  107   Wed Jan 20 11:48:54 2021 Cristinatest without bakeoutHEBT BPM cleaned @GSI   19.01.21DONEAccepted20.01.21Mobile 321.01.21Refused24.02.21M.Müller    
  108   Fri Jan 29 11:50:13 2021 CristinaGeneralPillow seals SFRS   14.01.21DONEAccepted18.01.21Customised26.02.21Cond. Accep.12.03.21Cristos    
  109   Fri Jan 29 11:52:53 2021 Cristinapumping speedNEG strips CRYRing   End Dec 20DONEAccepted25.01.21Fischer-Mommsen17.02.2021Accepted02.03.21Nikos    
  110   Fri Jan 29 11:54:20 2021 Cristinaleak checkGate Valve   14.01.21DONEAccepted28.01.21Customised28.01.21Refused29.01.21A.Tauschwitz    
  111   Fri Jan 29 11:55:45 2021 CristinaGeneralLower pressure of primary pumps   Dec 20DONEAccepted18.01.21Customised22.01.21Accepted-----G.Savino    
  112   Mon Feb 1 16:04:00 2021 Phetest with bakeoutAntriebe SIS100 On schedule 01.02.2021DONE 02.02.2021Setup 110.02.2021Accepted11.02.21M.Müller    
  113   Wed Feb 3 11:47:32 2021 Cristinaleak checkCARME vacuum chamberDec 2020Delayed 02.02.2021DONEAccepted02.02.2021Customised02.202.2021Accepted03.02.2021N.Petridis    
  114   Wed Feb 3 11:50:09 2021 Cristinatest with bakeoutDetector Pockets for scintillators SIS18   02.02.2021on-going 08.02.21HEBT Setup11.03.21Cond. Accep.12.03.21M.Müller    
  115   Wed Feb 17 11:30:26 2021 Cristinatest without bakeoutCECOM diagnostic chamber1.02.21  17.02.21DONEAccepted18.01.21Customised19.02.21Cond. Accep.      
  116   Wed Feb 17 11:31:08 2021 Cristinatest without bakeoutSIS100 BPM   15.02.21DONEAccepted16.02.21 18.02.21Accepted24.02.21M.Müller    
  117   Wed Feb 17 11:50:45 2021 Cristinaleak checkSIS100 HF Cavities   15.02.21DONEAccepted15.02.21Customised16.02.21Accepted17.02.21In Weitestadt    
  118   Fri Feb 19 08:39:57 2021 Cristina HEBT BPM cleaned @GSI-second measurement   10.02.21DONEAccepted10.02.21Customised18.02.21Accepted24.02.21M.Müller    
  119   Fri Feb 19 08:41:46 2021 Cristinaleak check2x Cryostats-Kujouharov1.02.21 11.02.2111.02.21DONE 12.02.21Customised02.03.21Cond. Accep.09.03.21Kojouharov    
  120   Wed Feb 24 13:50:25 2021 Cristinaleak checkCavity for DALINAC22.02.21Delayed01.03.2109.03.21DONENot Needed10.03.21Customised11.03.21Cond. Accep.18.03.21Dmytriiev D.The cavity is dirty und must be cleaned   
  121   Wed Feb 24 13:51:01 2021 Cristinatest with bakeout3D printed tube per pLinac01.03.21  08.03.21DONEAccepted16.03.21Setup 118.03.21Accepted18.01.21Büro Andreas    
  122   Wed Mar 10 12:11:04 2021 Cristinatest with bakeoutViewports DN100 ESR   16.02.21on-goingNot Needed16.02.21Setup 116.03.21Cond. Accep.26.03.21R.Sanchez    
  123   Thu Mar 18 11:40:02 2021 Cristinatest with bakeoutSIS100/HEBT Manipulator C.Dorn   17.03.21DONENot Needed18.03.21Setup 124.03.21Accepted29.03.21M.Müller    
  124   Wed Apr 28 10:05:13 2021 Cristinatest without bakeoutSIS100 pumping chambers -after cleaning by the Company   23.04.21on-goingAccepted26.04.Customised21.05.21Cond. Accep.  5 chambers checked: 07-00052-05-3; 06-00052-06-0;
07-00052-02-2; 07-00052-03-9; 07-00052-04-6
  
  125   Wed Apr 28 10:21:27 2021 Cristinatest without bakeoutCecom after cleaning   06.04.21DONENot Needed06.04.21Customised08.04.21Accepted12.05.21M.Müller    
  126   Wed Apr 28 10:23:18 2021 Cristinatest without bakeout3Dprinting Copper coated sample   25.03.21DONENot Needed25.03.21 26.03.21Cond. Accep.      