Incoming-Outgoing Devices Coating Acceptance without Bakeout Pumping Speed Acceptance with Bakeout Leak Check Safety im Labor
  Incoming-Outgoing Devices, Page 6 of 9  Not logged in ELOG logo
ID Date Author Category Subject Expected Current Status New Expected Date Date Received Status Visual Inspection Test Started Setup Test Ended Result Outgoing Date Taken by
  107   Wed Jan 20 11:48:54 2021 Cristinatest without bakeoutHEBT BPM cleaned @GSI   19.01.21DONEAccepted20.01.21Mobile 321.01.21Refused24.02.21M.Müller
  108   Fri Jan 29 11:50:13 2021 CristinaGeneralPillow seals SFRS   14.01.21DONEAccepted18.01.21Customised26.02.21Cond. Accep.12.03.21Cristos
  109   Fri Jan 29 11:52:53 2021 Cristinapumping speedNEG strips CRYRing   End Dec 20DONEAccepted25.01.21Fischer-Mommsen17.02.2021Accepted02.03.21Nikos
  110   Fri Jan 29 11:54:20 2021 Cristinaleak checkGate Valve   14.01.21DONEAccepted28.01.21Customised28.01.21Refused29.01.21A.Tauschwitz
  111   Fri Jan 29 11:55:45 2021 CristinaGeneralLower pressure of primary pumps   Dec 20DONEAccepted18.01.21Customised22.01.21Accepted-----G.Savino
  112   Mon Feb 1 16:04:00 2021 Phetest with bakeoutAntriebe SIS100 On schedule 01.02.2021DONE 02.02.2021Setup 110.02.2021Accepted11.02.21M.Müller
  113   Wed Feb 3 11:47:32 2021 Cristinaleak checkCARME vacuum chamberDec 2020Delayed 02.02.2021DONEAccepted02.02.2021Customised02.202.2021Accepted03.02.2021N.Petridis
  114   Wed Feb 3 11:50:09 2021 Cristinatest with bakeoutDetector Pockets for scintillators SIS18   02.02.2021on-going 08.02.21HEBT Setup11.03.21Cond. Accep.12.03.21M.Müller
  115   Wed Feb 17 11:30:26 2021 Cristinatest without bakeoutCECOM diagnostic chamber1.02.21  17.02.21DONEAccepted18.01.21Customised19.02.21Cond. Accep.  
  116   Wed Feb 17 11:31:08 2021 Cristinatest without bakeoutSIS100 BPM   15.02.21DONEAccepted16.02.21 18.02.21Accepted24.02.21M.Müller
  117   Wed Feb 17 11:50:45 2021 Cristinaleak checkSIS100 HF Cavities   15.02.21DONEAccepted15.02.21Customised16.02.21Accepted17.02.21In Weitestadt
  118   Fri Feb 19 08:39:57 2021 Cristina HEBT BPM cleaned @GSI-second measurement   10.02.21DONEAccepted10.02.21Customised18.02.21Accepted24.02.21M.Müller
  119   Fri Feb 19 08:41:46 2021 Cristinaleak check2x Cryostats-Kujouharov1.02.21 11.02.2111.02.21DONE 12.02.21Customised02.03.21Cond. Accep.09.03.21Kojouharov
  120   Wed Feb 24 13:50:25 2021 Cristinaleak checkCavity for DALINAC22.02.21Delayed01.03.2109.03.21DONENot Needed10.03.21Customised11.03.21Cond. Accep.18.03.21Dmytriiev D.
The cavity is dirty und must be cleaned
  121   Wed Feb 24 13:51:01 2021 Cristinatest with bakeout3D printed tube per pLinac01.03.21  08.03.21DONEAccepted16.03.21Setup 118.03.21Accepted18.01.21Büro Andreas
  122   Wed Mar 10 12:11:04 2021 Cristinatest with bakeoutViewports DN100 ESR   16.02.21on-goingNot Needed16.02.21Setup 116.03.21Cond. Accep.26.03.21R.Sanchez
  123   Thu Mar 18 11:40:02 2021 Cristinatest with bakeoutSIS100/HEBT Manipulator C.Dorn   17.03.21DONENot Needed18.03.21Setup 124.03.21Accepted29.03.21M.Müller
  124   Wed Apr 28 10:05:13 2021 Cristinatest without bakeoutSIS100 pumping chambers -after cleaning by the Company   23.04.21on-goingAccepted26.04.Customised21.05.21Cond. Accep.  
5 chambers checked: 07-00052-05-3; 06-00052-06-0; 07-00052-02-2; 07-00052-03-9; 07-00052-04-6
  125   Wed Apr 28 10:21:27 2021 Cristinatest without bakeoutCecom after cleaning   06.04.21DONENot Needed06.04.21Customised08.04.21Accepted12.05.21M.Müller
  126   Wed Apr 28 10:23:18 2021 Cristinatest without bakeout3Dprinting Copper coated sample   25.03.21DONENot Needed25.03.21 26.03.21Cond. Accep.  
ELOG V3.1.5-fc6679b