  32   Fri May 7 04:39:00 2021 Liliana, Akash, Wolfram, Helmut, ShahabRunsData taking starts
File start being recorded at 4:38 am 
Sync with the server is working. 

Be aware that the timestamp of the files is 1h behind with respect to real time
  31   Fri May 7 04:26:54 2021 ShahabRuns245 MHz resonator extra 20dB gain off
made sure that the extra 20dB amplifier is off.
  30   Fri May 7 04:01:51 2021 ShahabRunsPicture after scraping
this picture is after scraping by helmut, showing the 410 MHz detector, that is we would expect an isomer where the marker M1 is, i.e. at 2.2kHz on the left side, which we unfortunately don’t see (yet).
  29   Fri May 7 03:51:56 2021 ShahabAnalysispeak frequencies
a reference schematic of the peaks on 410 MHz (211th harmonic) and 245 MHz (126th harmonic)
  28   Fri May 7 03:46:58 2021 Liliana, Akash, Wolfram, Helmut, ShahabGeneralScraper settings
Scraper settings have been played around with to try and remove satellite lines...

Helmut has now set scraper id GE01DS_H at -45mm (in position)

Image of injection structure attached... 72Ge is the isotope in focus on the RSA
  27   Fri May 7 03:44:55 2021 Helmut WeickAcceleratorscraper optimisation
Opened TE4 slits again to +/-10mm.

Then we tried different scrapers:
in south arc outside: E02DS3HG, cuts at ~ -25mm, at -15mm gone, leave at -35mm.

on straight section: EEXDS2HA cuts at ~ -25mm, leave at -25mm.

EEXDS1HA, closing it to -25mm revealed a double peak structure with distance just like the wanted isomer (-2.2MHz at h=211).
But it is present on all intense peaks at the same distance, so it must be an artefact of a strange isochronicity curve.
Closing it to -15mm even had only the smaller lower frequency line survive.
But then it must be also possible to have only the stronger line. leave at -25mm

This worked with scraper in north arc E01DS_H which can cut from both sides.
The insie can ve iused to cut the lower Brho, 
at -50mm still two peaks, at -45mm left peak almost gone, -40mm left peak gone but right still intense, leave at -40mm.

-> Lower Brho seems to be clearly related to lower frequency, higher Brho side is not so clearly related to frequency.

Measure in this setting, nice void at wanted frequency. But no isomers appear so far.
 
  26   Fri May 7 03:33:11 2021 Liliana, Akash, Wolfram, Helmut, ShahabGeneralstatus
At the moment we see a second peak to the left of each intense line. 
The distance between the main peak and the shadow is roughly the same for each peak.
This hints to a sharp fall in the isochronicity curve.
Helmut now tries to remove these shadows by using different scrappers. 
  25   Fri May 7 02:01:08 2021 Liliana, Akash, Wolfram, Helmut, ShahabAcceleratorBeam issues for short duration
RFQ fall-out (HKR working on it...)

Beam stop time: 01.58am

Beam resumption: 02.02am
  24   Fri May 7 01:49:03 2021 Rui-Jiu ChenDAQComparison of I_Raw/Q_Raw between different reference level
This is a comparison of I_Raw/Q_Raw between different reference level. The range of NTCAP ADC is only 2^15 bit. So signals (I_Raw and Q_Raw) should 
not be outside ADC range. It is clear that there is not point outside the ADC range when using reference level -30dBm.
  23   Fri May 7 01:47:36 2021 Ragan, Rui-JiuDAQChange reference level to -30dBm
Reference Level: -30 dBm.

Start taking data.
SC_2021-05-07_00-11-24
IQ_2021-05-07_00-11-24
  22   Fri May 7 01:44:24 2021 Rui-Jiu ChenDAQChange reference level to -40dBm
Reference Level: -40 dBm.

Start taking data.
SC_2021-05-07_00-06-57
IQ_2021-05-07_00-06-57
  21   Fri May 7 01:07:27 2021 Helmut WeickAnalysismaybe frequency ID
We think we see the frequency range of A/q=2.25 at 243.1 MHz.
This would correspond to L=108.2m and E=386.4 MeV/u (gamma_t = 1.3955) at h = 126.
Path length is a bit short, for L=108.4m it should be 370.6 MeV/u. 
(later reanalysis shows the measured frequency corresponds to 108.38m, which is like expected)

We closed scrapers on arc outside and straight section outside to limit Brho from both sides.
GE02DS3HG = -35mm, GEEXDS2AH = -25mm

Expected frequencies see below:
  20   Thu May 6 23:06:18 2021 Rui-Jiu ChenDAQChange reference level to -50dBm
Beam is secondary beam now. The intensity is lower. Change reference level to -50dBm.
Carrier frequency:245MHz
IQ rate(S/s): 20M.
Reference Level: -50 dBm.

Start taking data.
SC_2021-05-06_23_02_46
IQ_2021-05-06_23_02_33
  19   Thu May 6 22:05:30 2021 HelmutAcceleratorBeamline and ESR data sets for 72Ge setting
parammodi exports, E-SIS = 441.0 MeV/u with Be-1840 mg/cm² target in, isoc. ESR, at least we see fragments
  18   Thu May 6 21:45:30 2021 HelmutDetectorsbeam position on TE5 grids
The two grids do not work very well, one x position is opposite to the other.
But at least a guidance for the future, this was good injection of 78Kr with a thick Be target.
  17   Thu May 6 21:36:04 2021 Regina + Markus + YuriAcceleratorCooler Curve
Final cooler curve, Isochronous 78Kr
  16   Thu May 6 21:26:02 2021 Yuri et al.AcceleratorEnergies
gamma_t = 1.3955
Br(72Ge) corresponds to 6.79575 Tm
E (Kr) at Br(72Ge) = 392.9 MeV/u
ESIS = 467.45 MeV/u (pre-drilling, after 1.8 g/cm2 target)
ESIS = 440.98 MeV/u (final energy for 72Ge)

-during setup, a 20 mm offset in the TE line was observed. Beam centered via changing the Br of the beamline (~4 MeV/u up). Optimized pre-drilling transmission ~20% (with thick target)
  15   Thu May 6 18:21:42 2021 Ragan, Rui-JiuDAQNTCAP started again
NTCAP was stopped at 17:34 for the optimisation purpose.
NTCAP started again at 18:20 with the change in Reference Level (dBm): 0

SC_2021-05-06_18-20-05
\IQ_2021-05-06_18-20-05
  14   Thu May 6 17:48:48 2021 W. Korten, HelmutGeneralESR setting for 72Ge ions with primary beam
Setting the 78Kr (after the target) to the Brho of the 72Ge beam at 368.4 MeV/u (gamma=1.3955), i.e. 6.79575 Tm, which leads to an energy of 392.93 (of 78Kr). 
With the 10mm Be target the beam energy should then be 467.8 MeV/u .
Yes, with my slightly different target thickenss 467.5 MeV/u (Helmut).

For 72Ge at this Brho after the target it then needs 440.95 MeV/u.
LISE in proj. fragmentation option Morissey for projectile energy loss and ATIMA 1.4 with Be 1839 mg/cm^2).
  13   Thu May 6 17:02:49 2021 Ragan, Rui-JiuDAQScaler signals and parameters of NTCAP
At the moment, we record 7 signals in scaler channels and one Schottky signal (245 MHz resonance cavity) in the NTCAP with the attached information.