  110   Mon May 20 14:02:03 2024 Jelena, Oliver, ShahabDAQRetune 245 MHz
Mew numbers for 245 MHz plunger is 190 (both)
  1   Tue Apr 16 15:35:07 2024 JanCollaborationG-PAC Proposal
  93   Sat May 18 13:13:45 2024 Yuri, Taka, Xinliang, Sophia, Yuanming, Ragan, Shahab CalibrationShorter shots with 98 Mo
now making shorter shots with 98-Mo
3 seconds each
50 MSPS

98Mo
13:57  RSA01-2024.05.18.13.57.32.674.tiq, RSA02-2024.05.18.13.57.32.472.tiq
13:58 RSA01-2024.05.18.13.58.32.760.tiq, RSA02-2024.05.18.13.58.32.552.tiq
14:00 RSA01-2024.05.18.14.00.23.759.tiq, ../RSA02/RSA02-2024.05.18.14.00.23.551.tiq
14:01 RSA01-2024.05.18.14.01.09.543.tiq, ../RSA02/RSA02-2024.05.18.14.01.16.038.tiq
14:01 RSA01-2024.05.18.14.01.54.049.tiq, ../RSA02/RSA02-2024.05.18.14.02.05.544.tiq 


last long shot :
14:05 RSA01-2024.05.18.14.05.14.375.tiq, ../RSA02/RSA02-2024.05.18.14.08.54.672.tiq

1 second each 


RSA01-2024.05.18.14.08.54.879.tiq
  6   Sun May 12 18:34:54 2024 RuijiuAnalysisHow to use queqiao to transfer tiq data
If the ssh to lxir131 was disconnected, you can connect to lxir131 and restart queqiao program to transfer tiq data from NAS to luster.

1. Open a terminal on any GSI linux computer, like the one in the Measurement Room:


2. start "Online data analysis system":

(base) litv-exp@lxg1478:~$ start_OnlineDataAnalysisSystem


3. click the 3rd button "Copy data from RSA hard disk to luster" to start "queqiao" program.

4. click "start" button on "queqiao" user interface to transfer tiq data on RSA spectrum analyzer.
  24   Wed May 15 11:45:22 2024 DavidAnalysisLustre Trouble
Since around 11:30, Lustre is down, therefore in https://sparc-daq-02.gsi.de/, the spectrograms are not being updated. Expected time to recovery > 2 hours.
The data will still be stored on the local hardisk. Whenever Lustre is online, we start file transfer and analysis.

Attached can be found an information email sent:
-------------------
Dear Lustre-users,

the main metadata server of the Lustre file system shows repeated errors that break I/O on at least
some clients.

We will have to restart the server, which will cause a downtime of min. 2 hours.
-----------------------------------------------------------------------
  38   Wed May 15 23:04:32 2024 XinliangAnalysisElectron cooler data
The cooler curve measured during May 14 afternoon.
  74   Fri May 17 19:43:03 2024 Jelena B, Zsolt P., Shahab, DavidAnalysis+ Beam issues
Important - analysis 
-> we are trying to get PID with a new setting to see if 98Zr decays with 30s half-life
--> we are taking 1 min cycles 
---> strongest line does not corespondents to 96Sr38+ as it decays very fast (few seconds) and we observe long-lived one - still we have to confirm this 

----> analysis is still ongoing 

We lost the beam at 19:35

 
  11   Tue May 14 23:22:55 2024 Helmut WeickAcceleratorisochronicity curves
Sergey started with a setting with quadrupoles already changed like in 2021.
Ths was used for the first isochronicity curves.
It also gave soem, however, not good peak shapes with scrapers closed.
But after a failure only a new setting of quads could revover the peaks.

Then more cooler curves were measured and found to have quite a slope.
Changing ESR energy does not change the curves much, but changing the quads does.
With the stronger variation of quads (+1.65% on two quadrupole families) the curve tilts to opposite side.

All curves in EXCEL.
Cooler voltage converted to Brho with gamma ~ 1.4 and curves in relative frequency spread shifted on top of each other.
In new injections the quads are set new, which causes a frequency jump. Pasted parts of curves to remove jump.
  12   Tue May 14 23:40:03 2024 Helmut, Sergey, YuryAcceleratorpaper log book
two pages of log book on paper for teh first setup,
injection into ESR and tuning primary beam 100Mo and fragment 98Mo.
  33   Wed May 15 19:20:32 2024 Helmut WeickAcceleratorscraper setting
After the orbit correction on the target straight section the scrapers work better.
One pair of scrapers works best:
GEEXDS2HA (outside straight section =  low Brho side) = -4.0 mm
GE02DS3HG (outside arc              = high Brho side) = -71.4 mm
All other scrapers are open (finished playing with scrapers ~18:20)
When one side is opened more one can cut more on the other.
We can attack the beam from both sides.
With scrapers good resolution, David already posts lifetimes of the isomer.
Details in paper log book.
  34   Wed May 15 19:45:44 2024 Helmut WeickAcceleratorCooler curves after beam shift
After the Beam position tuning but before the scraper tuning two more cooler curves were taken.
The first with all scrapers open shows a similar shape to before with the same quadrupole setting.
Afterwards the ESR ebergy was shifted by -0.8 MeV/u to get the beam more on an outer orbit.
The curve then is shifted and has a bit less acceptance.
  35   Wed May 15 20:17:20 2024 JeroenAcceleratorFewer spills from SIS18 then lost beam
Apparently fewer spills coming from SIS18, see attached.

Beam was lost at 20:17:52. 
  48   Thu May 16 11:20:10 2024 SergeyAcceleratorScreenshot of ESR pattern with 140 repetitions (each is 100 ms)
Injection Beam Process: 100ms
Bunching Beam Process: 16ms
Intermediate Beam Process: 100 ms, which is repeated 140 times
Intermediate Beam Process: 16 ms
  Draft   Thu May 16 12:48:58 2024 SergeyAcceleratorTune to 98Zr
- stop longer measurements
- change quadrupole and sextupole magnets
- rescale SIS-TE-ESR
  52   Thu May 16 15:24:30 2024 Ide, HubbardAcceleratornew Plunger setting
plunger motors were set

to +/-390 mm for 245 MHz resonator
and +/-55 mm for 410 MHz resonator
  55   Thu May 16 16:43:29 2024 YuriAcceleratorHHT
HHT sees radiation from us. We stop for 10 min for them to see the speed with which the radiation level decreases.
  Draft   Fri May 17 17:03:39 2024 Helmut, YuryAcceleratorapprox. 96Sr setting
Only 96Sr would yield very few line with only ions from tiem to time.
So we went a bit lower in Brho 7.69 Tm -> 7.65 Tm.
The setting is calculated as a 98Mo39+.
E-SIS = 455.3 MeV/ for 100Mo.
after target 98Mo now with 39+ gives 7.6500 Tm.
In ESR also 39+.
In LISE we get the same average gamma as before for 98Zr (gamma = 1.40082).
  72   Fri May 17 17:09:26 2024 Helmut, YuryAcceleratorapprox. 96Sr setting (98Zr39+)
Only 96Sr would yield very few line with only ions from time to time.
So we went a bit lower in Brho 7.69 Tm -> 7.65 Tm.
The setting is calculated as a 98Mo39+.
E-SIS = 455.3 MeV/ for 100Mo,
after target 98Mo now with 39+ gives 7.6500 Tm.
In ESR also 39+.
In LISE we get the same average gamma as before for 98Zr (gamma = 1.40082).

The 98Zr was also entered as a 98Mo40+-
  77   Fri May 17 21:56:58 2024 Jelena B, Zsolt P.AcceleratorOptimizing setting
We are optimizing setting for 96Sr
start time: 21:52
  78   Fri May 17 22:06:05 2024 Jelena B, Zsolt P.AcceleratorESR
ESR is down