ID Date Authordown Category Subject Text Attachments
  28   Fri Jun 20 06:37:51 2025 KonstantinAcceleratorPosition of contaminantsI checked the positions of the contaminants.
Therefore, I drove the scrapers and observed
the signal at the Schottky detector
  
  56   Tue Jun 24 15:44:06 2025 KonstantinDAQPhase shift in DAQ1In the SetParameters.C file is a parameter
called fPar->piPhaseOffset. It was shifted
from 100 to 50 in order to see ion bunches
  
  29   Fri Jun 20 11:25:32 2025 Julien, Kristian, KonstantinLaserAutomated laser scans In contrast to entry [URL=https://elog.gsi.de/esr/E0052_2025/12]E12[/URL],
the cabling for the automated start of the
laser scan is now connected to [B]IO3 of
  
  24   Wed Jun 18 11:44:15 2025 Julien, Konstantin, Stefan, Rima Jitter CFDPulses on photodiodes in entry 20 

1. seem wide, so we also looked at qswitch
  
  25   Wed Jun 18 14:01:40 2025 Julien, Konstantin, Stefan, Rima Ion bunch on PMTsApparentlty did not work yesterday evening
(no signal), but looks fine now (see attachment)
 Bildschirmfoto_bunch_on_PMT_2025-06-18_14-11-44.png 
  22   Wed Jun 18 07:59:00 2025 Julien, KonstantinLaserPhase-offsetWe recognized that the output power of the
pump laser was instable when externally triggered
with 200kHz (stand-bye frequency of ESR).
 IMG_3889.jpgIMG_3888.jpgIMG_3891.jpgIMG_3892.jpg 
  23   Wed Jun 18 08:07:17 2025 Julien, KonstantinLasernew FCU CalibrationUV power was not stable but dropping from
~18 mW to 13 mW after opening COBRA shutters.
New calibration of frequency conversion unit:
 2025_06_18_FCU_Cal_Table.JPG2025_06_18_FCU_Cal_Plot.JPG 
  51   Mon Jun 23 10:52:34 2025 Julian, Lukas, Zsolt, Nadine, KonstantinLaserFrequency conversion unitWe exchanged the old BBO of the Cobra's FCU
with a new one. The output power of the Cobra
was around 120mJ. In the end, we achieved
  
  53   Mon Jun 23 10:59:36 2025 Julian, Lukas, Zsolt, Nadine, KonstantinRunsScan routine-Start new injection
  ->wait for 60 injections to be complete
  ->note down SIS intensity (at extraction)
  
  61   Thu Jun 26 18:13:17 2025 Jan, CarstenDetectorsPMT voltages & thresholdscurrent settings of PMT voltages and thresholds
at the CAEN CFD:
  
  64   Thu Jun 26 22:51:04 2025 Hendrik, FinnRunsNightshift data runsAfter the scan at 22:04 teh FCU new was new
calibrated. For this MEdusa was stopped and
reopened in the laser lab. This stops the
  
  66   Fri Jun 27 06:55:45 2025 Esther. KonstantinLaserLaser-ion overlapWe cross-checked the laser-ion superposition
by using the T-scrapers. We did it only after
the scans in order to do not change the duty
 2025-06-27_06-52-01-807.png2025-06-27_07-12-27-135.png2025-06-27_07-32-28-599.png2025-06-27_07-51-52-620.png 
  Draft   Fri Jun 27 06:13:02 2025 Esther, KonstantinRunsEarly shift - data taking[B]Notes:[/B] 
1. TE slits at -10 and +10
2. SIS intensity unstable until about 9:00
  
  67   Fri Jun 27 11:21:25 2025 Esther, KonstantinDAQTimingWe cross-checked the timing. Laser pulse is
detected at bins 136 (PD-North) and 171 (PD-south),
respectively. Therefore, the laser puls is
  
  18   Wed Jun 18 00:33:56 2025 Esther, Alexis, Anton, Rodolfo, CarstenDAQR4l-41We have some issues with the RIO computer
R4l-41 (DAQ1). We had to switch off completely
twice. Only then it reacted properly. Maybe
  
  20   Wed Jun 18 01:58:02 2025 Esther, Alexis, Anton, Rodolfo, CarstenAcceleratorNo Bunched BeamThe Bunching is not set properly. We do not
see the ion bunch with the Photomultiplier.
 Bildschirmfoto_PD_PMTSouth_2025-06-18_1.png 
  71   Sat Jun 28 15:28:22 2025 Carsten., Uwe RunsRuns with new scan range22:10  SIS Trafo GS09DT scale was changed
to 4e8 (not just the lassie monitor)
23:50 Ausfall ESR: GE01 KP01 bis KP05 und
  
  13   Mon Jun 16 21:47:23 2025 Carsten, Wilfried, Simon DetectorsNew threshold values for PMTsWe adjusted the thresholds for the PMTs and
increased the voltage of PMT middle to 2.7kV
  
  57   Tue Jun 24 17:39:13 2025 Carsten, Stefan, Simon, Rima, NilsDetectorsPMT behaviour - noise / PMT voltages / CFD Threshholds / CAEN Power supply (broken channel resetted)PMT North and South have been changed:

CFD CH0: Middle Thr 7 / CAEN HV Ch1: 2750
  
  14   Mon Jun 16 22:27:01 2025 Carsten, SimonDAQThresholds We also adjusted the thresholds for the mesytic.
Doing that, we noticed that one of the trafos
is broken (5th row, middle).
  