HOME
ESR
EXPERIMENTS
LABS etc
|
E121
E127
E132
E125
E143
laser_cooling_2021
E142
Ê128
E146
E0052
E0018
E0028
E0038
|
proton-capture on 118Te |
Not logged in |
|
|
Message ID: 283
Entry time: Fri Jun 5 14:06:15 2020
|
Author: |
Laszlo |
Category: |
Detectors |
Subject: |
DSSSD and SCRAPER position estimate for Xe and Te experiments |
Year: |
2020 |
|
|
We don't know the exact absolute positions of the detector (+scraper) and the beam. However, what we have to know is only these two relative positions respect to each other. To get this distance I use two methods:
1, combining the infos from the set position during the beamtime + the measured pg peak position on the detector. The pg peak position is defined only by the eye (because of the low number of counts in every case, it doesnt make much sense to make fits). Since we rely on the detector resolution, we would be never more accurate than ~ +/-1.5mm anyhow. The active area of the detector is 49.5x49.5mm2 with a 45° tilt in y.
2, MOCADI simulation of the beam and the pg peak. This is used only as a crosscheck.
3, The scraper had a small angle in y direction causing ~0.5cm shift to the upper direction. the length of the scraping edge is 7cm
-124Xe with scraper measurement:
- measurement
d1 = moved back from beam = 15 +/-.5 mm
d2 = DSSSD frame width = 8.85 mm
d3 = pg center on DSSSD = 7-7.5 bin = 21.7-23.2 mm = avg = 22.5 mm
--> pg from beam in x = -46.4mm +/- 1.5mm
--> pg on DSSSD from center ~ -3.28mm +/- 1.5mm
- simulation
x = -46.5 mm
y = 0 mm
- detector active area position
x = (-73.35mm) - (-23.85mm)
y = (-14.2195mm) - 23.5125mm
- SCRAPING: x=-35mm +/-0.5mm away from beam
y=(-20mm) - (40mm)
-118Te:
- measurement
d1 = moved back from beam = 16 +/-.5 mm
d2 = DSSSD frame width = 8.85 mm
d3 = pg center on DSSSD = 7.5 bin = 23.2 mm
--> pg from beam in x = -48.05mm +/- 1.5mm
--> pg on DSSSD from center ~ -3.28mm +/- 1.5mm
- simulation
x = -48 mm
y = 0 mm
- detector active area position
x = (-74.35mm) - (-24.85mm)
y = (-14.2195mm) - 23.5125mm
- SCRAPING:
x=-35mm +/-0.5mm away from beam
y=(-20mm) - (40mm)
notes during beam-time:
https://elog.gsi.de/esr/E127/97?suppress=1 |
|
|
|