Entry  Wed May 11 03:17:14 2022, Patrick, Volker, Guy , Runs, Start laser scanning 
Runs of the night shift. The wavelength range is 601.95 - 601.735 nm.
We started the wavemeter python script on atppc023 located in Desktop/wavemeter_Bi.
We changed the wavelength range in go4 to the actual scan range.
Entry  Wed May 11 06:41:32 2022, Simon, Christopher, Shahab, Runs, shifts 
new shift started.
Entry  Wed May 11 06:47:58 2022, Simon, Christopher, Shahab, Runs, restart laser scan 

[TABLE border="1"]
Time | SIS-intensity | ESR-intensity after orbit change| cooler-HV | LMD-DAQ2 file nr | LMD-DAQ1 file nr | scan range(nm) | step width increment (nm) |
    Reply  Wed May 11 08:01:44 2022, Zoran, Runs, Start laser scanning 
[quote]
[I]Questions:[/I]
[B]There are many other masses/isotopes/etc. visible in the Shottky spectrum. Is this wanted?[/B]
Entry  Thu May 12 00:16:13 2022, Patrick, Volker, Guy, Rui-Jiu, Runs, Runs night shift 

[TABLE border="1"]
Time | SIS-intensity | ESR-intensity after orbit change| cooler-HV | LMD-DAQ2 file nr | LMD-DAQ1 file nr | scan range(nm) | step width increment (nm) |
Entry  Mon May 16 18:01:23 2022, mbsMax, Danyal, Wilfried, Rodolfo, Patrick, Kristian, David, Ruijiu , Runs, runs afternoon/night shift 16.05 
These are the runs after the septum was repaired on 16.05.

[TABLE border="1"]
Entry  Mon May 30 02:12:20 2022, Max, Patrick, ~Konstantin, Ragan, Ken, Runs, runs night shift 30.05. 2022-05-30_resonance_10_loops.png48_AM.png
These are the first runs of the substitute beamtime.

[TABLE border="1"]
Entry  Mon May 30 16:17:39 2022, Kristian, David, Wilfried, Carsten, Danyal, Rodolfo, Runs, Afternoon shift 30.05 
These are the first runs after changing to the thick stripper foil.

[TABLE border="1"]
Entry  Mon May 30 23:18:06 2022, Carsten, Rodolfo, Konstantin, Patrick, Ragan, Ken, Kristian, Max, Danyal, Runs, Runs shifts 31.05. 2022-05-31_particles.png
These are the first runs with 208Bi.

[TABLE border="1"]
Entry  Wed Jun 1 00:03:08 2022, Konstantin, Simon, Kristian, Runs, 209-Bi runs 
[TABLE border="1"]
Time | SIS-intensity | ESR-intensity after orbit change| cooler-HV | cooler current (mA) | LMD-DAQ2 file nr | LMD-DAQ1 file nr | scan range(nm) | step
width increment (nm) | dwell time(s) | n loops |comments
Entry  Fri Jul 30 10:21:27 2021, Rodolfo, Laser, Kink Laser_beamline_ESR_NordBogen.jpg
The laser beamline in the ESR north arc has a [B]knik[/B], therefore the laser beam can not get the "laser tower" in the north east arc. This path is used
to get the laser beam up to the electron-cooler side, such that the laser beam co-propagates the ion beam. 
Entry  Fri Apr 22 09:38:24 2022, Rodolfo, Laser, getting ready for Fluorescein548 
We are going to change dye. Therefore I have take out the DCM-dye-solution* out of the dye circulators, rinsed them with Ethanol (5 times) and put new filters.

* This was a solution of 0.3 g/l in 1:1 solvent mixture of Ethanol and DMSO. 
Entry  Mon Apr 25 18:47:12 2022, Rodolfo, Laser, New dye circulators Neue_Cobra-Farbstoffpumpe.jpg
I have put into operation the new circulators (SN. 182231, 182201) for our dye laser (the Cobra). I have rinsed them with pure Ethanol first and I have
not seen any leaks.
Entry  Mon Apr 25 21:47:28 2022, Rodolfo, Laser, green instead UV Libelle_Umtausch_GrüneOptik.jpgUmtausch_Spiegel_2statt3.jpg
I am exchanging the optical elements (mirrors and lenses) for the laser spectroscopy on bismuth. At some places I am also exchanging the 3"-mirror holders
and installing 2"-mirror holders instead.
Entry  Fri Apr 29 21:18:12 2022, Rodolfo & Max, Laser, Fluorescein 27, Rh 610 + Rh 640 
We (Max and Rodolfo) have tested the dyes. I have prepared the dye-solutions according to the recipes given in Sirah's User Manual. 

The seed energy for the Cobra was 520 mJ @ 532 nm. The output energy after the Cobra's main amplifier was:
Entry  Wed May 4 22:55:37 2022, Rodolfo, Sebastian, Laser, FCU / Temp Control Bug 
We found a "Bug" in the control of the Sirah dye system.

Due that we don't use the FCU and the temperature control unit we could not start the Sirah software without getting numerous errors. 
Entry  Wed May 4 22:56:22 2022, Rodolfo, Sebastian, Konstantin, Laser, Laser step complete, scan complete fixed 
"Laser step complete" and "laser scan complete" are working again.

Problems:
Entry  Thu May 5 15:24:34 2022, Sebastian, Laser, laser busy problem 
Current status: 
Laser busy signal works correctly (5V if the grating moves, 0V if not) if the laser is operated by the Sirah software.
Entry  Fri May 6 16:41:57 2022, Patrick, Rodolfo, Laser, Wavemeter Screenshot_(4).pngBi2022_laserscan_test.PNG
We coupled the laser through a multi-mode fiber into the wavemeter.
With the main amplifier enabled, we got enough power behind the fiber (0.5 - 1.5 mW) to use the wavemeter with 34 ms exposure time (1s / 30Hz to prevent
jumps in the wavemeter readout).
Entry  Mon May 9 13:48:20 2022, Rodolfo, Laser, Laser for H-like 209Bi 
I have changed the dye to Rhodamin 610 + Rhodamin 640. The Cobra wavelength can be tuned now from 600 to 630 nm.

The current wavelength is set to 605 nm.