Message ID: 110     Entry time: Sun May 9 18:50:23 2021
Author: Helmut, Wolfram, Yuri 
Category: Accelerator 
Subject: changed to 70Se 
18:45  changed SIS, ESR setting for 70Se without predrilling blind change.
E-SIS =  446.55 MeV/u, is centerd as before on TE3UF target grid.
set beamline after taret as 78Kr 36+ E = 337.375 MeV/u
set ESR to A = 70, Z=34 at isochronous E/m + 0.8 MeV/u = 369.2 MeV/u
kicker delay unchanged

4 quadrupoles failed during the change, skip cycle and reset, they work again, (GE01QS0D, GE01QS1F, GE01QS2F, GE01QS4F)

Now many lines in Schottky.

also 2 corrector coils were off, on again, now good resolution.