 |
Jelena B, Zsolt P. | General | Beam issues |
We lost beam at 16:29.
Cooler has to be investigated. |
Attachment 1: 2024-05-17_16-38-18-294.png
|
|
69
|
Fri May 17 16:42:00 2024 |
Jelena B, Zsolt P. | General | Beam back |
Beam is back at 16:38.
We are changing the setting. |
75
|
Fri May 17 20:33:43 2024 |
Jelena B, Zsolt P. | General | Beam returned to FRS |
We have again beam at FRS..
But we are taking still cycles on a same way as before...and discussing to go back to the old zirconium setting
In one hour HHT will enter the cave. |
76
|
Fri May 17 21:44:39 2024 |
Jelena B, Zsolt P. | General | Beam issues |
We do not have beam, and we have some instability during last 1-1.5 hour. |
82
|
Fri May 17 23:14:51 2024 |
Yoshi, Ohnishi | General | shift started |
Just test |
Attachment 1: 2024-05-17_23-15-51-921_tcl1064.png
|
|
Attachment 2: 2024-05-17_23-18-18-714.png
|
|
83
|
Fri May 17 23:30:16 2024 |
Shahab | General | HHT people inside |
no beam since about one hour, also HHT people inside since about 10 min. |
85
|
Sat May 18 00:15:44 2024 |
Yoshi, Ohnishi | General | Beam back |
Beam is back, but it stopped again at 0:17...... |
Attachment 1: 2024-05-18_00-16-05-529_tcl1064.png
|
|
Attachment 2: 2024-05-18_00-20-39-639_tcl1064.png
|
|
107
|
Mon May 20 09:01:51 2024 |
Oliver, Jelena | General | Shift news |
Data collection runs smooth so far.
Yuri Litvinov will start modifying SP magnets now. The resolution will change. |
108
|
Mon May 20 13:26:55 2024 |
Jelena, Oliver, Shahab | General | Plunger values |
plunger 150 for 250
plunger 48 for 410 |
109
|
Mon May 20 13:31:09 2024 |
Jelena, Oliver, Shahab | General | New setting focussing on 96-Sr |
plunger 150 for 250
plunger 48 for 410
From file starting from 13:21 is a new setting for 96Sr. |