Entry  Thu Apr 3 09:43:14 2025, All, Accelerator, Stop 194Pb, switch to 208Pb82+ 
The repair of SIS electron cooler power supplies

In the meantime we received a few injections and confirmed that 194Pb setting is still as it was before entering into the ESR
Entry  Thu Apr 3 23:23:20 2025, Zhang Min, Zhou Xu, Accelerator, Beam injection change 2025-04-03_23-21-03-095.png
The SIS operator says that FRS doesn't need beam now, ESR will receive the full SIS beam extraction every 3 secs overnight. All the secondary beams are
injected into ESR from now on.
Entry  Fri Apr 4 17:04:39 2025, H. Weick, S. Litvinov, Accelerator, slits after target, Bio_REM alarm primary_beam_on_TE4_slits.JPG
A Bio-REM detector on the roof of ESR caused an alarm and shut down the whole accelerator.
Too much primary beam going to ESR, noe we avoid it by catching the primary beam at TE4 slits.
The distribution on current grids looks liek in the LISE simulation, we cut at 5mm.
Entry  Fri Apr 4 17:10:35 2025, H. Weick, S. Litvinov, Accelerator, ESR scraper setting 
the new scraper setting for good isochronicity but still acceptable intensity losses is:
Done at ~ 15:00 today.
GEEXDS1HA (outside)          =  -8 mm
Entry  Sun Apr 6 18:36:56 2025, Shahab, Moriguchi, Taka, Accelerator, Beam stopped 
Beam stopped due to device trouble.
Entry  Sun Apr 6 18:48:36 2025, Shahab, Moriguchi, Taka, Accelerator, Beam back 
Beam is back now.
Entry  Sun Apr 6 19:23:09 2025, Shahab, Moriguchi, Taka, Accelerator, Beam sharing 
Beam sharing with FRS is now 1 to 1.
Entry  Sun Apr 6 20:13:03 2025, Taka, Moriguchi, Accelerator, Beam sharing 
Now we have every injection.
Entry  Sun Apr 6 21:29:37 2025, Taka, Moriguchi, Accelerator, Beam sharing 
again, ESR : FRS = 1 : 1
Entry  Mon Apr 7 07:09:01 2025, Jelena, Guy, Accelerator, Beam interruption, FRS 
Beam is gone since 7:02. Control room is notified. Beam is back since 7:14. FRS started taking spills.