  Draft   Fri Jun 27 14:23:39 2025 Nils, Wilfried, JulianRunsRuns afternoon shift 27.06.15:30 We have a break due to an issue at UNILAC
(quadrupole failed). Also radiation safety
interlock was triggered at the fragment separator.
  
  67   Fri Jun 27 11:21:25 2025 Esther, KonstantinDAQTimingWe cross-checked the timing. Laser pulse is
detected at bins 136 (PD-North) and 171 (PD-south),
respectively. Therefore, the laser puls is
  
  66   Fri Jun 27 06:55:45 2025 Esther. KonstantinLaserLaser-ion overlapWe cross-checked the laser-ion superposition
by using the T-scrapers. We did it only after
the scans in order to do not change the duty
 2025-06-27_06-52-01-807.png2025-06-27_07-12-27-135.png2025-06-27_07-32-28-599.png2025-06-27_07-51-52-620.png 
  Draft   Fri Jun 27 06:13:02 2025 Esther, KonstantinRunsEarly shift - data taking[B]Notes:[/B] 
1. TE slits at -10 and +10
2. SIS intensity unstable until about 9:00
  
  64   Thu Jun 26 22:51:04 2025 Hendrik, FinnRunsNightshift data runsAfter the scan at 22:04 teh FCU new was new
calibrated. For this MEdusa was stopped and
reopened in the laser lab. This stops the
  
  63   Thu Jun 26 21:27:34 2025 Carsten, Jan, SimonCalibrationTimingWe checked the timing (before the start of
the measurement cycle documented below).
Timing and measurement window are attached.
 Bildschirmfoto_timing_new_2025-06-26_19-00-04.png 
  62   Thu Jun 26 19:01:46 2025 Carsten, Jan, SimonRunsLate shift 26.06.
[B] Scan parameters:[/B]
[TABLE border="1"]
  
  61   Thu Jun 26 18:13:17 2025 Jan, CarstenDetectorsPMT voltages & thresholdscurrent settings of PMT voltages and thresholds
at the CAEN CFD:
  
  60   Wed Jun 25 05:53:54 2025 RodolfoLaserFCUCobra's FCU was recalibrated. Table saved
as FCU_547-554_RS_2024-06-25.fcu.
  
  59   Tue Jun 24 22:24:36 2025 Carsten, Finn, Hiroshi, Esther, RodolfoRunsData taking (night shift 24.06.)
[B] Scan parameters:[/B]
[TABLE border="1"]
  
  58   Tue Jun 24 18:49:18 2025 Carsten, Rima, Nils, SimonRunsSecond attempt (Late shift 24.06.)
[B] Scan parameters:[/B]
[TABLE border="1"]
  
  57   Tue Jun 24 17:39:13 2025 Carsten, Stefan, Simon, Rima, NilsDetectorsPMT behaviour - noise / PMT voltages / CFD Threshholds / CAEN Power supply (broken channel resetted)PMT North and South have been changed:

CFD CH0: Middle Thr 7 / CAEN HV Ch1: 2750
  
  56   Tue Jun 24 15:44:06 2025 KonstantinDAQPhase shift in DAQ1In the SetParameters.C file is a parameter
called fPar->piPhaseOffset. It was shifted
from 100 to 50 in order to see ion bunches
  
  55   Tue Jun 24 12:25:34 2025 CarstenDetectorsPMT behaviour - noise / PMT voltages / CFD Threshholds / CAEN Power supply (broken channel resetted)In position North there is still the "old"
9423B PMT that draws quite some current.
On this detector threre is also some quite
  
  54   Mon Jun 23 18:36:39 2025 Wilfried, SimonDetectorsPMT test with LEDWe tested the PMTs again, this time with an
UV LED that is mounted at a window close
to the XUV detector.
  
  53   Mon Jun 23 10:59:36 2025 Julian, Lukas, Zsolt, Nadine, KonstantinRunsScan routine-Start new injection
  ->wait for 60 injections to be complete
  ->note down SIS intensity (at extraction)
  
  51   Mon Jun 23 10:52:34 2025 Julian, Lukas, Zsolt, Nadine, KonstantinLaserFrequency conversion unitWe exchanged the old BBO of the Cobra's FCU
with a new one. The output power of the Cobra
was around 120mJ. In the end, we achieved
  
  50   Mon Jun 23 01:01:17 2025 CarstenDetectorsCAEN PMT Power supplySince yesterday, channel 0 of the CAEN PS
is dead (no voltage even without cable).
Changed detector south to channel 3.
  
  Draft   Sun Jun 22 23:48:35 2025 CarstenAcceleratorSummary of todays settings and tests Scraping, beam intesnity optimizations and
nuching were set up and optimized during
the day.
  
  47   Sun Jun 22 22:29:04 2025 CarstenAcceleratorBackup copy of present accelerator settings - don't use if you don't know what you are doing# Version: 1.3
# Comment: ParamModi Export at 2025-06-22T22:28:05.633712878+02:00[Europe/Berlin]
# Context: ESR_25_12_THORIUM_20June_v3.C1
  
  46   Sun Jun 22 21:36:48 2025 Carsten, Finn, Zac, EstherRunsFirst laser scans
[B] Scan parameters:[/B]
[TABLE border="1"]
  
  45   Sun Jun 22 18:47:23 2025 Carsten, Peter, Marek, SimonDAQPMT and particle detector settingsFinal voltages and thresholds for the PMTs
and particle detectors before the first scan:
  
  Draft   Sun Jun 22 11:31:59 2025 Arya, Carsten, Julien, KonstantinGeneralSummary morning shift1. UNILAC running again, so we resumed the
beam tuning wherre we stopped yesterday at
14:00
  
  43   Sat Jun 21 22:33:04 2025 Peter , DanyalDetectorsPMTs are switched offWe have switched off all 3 PMTs  !   
  42   Sat Jun 21 21:55:18 2025 Peter, Danyal, MarekDetectorsPMT ratesWe have made two foam rings (outer diameter
ca. 70 mm with a thickness of 10 mm each
and placed them successively underneath PMT
 no_rings_under_PMT_north.png2_rings_under_PMT_north.png 
  41   Sat Jun 21 18:00:49 2025 Carsten, Peter, Danyal, Kristian, Marek DetectorsPMT signalsCarsten and Kristian changed (18:00) the thresholds
of PMT north and PMT middle in the ESR cave.
 Panel4.gif 
  40   Sat Jun 21 17:00:10 2025 Carsten, Peter, Danyal, Kristian, MarekDetectorsPMT north exchangedWe noted that the dark countrate of PMT north
is about 20x higher than that of PMT middle.
 Panel4.pngPanel4.jpg 
  39   Sat Jun 21 11:42:50 2025 Arya, Julien, WilfriedGeneralTest laser scanTest scan to see whether laser spot is moving
while scanning
  
  38   Sat Jun 21 08:48:16 2025 Arya, Julien, WilfriedAcceleratorLow 229Th particle numbers and 229Th lifetime in ringWith reference to entry 37 Laser timing:

- at last 30 injections accumulation: 10k
 Bildschirmfoto_timing_full_2025-06-21_09-30-46.pngBildschirmfoto_timing_end_of_manipulation_2025-06-21_09-36-24.pngBildschirmfoto_timing_full_60_2025-06-21_11-25-51.pngBildschirmfoto_PDSouth_lifetimes_2025-06-21_11-26-43.png 
  37   Sat Jun 21 07:28:35 2025 Arya, Julien, WilfriedLaserLaser TimingWe roughly adjusted the timing based on attachment
1, for ions to be in center of electron cooler
(east arc), corrected for PMTs being 2.5m
 Bildschirmfoto_IonBunch_PDs_2025-06-21.pngBildschirmfoto_rough_timing_2025-06-21_07-22-59.pngBildschirmfoto_timingcorrected_2025-06-21_08-21-53.pngBildschirmfoto_timing_final_2025-06-21_08-46-18.png 
  36   Sat Jun 21 03:13:02 2025 Alex, Anton, Rodolfo, HiroshiDetectorsPart Det SouthBunch signal on Particle Detector South. On
the 
 Bildschirmfoto_PartDetSouth_2025-06-21.png 
  35   Sat Jun 21 03:06:19 2025 Rodolfo, Alex, Hiroshi, AntonLaserbeam overlap with t-scrapers[TABLE border="1"]
motor|ion beam position (mm) from outside|ion
beam position (mm) from inside
 2025-06-21_05-14-39-706.png2025-06-21_05-22-21-447.png2025-06-21_05-27-59-895.png2025-06-21_05-31-37-019.pngMRC-settings_Th-Beam_2025-06-21.JPG 
  34   Sat Jun 21 02:32:24 2025 Alex, Anton, Rodolfo, Hiroshi, CarstenLaserLaser scanning settingThis is the initial scanning range
[LIST]
[*] 3 Loops
  
  33   Sat Jun 21 01:40:31 2025 Carsten, Alex, Anton, Rodolfo, HiroshiAcceleratorbeam parametersThe revolution frequency for the measurement
condition is: 1.542728 MHz.
The electron cooler voltage is: 104411 V.
  
  32   Sat Jun 21 00:52:07 2025 CarstenAcceleratorSummary of the last days (bunches wiht several isotopes still in ) / frequency of the Initially, we has very low SIS beam intensities
in the 1e8 region. Setting up ESR wiht Stacking
etc. turned out to be extremly tedious for
  
  31   Sat Jun 21 00:23:22 2025 RodolfoLaserDyeI have prepared new (fresh) dye solutions
of Fluorescein 27: 2 charges. They are in
the Safety Cabinet (Sicherheitsschrank) in
 Farbstoff_FL27.jpg 
  30   Fri Jun 20 15:58:21 2025 Wilfried, Konstantin, SimonLaserLaser stepwidthFrom previous Bi-Beamtimes, we expect the
width of the transition to be >50GHz (FWHM).
The current step width is 0.002nm which corresponds
  
  29   Fri Jun 20 11:25:32 2025 Julien, Kristian, KonstantinLaserAutomated laser scans In contrast to entry [URL=https://elog.gsi.de/esr/E0052_2025/12]E12[/URL],
the cabling for the automated start of the
laser scan is now connected to [B]IO3 of
  
  28   Fri Jun 20 06:37:51 2025 KonstantinAcceleratorPosition of contaminantsI checked the positions of the contaminants.
Therefore, I drove the scrapers and observed
the signal at the Schottky detector
  
  27   Wed Jun 18 20:24:01 2025 Carsten, Shahab, Ragandeep, Danyal et al. (the dayshift) and ESR crewAccelerator229Th89+ identificationWe believe to have identified the 237U92+
and the 229Th89+ peaks. 
 245_MHz_Schottky_229Th89.jpg 
  26   Wed Jun 18 19:05:28 2025 Carlo, Zac, Shahab, RaganAnalysisPID with rionidFor PID with rionid we used: 
- LISE file from last year (attached.
- .npz file from 410 RSA (attached).
 Schermata_2025-06-18_alle_19.03.04.pngE142_TEline-ESR_229Th.lppRSA01-2025.06.18.18.06.02.162.tiq_spectrum.npzSchermata_2025-06-18_alle_19.32.53.png 
  25   Wed Jun 18 14:01:40 2025 Julien, Konstantin, Stefan, Rima Ion bunch on PMTsApparentlty did not work yesterday evening
(no signal), but looks fine now (see attachment)
 Bildschirmfoto_bunch_on_PMT_2025-06-18_14-11-44.png 
  24   Wed Jun 18 11:44:15 2025 Julien, Konstantin, Stefan, Rima Jitter CFDPulses on photodiodes in entry 20 

1. seem wide, so we also looked at qswitch
  
  23   Wed Jun 18 08:07:17 2025 Julien, KonstantinLasernew FCU CalibrationUV power was not stable but dropping from
~18 mW to 13 mW after opening COBRA shutters.
New calibration of frequency conversion unit:
 2025_06_18_FCU_Cal_Table.JPG2025_06_18_FCU_Cal_Plot.JPG 
  22   Wed Jun 18 07:59:00 2025 Julien, KonstantinLaserPhase-offsetWe recognized that the output power of the
pump laser was instable when externally triggered
with 200kHz (stand-bye frequency of ESR).
 IMG_3889.jpgIMG_3888.jpgIMG_3891.jpgIMG_3892.jpg 
  21   Wed Jun 18 03:12:25 2025 RodolfoLaserBeam StabilizationThe laser beam pointing has changed, even
thought the MRC settings are the same as
given in Entry 5 (this elog). This could
 MRC-Settings_2025_06-18.JPG 
  20   Wed Jun 18 01:58:02 2025 Esther, Alexis, Anton, Rodolfo, CarstenAcceleratorNo Bunched BeamThe Bunching is not set properly. We do not
see the ion bunch with the Photomultiplier.
 Bildschirmfoto_PD_PMTSouth_2025-06-18_1.png 
  19   Wed Jun 18 00:56:28 2025 Carsten, Rodolfo, Anton, Alexis, Esther beam overlap with t-scrapersWhen testing the overlap between laser and
ion beam we observed the following positions:
  
  18   Wed Jun 18 00:33:56 2025 Esther, Alexis, Anton, Rodolfo, CarstenDAQR4l-41We have some issues with the RIO computer
R4l-41 (DAQ1). We had to switch off completely
twice. Only then it reacted properly. Maybe
  
  17   Tue Jun 17 19:25:30 2025 RodolfoAcceleratorT-Scrapers in E-CoolerHere are the instructions to drive the T-Scrapers
inside the ESR Electron Cooler
 Scrapereinstellung_am_E-Kühler.pdf 
  16   Tue Jun 17 16:33:16 2025 Carsten, SimonDAQGate Q-swtichThe gate generator of the Q-switch signal
for the Vuprom TDC was set to 10ms.
  
  15   Tue Jun 17 09:32:00 2025 KonstantinDAQMeda data acquisitionThe metadata provided by Medusa (Labview channels
in former times) are now labelled correctly
in Go4. 
 Bildschirmfoto_2025-06-17_11-23-40.png 
  14   Mon Jun 16 22:27:01 2025 Carsten, SimonDAQThresholds We also adjusted the thresholds for the mesytic.
Doing that, we noticed that one of the trafos
is broken (5th row, middle).
  
  13   Mon Jun 16 21:47:23 2025 Carsten, Wilfried, Simon DetectorsNew threshold values for PMTsWe adjusted the thresholds for the PMTs and
increased the voltage of PMT middle to 2.7kV
  
  12   Mon Jun 16 07:26:01 2025 KonstantinDAQStartup of Medusa and DAQ1The laser control software (Medusa) is hosted
on the Windows PC ATPPC023. First connect
via the command
 MedusaStartup.JPGMedusa.png 
  11   Fri Jun 13 18:14:02 2025 Konstantin, CarstenDAQDAQ FolderDryrun of DAQs. Folders of the data are:

  
  10   Thu Jun 12 16:27:45 2025 CarstenDAQNTCAP directoryOn the NTCAP the directory is changed to 
Q:/E0052
  
  9   Thu Jun 12 15:53:13 2025 CarstenDAQdata directory and backup disk (WDBook2 RAID)The data of DAQ1 are stored in the following
directory and with the following filenames
  
  8   Wed Jun 11 17:33:04 2025 Carsten, JanDAQDAQ2 - new computer , new directories (lxg0155 doesn't work reliably)LXG0155 (used in form er beamtimes) crashes
and hangs and hangs eventually. 
  
  7   Wed Jun 11 16:44:39 2025 Carsten, JanDetectorsDetector voltages and thresholds for DAQ2 (Mesycontrol)Voltages (2650v) for the small band 9423 is
ok. Signals are nicely separated from background,
thresholds can be easily set.
 Mesytec_CFD_Settings_2025-06-11_17-17-33.png 
  6   Wed Jun 11 11:20:23 2025 Konstantin, SimonDAQoctal gate generator delaysWe checked the set delays of the OG 8000 octal
gate generator and compared them with the
values measured before the Bi-beamtime (see
  
  5   Fri Jun 6 14:27:10 2025 Rodolfo, KonstantinLaserMRC Beam Stabilization PresettingsThese are the settings for the Beam Stabilization
from MRC. 
 MRC-Settings_2025_06-06.JPGAFG_Settings_Thorium_2025-06-06.jpgMRC-Controller_Settings_Thorium_2025-06-06.jpg 
  4   Wed Jun 4 16:18:57 2025 Rodolfo, SimonDetectorsPMT dark count ratesI adjusted the offsets of the amplifiers in
the cave and measured the dark count rates
  
  3   Wed Jun 4 16:17:47 2025 SimonDetectorsNitrogenThe nitrogen supply for the PMTs is turned
[B]ON[/B].
  
  2   Mon Jun 2 16:36:57 2025 CarstenDetectorsMesycontrolssh -Y litv-exp@x86l-204
'mesycontrol'
 MSCF16-F-V.pdf 
  1   Tue May 20 16:14:30 2025 Rodolfo, SimonDetectorsPMT arrangement at ESRThis is the arrangement of the photomultipiers
at the optical detection region at ESR for
Thorium 2025
 PMT_Arrangement_2025-05-20.jpg 