  Bound beta decay experiment on Tl-205  Not logged in ELOG logo
Message ID: 13     Entry time: Wed Jan 29 10:42:42 2020
Author: Shahab 
Category: General 
Subject: Gas target control with the new control system event 
Many thanks to Sergey and Nikos we have tested the connection of the new control system for turning on and off of the gas target.

Connections:

For the test event machines 12 (event 162) and 14 (event 163) were chosen for gas target on and off. The old Pulzzentrale code remains unchanged on 10. The middle output of the TIF editors can then be connected to the gas target control.

The created pulses were measured on the oscilloscope and hat the duration of 1us and amplitude of 5V.

The gas target control then produces the required long pulse which comes out as a BNC connection. If in the local mode, gas target can controlled by out-on and out-off. For the above scenario, we need the event mode.

The output of the gas target control is connected to the ESR-Messhuette-Panel number 2, which goes back to Messhuete and form there to the top of ESR.


All connections are working properly until the gas target itself.

Software:

Different subchains can be activated and deactivated on demand. Also their duration can be changed on the fly, but currently a change in other settings (such as Quadrupoles) might reset the duration values to their default.
Attachment 1: IMG_20200128_153508.jpg  408 kB  | Show | Show all
Attachment 2: IMG_20200128_145345.jpg  666 kB  | Show | Show all
Attachment 3: IMG_20200128_145340.jpg  741 kB  | Show | Show all
Attachment 4: IMG_20200128_145307.jpg  677 kB  | Show | Show all
Attachment 5: IMG_20200128_144555.jpg  962 kB  | Show | Show all
ELOG V3.1.5-fc6679b