73
|
Fri Mar 20 05:03:03 2020 |
Shahab | Runs | run entry - run046 | | beam: 124Xe54+
energy: 10 MeV/u
|
|
72
|
Fri Mar 20 04:32:22 2020 |
Shahab | Runs | run entry - run046 | | beam: 124Xe54+
energy: 10 MeV/u
|
|
71
|
Fri Mar 20 04:29:45 2020 |
Jan | DAQ | DAQ settings for the first night | | |
   |
70
|
Fri Mar 20 01:36:48 2020 |
Laszlo | General | 124Xe primary beam at 10Mev TargetON | | We didmt see any effect on the lifetime if
the target is switched on. It is because
we use only hydrogen target (but why
|
|
69
|
Fri Mar 20 01:22:23 2020 |
Shahab | Runs | Setting for Gas target | | Setting for the machines. |
|
68
|
Fri Mar 20 01:21:00 2020 |
Laszlo | General | target is switched on event based | | |
|
67
|
Fri Mar 20 01:11:58 2020 |
Laszlo | General | Target - beam jntersection | | We have managed to find the target position
with the beam by looking at the xray spectra.
The trick was that at 10mev we
|
|
66
|
Thu Mar 19 23:48:56 2020 |
Laszlo | General | 124Xe primary beam at 10Mev TargetOFF | | Beam lifetime is estimated to be 11sec at
least (hard to.see with the cursor the corrct
values on the shottky monitor)
|
  |
65
|
Thu Mar 19 19:14:40 2020 |
Laszlo | General | primary beam measurement | | Now our aim is to decelerate the primary beam
(naked 124Xe) down to 10MeV/u. At this energy
we can test our detectors and that how the |
|
64
|
Thu Mar 19 15:09:29 2020 |
Jan | General | starting off with DSSSD | | here is my short guide how to start with the
measurement as soon as we have a beam available.
|
|
63
|
Thu Mar 19 09:43:28 2020 |
Laszlo | General | Status of the ESR | | After two days of tuning the beam, yesterday
evening (~8pm), it was found out that within
one ESR pattern using the new control system |
|
62
|
Wed Mar 18 09:53:28 2020 |
Laszlo, Jan | General | vacuum after opening gate valve | | Gate valve to DSSSD setup was opened on Tue
17.03. ~9:00
|
 |
61
|
Tue Mar 17 11:44:58 2020 |
Jan | Runs | run entry - template | | beam: 118Te52+
energy: 7.4 MeV/u
|
|
60
|
Tue Mar 17 08:15:49 2020 |
Jan | General | current grids & screen in TE | | measured beam diagnosis with 124Xe48+ at 326
MeV/u |
 |
59
|
Mon Mar 16 15:15:22 2020 |
Jan | Calibration | Gamma- and X-ray intensities for efficiency calib | | Intensities for special gamma or x-ray lines
needed for efficiency calibration can be
found here:
|
|
58
|
Sun Mar 15 21:01:23 2020 |
Laszlo | Calibration | run044 - Xray35 calib Ba133 - a night long run | | Detector: 35
Source: Ba133
Distance: 334mm
|
|
56
|
Sun Mar 15 20:26:08 2020 |
Laszlo | Calibration | run043 - Xray35 calib Am241 | | Detector: 35
Source: Am241
Distance: 334mm
|
|
55
|
Sun Mar 15 19:46:34 2020 |
Laszlo | Calibration | run042 - Xray35 calib Ba133 - high rate | | Detector: 35
Source: Ba133, strong source
Distance: 334mm
|
|
54
|
Sun Mar 15 19:22:58 2020 |
Laszlo | Calibration | run041 - Xray145 calib Ba133 - high rate | | Detector: 145
Source: Ba133
Distance: 305mm
|
|
53
|
Sun Mar 15 18:53:42 2020 |
Laszlo | Calibration | run040 - Xray145 calib Am241 | | Detector: 145
Source: Am241
Distance: 305mm
|
|