Mon Sep 30 11:04:15 2019, Cristina, leak check, Cryo collimator 11-1-18-8, , , , 24.09.2019, DONE, Accepted, 25.09.2019, Customised, 25.09.2019, Accepted, 26.09.2019, L. Bozyk
|
|
Mon Sep 30 11:11:26 2019, Cristina, test with bakeout, Laser chamber -Winters, Beginning 2019, Delayed, , 16.08.2019, DONE, Accepted, 30.08.2019, Customised, 12.02.2020, Accepted, KW10, D.Winters
|
The measurement was stopped because of the wrong heating jackets |
Mon Sep 30 11:15:47 2019, Cristina , test with bakeout, Detector Recoil chamber ESR, , , , 2.09.2019, DONE, Accepted, 9.09.2019, Customised, 29.10.2019, Cond. Accep., 1.11.19, Hillenbrand
|
The chamber was brought in the lab without heating jackets, which where shipped on the 17.10.
Conditionally Accepted because the RGA after bakeout does not fulfil the requirements. |
Mon Sep 30 14:00:51 2019, Cristina, pumping speed, 800 l/s Agilent, , , , 20.09.2019, DONE, Accepted, 1Test:7.10.2019; 2Test: 14.11.2019, Fischer-Mommsen, 1.11.19, Cond. Accep., , Sent back to Agilent
|
Pumping Speed measured a bit lower than stated |
Mon Sep 30 14:04:43 2019, Cristina, pumping speed, Combi pump DN40, , , , 09.08.2019, DONE, Accepted, 20.08.2019, Fischer-Mommsen, 20.09.2019, Accepted, , Sent back to Agilent
|
|
Mon Sep 30 14:06:07 2019, Cristina, pumping speed, Slim SIP 150, , , , 9.08.2019, DONE, Accepted, 07.02.2020, Fischer-Mommsen, 06.03.2020, Accepted, ,
|
|
Wed Oct 9 07:55:47 2019, Phe, leak check, All metal gate valve (Bender), , , , 08.10.2019, DONE, Accepted, 21.10.2019, Customised, 24.10.2019, Accepted, 24.10.2019, M.Bender
|
Leak check required by Markus Bender for a "all metal gate valve". The gate valve was received on the 08.10.2019. No deadline. The gate valve is on Edgar's desk - so Edgar can check it when he's back from holiday. 23.10.2019 Test DONE |
Wed Oct 9 07:57:44 2019, Phe, test with bakeout, Cryring Detector Tube , , , , 09.10.2019, DONE, Accepted, 10.10.2019, Setup 1, 22.10.2019, Accepted, 24.10.2019, Spillmann
|
Detector tube has been received from Grossmontage (given to Andreas Kraemer). This Detector tube is for Cryring - measurement request from Dr. Uwe Spillmann. The Detector tube needs to have some additional components, which will be assembled by Alexander Borovik (from Giessen University).
Email has been sent to Alexander Borovik and he might pick the Detector Tube on 09.010.2019. The Detector Tube is on Phe's desk.
The detector tube has been picked up by Alexander Borovik (09.10.2019).
The additional component has been assembled to the Detector tube (09.10.2019) |
Wed Oct 9 08:01:51 2019, Phe, test with bakeout, Macor Samples from Tino Giacomini, , , , 02.10.2019, DONE, Accepted, 10.10.2019, Mobile 2, 6.11.19, Accepted, 8.11.19, Giacomini
|
Macor samples have been received from Tino Giacomini on the 02.10.2019. These Macor samples will be used for IPM chamber. The test request is a vacuum acceptance test with bake-out. |
Wed Oct 9 14:19:09 2019, Phe, test with bakeout, Scrapper for ESR (for Markus Steck), , , , 09.10.2019, DONE, Accepted, 14.10.2019, Setup 2, 18.10.2019, Accepted, 24.10.2019, Schwarz
|
Measurements asked as "urgent" for ESR. This piece was already measured in 2014, and then stored in an unkwon place. |
Mon Oct 14 10:08:14 2019, Cristina, leak check, Dipole chamber SIS100 First charge, , , , 10.10.2019, DONE, Accepted, 11.10.2019, Customised, 29.11.2019, Accepted, , Stored in the TH
|
6 dipole received on the KW41. Integral leak check and 1 test without bakeout
After the vacuum test the chambers must be inserted on the magnet: 1 chamber was not fitting easy into the magnet. It will go today (15.11.19) in the technology lab for mechanical measurements. |
Mon Oct 14 10:09:36 2019, Cristina, leak check, Roughing CWT 3 charge, , , , 10.10.2019, DONE, Accepted, 14.10.2019, Customised, 14.11.19, Accepted, , Stored in Weiterstadt
|
Integral leak check to be done for all CWT.
DONE:
07-51-23-0; 07-51-26-1; 07-51-30-8; 07-51-31-5; 07-51-17-9; 07-51-28-5;07-51-21-6 (Black-orange spots visible);07-51-36-0; 07-51-37-7; 07-51-32-2; 07-51-14-8;07-51-35-3;07-51-18-6; 07-51-29-2; 07-51-34-6 |
Wed Oct 16 08:24:29 2019, Toni, leak check, Kryokollimator , June 2019, Delayed, August, from September 2019, DONE, Not Needed, 02.09.2019, Customised, 09.12.2020, Accepted, ,
|
Collimator tested:11-1-02-7; 11-1-03-4; 11-1-4-01; 11-1-06-5; 11-1-09-6; 11-1-10-2; 11-1-11-9; 11-1-12-6; 11-1-14-0; 11-1-15-7; 11-1-16-4; 11-1-17-1; 11-1-18-8; 11-1-20-1;11-1-25-6; 11-1-22-5;11-01-24-4;11-1-28-7;11-1-27-0;11-1-29-4;11-1-26-3;11-1-13-3;11-1-21-8;11-1-40-9; 11-1-39-3;11-1-30-0;11-1-19-5 (LEAK!!!); 11-1-33-1;11-1-23-2; 11-1-43-0;11-1-42-3; 11-1-37-9; 11-1-63-8; 11-1-57-7; 11-1-45-4; 11-1-49-2; 11-1-44-7; 11-1-58-4; 11-1-24-9;11-1-36-2; 11-1-31-7; 11-1-38-6; 11-1-55-3; 11-1-53-9; 11-1-32-4;11-1-50-8; 11-1-34-8; 11-1-61-4;11-1-65-2; 11-1-64-5; 11-1-60-7;11-1-62-1;11-1-66-9; 11-1-51-5;11-1-59-1; 11-1-35-5; 11-1-52-2;11-1-48-5; 11-1-41-6; 11-1-46-1; 11-1-56-0; 11-1-54-6 |
Mon Oct 21 10:24:59 2019, Cristina, Other, Tube Heidelberg, , , , 17.10.2019, DONE, Accepted, First Test: 24.10.2019; Second Test:30.01.20 , Horizontal Coating Setup, 29.10.2019: Refused; Second Test: 05.02.2020, Accepted, 11.02.2020, C.Schröter
|
Tube to be coated for HD. After the first coating: PEELING. STOP and waiting for the nextstep to be decided in HD.
We cleaning the tubes many times, to try to remove all the film, and then we performes succesfully the second coating. |
Thu Oct 24 14:55:28 2019, Toni, , , , , , , , , , , , , ,
|
|
Thu Oct 24 14:58:25 2019, Toni, , , , , , , , , , , , , ,
|
|
Fri Nov 1 10:41:45 2019, Cristina, test with bakeout, IPM Chamber, , , , 4.09.2019, DONE, Refused, , , , Refused, 1.11.19, Angelo
|
Bellows to short |
Fri Nov 8 10:52:43 2019, Cristina, test with bakeout, Macor 2 for IPM, , , , 8.11.19, DONE, Accepted, 11.11.2019, Mobile 2, 18.11.2019, Accepted, 04.12.19, T. Giacomini
|
|
Mon Nov 11 08:06:09 2019, Phe, test without bakeout, Ref. Chamber for Beam Diagnostic Manipulator (Hackhalle), , , , unknown, DONE, Accepted, 11.11.2019; 10:15 am, stopped 12.11.2019, Customised, , Refused, ,
|
Broken gauge (cold cathode gauge). |
Thu Nov 14 14:00:28 2019, Phe, test without bakeout, Ref. Chamber for Beam Diagnostic Manipulator, , , , unknown, DONE, Accepted, 14.11.2019; 10:30 am, Customised, 22.11.2019, Cond. Accep., N/A, N/A
|
Wide range gauge is now installed on the chamber. The previous test with cold cathode gauge failed due to broken gauge.
Another complete new gauge is now installed on the chamber. |
|