Entry  Mon Mar 30 16:25:05 2020, ruijiu, Detectors, turn down the HV 
turn down the hv and pull out the detector.  

suggest by 
Entry  Mon Mar 30 20:51:06 2020, Ragan, Detectors, Bias Voltage for Si-pads Si_pad_bias-voltage.ods
The limit of the leakage current for all Si pads was increased from 1500 nA to 5000nA and 
leakage current was recorded for different Bias Voltages (32V, 35V, 40V, 45V, 50V, 55V 
and 60V).
Entry  Wed Apr 1 01:02:24 2020, ruijiu, Detectors, the detector cable is disconnected. 
 
Entry  Wed Apr 1 01:05:36 2020, ruijiu, Detectors, detector position fixed at 60 mm VID_20200401_010416.mp4
The detector cable was disconnected . We entered and reconnected the cable.
Entry  Thu Nov 19 09:14:40 2020, Jan, Detectors, remote MSCF settings for CsISiPHOS setting.1585477986det_mapping.png
Attached is a list of all set values for the 5 MSCF shaper modules.
This was done prior to run0251, which served as a final benchmark for those settings.
See: https://elog.gsi.de/esr/E121/62
Entry  Tue Dec 8 15:47:07 2020, Jan, Detectors, manual preamp & shaper settings for CsISiPhos amp_settings.pdf
attached is a document showing fotos of all involved amplifiers in the chain to document the manual settings active during the experiment.

Summary:
Entry  Mon Dec 3 15:06:04 2018, Chen, Sidhu, DAQ, Test of two preamplifier. 20181121_ElectronicCircuits_1.png20181121_ElectronicCircuits_2.png20181121_ElectronicCircuits_3.png20181121_ElectronicCircuits_4.png
[B]Description:[/B]
   We have two pre-amplifiers:
   New: Max. range 5GeV, Two sensitivity options: 1 GeV and 5 GeV,  Decay time = 30 us, pulse input 220 MeV/u, Ser. #MPR-32-D-5000-30-1118380.
Entry  Tue Mar 12 12:54:58 2019, Chen, Sidhu, DAQ, how to start DAQ and plot histogram. 000000000001_edit.png55_PM.pngdrawing-1.png
[B]1. login litv-exp account[/B]
rchen@lxg1254:/data.local2/2002_238UIMS$ ssh -X litv-exp@lxg0155.gsi.de
(don't login on lx-pool.)
Entry  Tue May 28 08:36:14 2019, Jan, DAQ, MBS start & RFIO server 
You need a DAQ-PC and the RIO crate computer.
All of the DAQ proceedures laid out here are operated from inside the DAQ screen session.
Right now for e121 the following DAQ-setup is used: (might change in the future)
Entry  Wed Jun 26 16:20:31 2019, Jan, DAQ, unpacker: lmd > root E121.specdet_mapping.hh
I have written an unpacker for the lmd data taken with the current daq-system for E121.
The crate configuration is as follows:
ADC1 channels 1-32 (Caen 785)
Entry  Tue Feb 25 15:48:31 2020, ruijiu chen, DAQ, Important folders of e121 eperiments: 
1. slow control:
1.1. program file:
litv-exp@ringpi:~/epics/mrcc_ioc/db $ 
Entry  Tue Feb 25 15:49:58 2020, ruijiu chen, DAQ, changing scaling factor. 
How to change scaling factor?
The parameters is in f_user.c file:
1. open the f_user.C with emacs :
Entry  Sat Mar 28 12:19:21 2020, Ragan, RuiJiu, DAQ, Change of the polarity of Amplifiers 7888530B-DE66-4D37-A0A8-933307DD2AB8.MOV
Since last night, the signals from the p-side of all the Si pads were seen as negative on picoscope.
The signals from DSSSD, all n-sides of Si pads and CsI were positive which all are in MSCF-5.
Thus, I and RuiJiu, changed the polarity jumpers of MSCF 1,2,3 and 4(all the four jumpers inside the mentioned MSCF) and now hope to see positive signals
Entry  Sat Mar 28 15:07:40 2020, ruijiu, DAQ, start run  
 
Entry  Sat Mar 28 16:12:25 2020, ruijiu, ragan, DAQ, enter ESR and turn on the HV crate. 
 
Entry  Sun Mar 29 09:40:35 2020, ruijiu, DAQ, restart go4 IMG_20200329_093354.jpg
go4 crush up. 
the problem is 
due to  mbs. 
Entry  Sun Mar 29 13:05:36 2020, ruijiu, DAQ, start ntcap IMG_20200329_130438.jpg
IQ_2020-03-29_13-05-
56
SC_2020-03-29_13-05-
Entry  Mon Mar 30 14:24:46 2020, ruijiu, DAQ, stop taking data. 
1. stop run0272.lmd.
2. stop NTCAP. 
  NTCAp file:
Entry  Thu Oct 1 22:20:03 2020, Jan, DAQ, final unpacker config E121.specdet_mapping.hh
We identified an issue with randomly missing adc channels in all lmd-files before run 0273.
This led to errors in the unpacking process. 
Entry  Mon Nov 2 16:45:55 2020, Jan, DAQ, f_user & mbslog f_user.cmbslog.l
Attached is the f_user.c and the mbslog.l files.
The readout function is for the following setup:
3x ADC CAEN V785 