Wed May 11 22:45:22 2022 |
Max, Wilfried, Patrick | General | scanning wavelength |
The scan parameters for the next shift are:
in COBRACONTROL:
increment: 0,005nm
from position: 601,62nm
to position: 601,405nm
These are the wavelengths in air!
The wavelength in vacuum we expect is: 601.832nm
You can check the current wavelength in vacuum on the wavemeter in the LabView GUI.
edit: In the night shift, we checked the scanned vacuum wavelengths in the wavemeter and also checked the expected transition wavelength.
The resonance should be very much in the center of the above mentioned scan range.
The increment corresponds to 4.1 GHz steps. Is this small enough? |
56
|
Thu May 12 10:21:30 2022 |
Ragan, Shahab, Simon, Sebastian, Christopher, Wilfried | General | No Beam |
There is no beam in the ESR due to some problem in the UNILAC. |
Attachment 1: Screenshot_from_2022-05-12_09-21-38.png
|
|
57
|
Thu May 12 11:30:18 2022 |
Ragan, Shahab, Simon, Sebastian, Christopher, Wilfried | General | Beam is back |
Beam is back in the ESR. |
Attachment 1: Screenshot_from_2022-05-12_10-32-24.png
|
|
58
|
Thu May 12 11:31:11 2022 |
Simon, Christopher, Shahab, Wilfried, Sebastian, Ragan | General | Runs morning shift |
Time | SIS-intensity | ESR-intensity after orbit change | cooler-HV | LMD-DAQ2 file nr | LMD-DAQ1 file nr | scan range(nm) | step width increment (nm) | dwell time(s) | n loops | comments
|
11:30 | - | 8,2e6 | 223219 | 497 - 500 | 8119 - 8119 | 601.62 - 601.405 | 0.005 | 5s | 6 | after this run we had to give the ESR Group the beam
|
|
|
59
|
Thu May 12 12:02:56 2022 |
Ragan, Shahab, Simon, Sebastian, Christopher, Wilfried | General | No beam |
There is no beam in the ESR again. |
Attachment 1: Screenshot_from_2022-05-12_11-02-37.png
|
|
60
|
Thu May 12 12:51:30 2022 |
Ragan, Shahab, Simon, Sebastian, Christopher, Wilfried | General | Beam is back |
12:50 Beam is back again in the ring.
12:52-until now Kicker problem in the ESR. |
Attachment 1: Screenshot_from_2022-05-12_11-51-35.png
|
|
Attachment 2: Screenshot_from_2022-05-12_12-08-52.png
|
|
68
|
Fri May 13 16:55:58 2022 |
Danyal, Carsten, Phillip, Wilfried | General | End of E128 Beamtime |
Dear all,
unfortunately, the E128 experiment must now come to an early end.
The problem(s) with the injection septum are severe and no work around solution (with acceptable risks) could be found.
Several things were tried, but without hope.
Many thanks to everybody involved during the preparation time and the shifts during the beamtime.
Best wishes,
Wilfried |
69
|
Mon May 16 14:20:05 2022 |
Ragan, Danyal, Carsten, Phillip, Wilfried et al. | General | E128 Beamtime |
> Dear all,
>
> unfortunately, the E128 experiment must now come to an early end.
> The problem(s) with the injection septum are severe and no work around solution (with acceptable risks) could be found.
> Several things were tried, but without hope.
>
> Many thanks to everybody involved during the preparation time and the shifts during the beamtime.
>
> Best wishes,
>
> Wilfried
There is beam again in the ESR. The plan is to take beam until tomorrow morning. |
72
|
Mon May 16 17:38:38 2022 |
Max, Danyal, Wilfried, Rodolfo | General | laser bunch timing |
We overlapped the laser and ion bunch in the time domain.
Therefore we delayed the bunching HF in order to see the PMT signal between bin 10 and 22. Before the signal Peak was in channel ~145-5 and difficult to gate on.
Afterwards we also have to shift the laser.
The new values are:
PD NO: 77.5
PD SO: 113
Ion bunch: 16.5 |
Attachment 1: timing1605.png
|
|
91
|
Mon May 30 19:00:19 2022 |
Carsten | General | Scraper Settings and Parameters for the last measrements with thick target |
old Bunch frequency: 1.98777 MHz
Positions PL devices:
GE01DD2AG | -23
|
GE01DD2IG | 3
|
GE02DD2_G | -35
|
GE02DS3HG | 0
|
The voltages of the particle detectors were set to:
SA_SZ: 1500V
NA_SZ: 750V
But for the primatry beam measurements the detectors were still switched off
Set values for cooler:
SC3: 223513.377 + DeltaU = 160V
SC6: 223452.14 + DeltaU = 130V
SC9: 223452.14 + DeltaU = 130V
Electron current:
SC3: 300mA
SC6: 100mA (300mA in the second file)
SC9: 100ma (300mA in the second file)
Cooling in SC4: 550x
Cooling in SC7: 50x
Explanation of subchains:
SC4: Cooling at injection orbit
SC5: Ramp to central orbit
SC7: Cooling at central orbit
SC8: Scrapers /particle detectors in, XUV detector in, (~10s), bunching on
SC9: measurement
SC10: not used
SC11: Scrapers/particle detectors/XUV ectros out (~10s), bunching off |
Attachment 1: screenshot-2022-05-30_19-12-151030168345517073342_(002).png
|
|
94
|
Mon May 30 21:52:08 2022 |
Wilfried, Danyal, David, Rodolfo | General | Position of T-Scrapers |
We have determined the position of the H-like 208Bi ion beam using the T-Scrapers. The position actually did not change in comparison to the position of H-like 209Bi.
Here we have the values where the beam was "gone"
device | move in dir. | gone (mm) | x0 (mm)
|
GECEDS1VU | up | 0.7 |
|
| | |
|
GECEDS1HA | right | -22 | -4.7
|
| left | -13.0 |
|
| | |
|
GECEDS2VU | up | 0.0 |
|
| | |
|
GECEDS2HA | right | -18.5 | 3.1
|
| left | -9.5 |
|
Below you can see a screenshot with the settings of the beam stabilization system. |
Attachment 1: MRC_208Bi_30-05-2022-10Uhr.png
|
|
98
|
Tue May 31 15:19:58 2022 |
Max, Carsten, Danyal | General | scans for different E-cool currents |
until 15:15 we have measured with I_e = 100 mA (3 loops per file)
E_cool HV = 225255 V
after that (at 15:26) we changed to I_e = 200 mA (2 loops per file)
E_cool HV = 225272 V
after that (at 17:15) we changed to I_e = 50 mA (first 4 then 6 loops per file)
E_cool HV = 225247 V |
99
|
Tue May 31 17:22:09 2022 |
Max, Carsten, Danyal, Rodolfo, Wilfried | General | change E-cooler current I_e = 50 mA |
At 17:15 we changed again the E-cooler current I_e = 50 mA
(4 laser scan loops per injection)
E-cool HV = 225248 V |
1
|
Fri Jul 30 10:21:27 2021 |
Rodolfo | Laser | Kink |
The laser beamline in the ESR north arc has a knik, therefore the laser beam can not get the "laser tower" in the north east arc. This path is used to get the laser beam up to the electron-cooler side, such that the laser beam co-propagates the ion beam.
In order to try fix this, Markus suggested to get in contact with Herr Kredel (Groß Montage). He will be back from holidays on August 11th (2021). |
Attachment 1: Laser_beamline_ESR_NordBogen.jpg
|
|
2
|
Fri Apr 22 09:38:24 2022 |
Rodolfo | Laser | getting ready for Fluorescein548 |
We are going to change dye. Therefore I have take out the DCM-dye-solution* out of the dye circulators, rinsed them with Ethanol (5 times) and put new filters.
* This was a solution of 0.3 g/l in 1:1 solvent mixture of Ethanol and DMSO. |
3
|
Mon Apr 25 18:47:12 2022 |
Rodolfo | Laser | New dye circulators |
I have put into operation the new circulators (SN. 182231, 182201) for our dye laser (the Cobra). I have rinsed them with pure Ethanol first and I have not seen any leaks.
The idea is to use these circulators with either Pyrromethene 597 or a combination of (Rhodamin B + Rhodamin 101).
The "old circulators" (SN. 104830, 104801) will be used together with (Fluorescein 27 + NaOH). |
Attachment 1: Neue_Cobra-Farbstoffpumpe.jpg
|
|
4
|
Mon Apr 25 21:47:28 2022 |
Rodolfo | Laser | green instead UV |
I am exchanging the optical elements (mirrors and lenses) for the laser spectroscopy on bismuth. At some places I am also exchanging the 3"-mirror holders and installing 2"-mirror holders instead.
* Just in case. The "nice" laser profile comes from a laser pointer from Thorlabs (CPS532). The Cobra is still under construction. |
Attachment 1: Libelle_Umtausch_GrüneOptik.jpg
|
|
Attachment 2: Umtausch_Spiegel_2statt3.jpg
|
|
7
|
Fri Apr 29 21:18:12 2022 |
Rodolfo & Max | Laser | Fluorescein 27, Rh 610 + Rh 640 |
We (Max and Rodolfo) have tested the dyes. I have prepared the dye-solutions according to the recipes given in Sirah's User Manual.
The seed energy for the Cobra was 520 mJ @ 532 nm. The output energy after the Cobra's main amplifier was:
Fluorescein 27 (to be used for 208Bi):
Wavelength [nm] | Energy [mJ]
|
545 | 58
|
548 | 64
|
550 | 62
|
555 | 58
|
560 | 51
|
Rhodamin 610 + Rhodamin 640 (potential candidate to be used for 209Bi):
Wavelength [nm] | Energy [mJ]
|
600 | 65
|
605 | 98
|
610 | 104
|
615 | 103
|
620 | 97
|
625 | 82
|
* All values averaged over 500 laser pulses. |
9
|
Wed May 4 22:55:37 2022 |
Rodolfo, Sebastian | Laser | FCU / Temp Control Bug |
We found a "Bug" in the control of the Sirah dye system.
Due that we don't use the FCU and the temperature control unit we could not start the Sirah software without getting numerous errors.
The fix was to plug in the BBO oven again, move the FCU to "origin", than move to a specific location that the FCU goes in an "idle" mode.
Than the Sirah software can be started again without getting erros. |
10
|
Wed May 4 22:56:22 2022 |
Rodolfo, Sebastian, Konstantin | Laser | Laser step complete, scan complete fixed |
"Laser step complete" and "laser scan complete" are working again.
Problems:
1) Connections were wrong in the Software.
2) Sometimes the connection to "laser scan complete" was lost (Wackelkontakt).
3) The VI was initialized with the wrong LabJack Channels.
Now:
1) fixed connections in the software.
2) switch to an other "channel" of the LabJack device for "laser scan complete".
3) The channels in the Cobra VI are for...
laser scan complete -> Channel 5
laser step complete -> 6
We definetely should keep an eye and check frequently the signals, that we do not have a lost connection (Wackelkontakt) again of these 2 channels. |