  80   Wed Apr 2 13:27:52 2025 Michael, Alex, MaeveAcceleratorNo beam in the ESRThere is no beam in the ESR since couple of
minutes. According to the info from HKR,
the experts started to repair the magnets
  
  79   Wed Apr 2 12:58:15 2025 Ruijiu, WolframAnalysisfrequency drift   photo_2025-04-02_15-24-34.jpgphoto_2025-04-02_15-28-44.jpgfrequency_194Pb82.xlsx 
  78   Wed Apr 2 12:13:57 2025 Michael, AlexAcceleratorSome empty injections triggered while beam patterns are changedOperators seem to play with spill cycles,
we get every 1:1 shot, then 1:10 again. During
this, we noticed a few "empty injections"
  
  77   Wed Apr 2 11:09:42 2025 Michael, AlexAcceleratorThe beam is back in the ESRWe have the beam again the ESR since around
11:00.
The Schottky spectra look the same as before.
  
  76   Wed Apr 2 10:55:16 2025 Michael, Alex, WolframAcceleratorNo beam in the ESRSince few minutes do not see any beam in the
ESR (on RSAs). There is beam in SIS and injection
requests from the ESR seem to be there as
  
  75   Wed Apr 2 10:31:15 2025 Michael, AlexAcceleratorThe beam is back from 10:10     
  74   Wed Apr 2 10:05:06 2025 Michael, Alex, YuriAcceleratorNo beam since 09:59The SIS kicker has failed again.   
  73   Wed Apr 2 10:02:40 2025 Sergey + YuriAcceleratorESR TimeoutAt around 9:40, ESR timeout changed from 10
s to 30 s
Triggering only on real injections.
  
  72   Wed Apr 2 09:28:59 2025 Michael, AlexGeneralEmpty injections in the ESRSince the FRS started to take the beam again,
the ESR gets 1/10 shots from SIS. But, the
ESR seems to request about twice more frequently
  
  71   Wed Apr 2 08:47:27 2025 Michael, AlexGeneralThe beam is backThe beam is back. But, the experts have found
a problem with one of the modules of the
SIS kicker magnet. And, currently they have
  
  70   Wed Apr 2 08:04:47 2025 Michael, AlexGeneralNo beam The SIS kicker has failed again at 08:01.
Since this has happened already few times,
the experts from the on-call duty service
  
  69   Wed Apr 2 07:41:10 2025 Michael, AlexGeneralFrequency shift in SchottkyAfter the beam  was restored at 07:25, we
think that the frequency peak in the 244
MHz RSA2 has jumped again (closer to the
  
  68   Wed Apr 2 07:39:41 2025 Michael, AlexGeneralThe beam is back at 07:35    
  67   Wed Apr 2 07:33:59 2025 Michael, AlexGeneralBeam gone again7:29, beam gone again, operators say they
need another 5 minutes.
  
  66   Wed Apr 2 07:25:15 2025 Carlo, Chris, Alex, Michael GeneralBeam back07:20  we have beam back.   
  65   Wed Apr 2 07:16:33 2025 Carlo, Chris, Alex, MichaelDAQESR not requesting7:05 ESR not requesting new pulses from the
SIS. 
Operators are trying to fix the problem.
  
  64   Wed Apr 2 05:48:31 2025 Chris, Carlo, ZacGeneralBeam returnedBeam was returned to the ESR at 05:11.

HKR said there had been some problem with
  
  63   Wed Apr 2 04:59:50 2025 Zac, Chris, CarloGeneralReceiving injections but not seeing anything on RSAsStarting at around 04:09 we don't see anything
on RSAs. RSAs are still triggering and writing
files, but only see noise. Lassie indicates
 2025-04-02_05-18-32-212_tcl1146.png2025-04-02_05-21-50-973_tcl1146.png 
  62   Wed Apr 2 04:33:57 2025 Carlo, Zac, ChrisDAQScreenshots Lassiescreenshots of Lassie  2025-04-02_04-28-59-944_tcl1064.png2025-04-02_03-38-54-877_tcl1064.png 
  61   Wed Apr 2 02:51:31 2025 Carlo, Zac, ChrisDAQBeam is back02:44 beam is back   