HOME ESR EXPERIMENTS LABS etc
E121 E127 E132 E125 E143 laser_cooling_2021 E142 Ê128 E146 E0052 E0018
  proton-capture on 118Te, Page 28 of 29  Not logged in ELOG logo
ID Date Author Category Subjectdown Year Text Attachments
  471   Wed May 26 15:30:03 2021 Ragan, ThanassisGeneralChanging the beam energy 2021The ESR team is changing the beam energy to
6 MeV/u.
  
  316   Thu May 6 11:03:46 2021 Jan GloriusDAQCabling Documentation2021   e127b_cabling_docu_06_05_2021_.pdfe127b_2021_cabling_documentation.xlsx 
  346   Sun May 16 13:31:49 2021 LaszloDAQCabling Documentation2021Si HV and current was switched in the last
documentation.
 e127b_2021_cabling_documentation.xlsx 
  Draft   Fri Jun 28 14:06:28 2019 JanGeneralCAD of (p,g) setup     
  350   Tue May 18 21:08:16 2021 ESR teamGeneralBeam stacking2021Beam stacking. 3 pulses, stochastically cooled
and stacked on an inner orbit
 5B6943AF-DF56-4B0F-A77E-1E3C65B3B0C0.jpegB590F232-450A-4ACF-BBA4-DB31B7B35FDA.jpeg 
  572   Tue Jun 8 15:06:17 2021 ShahabAnalysisBeam lifetime2021measured beam lifetime after the second deceleration
using parallel plate Schottky detector and
the RSA5103 spectrum analyser. Analysis code
 pgamma_lifetime.001.pngpgamma_lifetime.002.png 
  353   Wed May 19 19:47:14 2021 YuriGeneralBeam Halflife at 30 AMeV2021   2021-05-19_17-35-00_tcl1032_lassie-monitor.png 
  449   Tue May 25 17:12:59 2021 Robert/ShahabAcceleratorBeam2021Beam is back; It is now being optimized   
  250   Mon Mar 23 14:23:01 2020 Pierre-MichelDAQBackup recoil files Recoil detector files backup to lxg1260:/data.local2/hillenbrand/Laszlo   
  3   Wed Feb 6 10:04:23 2019 Laszlo VargaSimulationsBackground subtraction for 124Xe, 109In, 73As made by MOCADI General remarks to the MOCADI simulations:


scraper size vertically > (p,g) spot at the
scraping position --> (p,g) can be separated
 template.pdf 
  88   Fri Mar 20 22:26:42 2020 JanDetectorsBaF2 deactivated BaF2 detectors are deactivated nor for the
following runs.
  
  32   Tue Feb 11 13:20:01 2020 JanDetectorsBaF2 - HV settings with these HV values the 6 channels are roughly
gain matched, such that the 7.83 MeV Po-decay
is around channel 5000.
 BaF2_HV_settings.pngbaf_bg_ch1.png 
  85   Fri Mar 20 16:54:53 2020 JanDAQBaF OFF downscaled red=32 I introduced a downscaling by a factor of
2^5=32 for the BaF2 during target OFF.
The reason is, that we get a lot reasonable
  
  288   Wed Mar 31 13:52:04 2021 JanDetectorsBaF Na22 Testing2021On 30. and 31.03.2021 we did some testing
with the 6 BaF detectors.
  
  289   Wed Mar 31 13:57:27 2021 JanDetectorsBaF HV settings2021The setting below is a start value for final
gain matching with a full ADC range of 12MeV:
  
  290   Wed Apr 14 09:42:50 2021 JanDetectorsBaF HV gain matching2021The preliminary gain matching settings for
a full ADC range of ~12MeV:
 BaF_Na22_gain_match_v1.pngbaf_gain_match_v1.dat 
  521   Fri May 28 14:14:31 2021 LaszloGeneralAlvarez failure at 10:30 28:05:20212021    
  411   Sun May 23 15:36:10 2021 Rui-Jiu Chen& AlexGeneralAll shifts until Monday morning (24th May) have been cancelled. 2021All shifts until Monday morning (24th May)
have been cancelled. 
Next update on further situation (in particular
  
  188   Sun Mar 22 13:33:19 2020 LaszloGeneral2nd storage of MCP data I made a backup for the MCP data on my own
GSI laptop. Looking for better solution...
the original "fresh" files stored at litv-exp@lxg1299:/data.local2/hillenbrand/Laszlo/
  
  271   Mon Apr 6 04:39:19 2020 LaszloCalibration2. Xray energy calibration 30angle:  E[keV] = 0.015898 *ch-1.91
90angle:  E[keV] = 0.0211075*ch-2.39
145angle: E[keV] = 0.01663  *ch-1.758
 9x 
ELOG V3.1.5-fc6679b