Mon Sep 30 11:04:15 2019, Cristina, leak check, Cryo collimator 11-1-18-8, , , , 24.09.2019, DONE, Accepted, 25.09.2019, Customised, 25.09.2019, Accepted, 26.09.2019, L. Bozyk
|
Mon Sep 30 11:11:26 2019, Cristina, test with bakeout, Laser chamber -Winters, Beginning 2019, Delayed, , 16.08.2019, DONE, Accepted, 30.08.2019, Customised, 12.02.2020, Accepted, KW10, D.Winters
|
Mon Sep 30 11:15:47 2019, Cristina , test with bakeout, Detector Recoil chamber ESR, , , , 2.09.2019, DONE, Accepted, 9.09.2019, Customised, 29.10.2019, Cond. Accep., 1.11.19, Hillenbrand
|
Mon Sep 30 14:00:51 2019, Cristina, pumping speed, 800 l/s Agilent, , , , 20.09.2019, DONE, Accepted, 1Test:7.10.2019; 2Test: 14.11.2019, Fischer-Mommsen, 1.11.19, Cond. Accep., , Sent back to Agilent
|
Mon Sep 30 14:04:43 2019, Cristina, pumping speed, Combi pump DN40, , , , 09.08.2019, DONE, Accepted, 20.08.2019, Fischer-Mommsen, 20.09.2019, Accepted, , Sent back to Agilent
|
Mon Sep 30 14:06:07 2019, Cristina, pumping speed, Slim SIP 150, , , , 9.08.2019, DONE, Accepted, 07.02.2020, Fischer-Mommsen, 06.03.2020, Accepted, ,
|
Wed Oct 9 07:55:47 2019, Phe, leak check, All metal gate valve (Bender), , , , 08.10.2019, DONE, Accepted, 21.10.2019, Customised, 24.10.2019, Accepted, 24.10.2019, M.Bender
|
Wed Oct 9 07:57:44 2019, Phe, test with bakeout, Cryring Detector Tube , , , , 09.10.2019, DONE, Accepted, 10.10.2019, Setup 1, 22.10.2019, Accepted, 24.10.2019, Spillmann
|
Wed Oct 9 08:01:51 2019, Phe, test with bakeout, Macor Samples from Tino Giacomini, , , , 02.10.2019, DONE, Accepted, 10.10.2019, Mobile 2, 6.11.19, Accepted, 8.11.19, Giacomini
|
Wed Oct 9 14:19:09 2019, Phe, test with bakeout, Scrapper for ESR (for Markus Steck), , , , 09.10.2019, DONE, Accepted, 14.10.2019, Setup 2, 18.10.2019, Accepted, 24.10.2019, Schwarz
|
Mon Oct 14 10:08:14 2019, Cristina, leak check, Dipole chamber SIS100 First charge, , , , 10.10.2019, DONE, Accepted, 11.10.2019, Customised, 29.11.2019, Accepted, , Stored in the TH
|
Mon Oct 14 10:09:36 2019, Cristina, leak check, Roughing CWT 3 charge, , , , 10.10.2019, DONE, Accepted, 14.10.2019, Customised, 14.11.19, Accepted, , Stored in Weiterstadt
|
Wed Oct 16 08:24:29 2019, Toni, leak check, Kryokollimator , June 2019, Delayed, August, from September 2019, DONE, Not Needed, 02.09.2019, Customised, 09.12.2020, Accepted, ,
|
Mon Oct 21 10:24:59 2019, Cristina, Other, Tube Heidelberg, , , , 17.10.2019, DONE, Accepted, First Test: 24.10.2019; Second Test:30.01.20 , Horizontal Coating Setup, 29.10.2019: Refused; Second Test: 05.02.2020, Accepted, 11.02.2020, C.Schröter
|
Thu Oct 24 14:55:28 2019, Toni, , , , , , , , , , , , , ,
|
Thu Oct 24 14:58:25 2019, Toni, , , , , , , , , , , , , ,
|
Fri Nov 1 10:41:45 2019, Cristina, test with bakeout, IPM Chamber, , , , 4.09.2019, DONE, Refused, , , , Refused, 1.11.19, Angelo
|
Fri Nov 8 10:52:43 2019, Cristina, test with bakeout, Macor 2 for IPM, , , , 8.11.19, DONE, Accepted, 11.11.2019, Mobile 2, 18.11.2019, Accepted, 04.12.19, T. Giacomini
|
Mon Nov 11 08:06:09 2019, Phe, test without bakeout, Ref. Chamber for Beam Diagnostic Manipulator (Hackhalle), , , , unknown, DONE, Accepted, 11.11.2019; 10:15 am, stopped 12.11.2019, Customised, , Refused, ,
|
Thu Nov 14 14:00:28 2019, Phe, test without bakeout, Ref. Chamber for Beam Diagnostic Manipulator, , , , unknown, DONE, Accepted, 14.11.2019; 10:30 am, Customised, 22.11.2019, Cond. Accep., N/A, N/A
|
Fri Nov 22 11:07:36 2019, Phe, test without bakeout, Beam Diagnostic Chambers from India for HEBT - small one, , , , unknown, DONE, Refused, 09.01.2020, Customised, 10.01.2020 - still pumping, Accepted, 15.01.20, Mahr Rainer
|
Fri Nov 22 11:08:19 2019, Phe, test with bakeout, SEM-Monitor for Beam Diagnostic SIS18, , , , 02.12.2019, DONE, Accepted, 03.12.2019, Setup 2, 13.12.2019, Cond. Accep., 06.01.2020, Fiedler, Sebastian
|
Fri Nov 22 11:09:19 2019, Phe, test with bakeout, Grid for Beam Diagnostic SIS18, , , , 02.12.2019, DONE, Accepted, 03.12.2019, Setup 1, 13.12.2019, Cond. Accep., 06.01.2020, Fiedler, Sebastian
|
Fri Nov 22 11:09:59 2019, Phe, Other, Septum SIS100 - NEG coated chamber, End 2019, Delayed, , unknown, TO COME, , , , , , ,
|
Fri Nov 22 11:10:33 2019, Phe, test with bakeout, Dipole Chambers for SIS100 (2box), 25.11.19, Delayed, Unknown, 17.01.20, DONE, Accepted, 12.02.2020, , End februar, Accepted, ,
|
Fri Nov 22 11:11:00 2019, Phe, test with bakeout, Quad Chambers for SIS100, , , , unknown, TO COME, , , , , , ,
|
Fri Nov 22 11:11:24 2019, Phe, leak check, 4th batch of roughing CWT for SIS100, , , , 06.01.20, DONE, Accepted, 10.02.2020, Customised, 13.03.20, Accepted, , Stored in Weiterstadt
|
Fri Nov 22 11:11:56 2019, Phe, test with bakeout, 'Spill-Cavitaet" ???, August 2019, Delayed, KW26, , TO COME, , , , , , ,
|
Thu Nov 28 11:09:29 2019, Cristina, test with bakeout, Reference chamber for Grid for beam diagnostic SIS18, , , , 06.01.2020, DONE, Not Needed, 09.01.2020; , Setup 1, 19.01.20, Accepted, ----------, ----------
|
Thu Nov 28 11:11:16 2019, Cristina, test with bakeout, Reference chamber for Monitor for beam diagnostic, , , , 09.01.2020, on-going, Not Needed, 08.01.2020; 09:05 am; repeat due to leak - 13.01.2019, 07:00 am, Setup 2, , , ,
|
Mon Dec 2 14:28:58 2019, Cristina, General, TS1MU1-test with magnet, August 2019 delayed to KW6 2020, Delayed, Unkwon, N/A, DONE, Accepted, 04.03.2020, Customised, , Accepted, , Grossmontage
|
Wed Dec 4 10:08:42 2019, Cristina, test with bakeout, Macor 3 charge, , , , 04.12.19, DONE, Accepted, 11.02.2020, Customised, 20.03.2020, Cond. Accep., 23.03.2020, T. Giacomini
|
Thu Dec 12 09:20:54 2019, Cristina, test with bakeout, IPM SIS100-Giacomini, Jannuary 2020, Delayed, Unknown, 21.04.2020, DONE, Not Needed, 04.05.2020, Customised, 15.05.2020, Accepted, Mai/Juni, Brough to the TH
|
Thu Dec 12 09:22:19 2019, Cristina, test without bakeout, Palmer PU Tank- Dimopoulou, January 2020, on schedule, January 2020, January 2020, DONE, Accepted, 28.01.20, Customised, 31.01.20, Accepted, 03.02.20, Grossmontage
|
Thu Dec 12 10:19:06 2019, Cristina, test with bakeout, Pumping chamber SIS100 -Stefan, End 2019, Delayed, Beginning2020, 10.12.19, DONE, Accepted, January, Customised, 05.02.2020, Accepted, , Stored in the TH
|
Fri Dec 13 09:03:27 2019, Christian, leak check, Fasersonde Unilac, , , , 12.12.19, DONE, Accepted, 12.12.19, Customised, 16.12.19, Refused, 16.12.19, Sthraldiagnose
|
Mon Dec 16 15:27:50 2019, Phe, test without bakeout, Beam Diagnostic from Inida - big one, , , , 13.13.2019 , DONE, Refused, 15.01.20, Customised, 19.01.20, Accepted, 24.01.201, M.Müller
|
Tue Dec 17 13:39:20 2019, Phe, leak check, Fasersonde Unilac -2 test, , , , 17.12.2019, DONE, Not Needed, 17.12.2019, Customised, 17.12.2019, Accepted, 20.12.2019, Beam diagnostic
|
Wed Dec 18 11:27:54 2019, Phe, leak check, Transistion tube for SIS100 string test, Beginning 2020, Delayed, February, 06.02.2020, DONE, Refused, , , , Refused, ,
|
Thu Jan 16 09:05:12 2020, Cristina, test without bakeout, BPM SIS100- 2010-3, 27.01.20, Delayed, 30.01.20, 30.01.20, DONE, Accepted, 03.02.2020, Customised, 05.02.2020, Refused, 10.02.2020, M.Müller
|
Mon Jan 20 10:40:00 2020, Cristina, test with bakeout, Ceramic Tube Diagnostic-Dorn 06-004-01376-3, KW4, On schedule, KW4, 20.01.20, DONE, Accepted, 21.01.2020, Setup 1, 27.01.20, Accepted, 29.01.20, M.Müller
|
Thu Feb 6 10:33:17 2020, Cristina, test without bakeout, BPM 2010-17 (keept in the new cryostat), KW7, On schedule, KW7, 10.02.2020, DONE, Accepted, 12.02.2020, Mobile 3, 14.02.2020, Refused, 18.02.2020, M.Müller
|
Thu Feb 6 10:34:00 2020, Cristina, test without bakeout, BPM 2010-15 (from the Company), KW8, On schedule, KW8, 18.02.2020, DONE, Refused, 19.02.2020, Mobile 3, 21.02.2020, Cond. Accep., 25.02.2020, M.Müller
|
Thu Feb 6 10:34:25 2020, Cristina, test without bakeout, BPM 2010-16 (keep in the old cryostat), KW9, On schedule, KW9, 26.02.2020, DONE, Refused, 26.02.2020, Mobile 3, 28.02.2020, Cond. Accep., 27.02.2020, Müller
|
Thu Feb 6 11:11:21 2020, Cristina, General, In kind contribution Sweden -Niko, March 2020, On schedule, , , , , , , , , ,
|
Thu Feb 6 12:45:52 2020, Cristina, test without bakeout, Protoype BV CWT, March, On schedule, , 26.08.20, DONE, Not Needed, 14.09.20, Customised, 21.09.20, Accepted, 22.09.20, S. Wilfert
|
Thu Feb 6 12:47:18 2020, Cristina, leak check, Interconnction bellows between Dipole and Quadrupole, October , On schedule, , 3.11.20, DONE, Accepted, 04.11.20, Customised, 04.11.20, Refused, 04.11.20, in Büro of S.Wilfert
|
Thu Feb 6 12:48:46 2020, Cristina, leak check, 30 SIS 100 pumping chambers, May 20, Delayed, December 20, , , , , , , , ,
|
Tue Feb 11 09:53:14 2020, Cristina, leak check, SIS100 Sextupole (6), September 2020, Delayed, , , , , , , , , ,
|
Tue Feb 11 09:54:49 2020, Cristina, test with bakeout, SIS100 Injection Kicker , September 2020, Delayed, , , , , , , , , ,
|
Tue Feb 11 09:57:17 2020, Cristina, test with bakeout, SIS100 diagnostic chambers, June 2020, Delayed, , 17.11.2020, DONE, Not Needed, 17.11.20, Customised, 25.11.20, Cond. Accep., 01.12.20, Grossmontage
|
Tue Feb 11 09:59:48 2020, Cristina, leak check, SIS100 Quadrupole chambers, March 2020, Delayed, September 20, September 20, DONE, Accepted, 30.09.20, HEBT Setup, 06.10.20, Accepted, 8.10.20, I.Pongrac
|
Fri Feb 14 13:34:54 2020, Cristina, test with bakeout, Berrilium Copper Stripes Dermati, 14.02.2020, On schedule, 14.02.2020, 14.02.2020, DONE, Not Needed, 17.02.2020; 11:30 am, Setup 1, 24.02.2020, Cond. Accep., 26.02.2020, Bardonner
|
Wed Feb 19 11:42:59 2020, Cristina, pumping speed, TMP Cryring (Nikita), KW8, On schedule, KW8, 19.02.2020, DONE, Refused, 9.03.2020, Fischer-Mommsen, 16.03.2020, Accepted, 29.05.2020, Nikita
|
Tue Mar 3 09:34:40 2020, Cristina, Coating, SPARC chambers , June 2019, Delayed, Febraury 2020, 12.02.2020, DONE, Accepted, 01.09.2020, Horizontal Coating Setup, 03.11.20, Accepted, 10.12.20, Track to Jülich
|
Tue Mar 3 09:58:03 2020, Cristina, test with bakeout, Ferrite RI (as received), 15.March, On schedule, , 20.03.2020, DONE, Not Needed, 23.03.2020, Setup 1, 27.03.2020, Cond. Accep., --------, ---------
|
Tue Mar 3 13:50:28 2020, Cristina, test with bakeout, Macor 4 -IPM Giacomini, KW10, On schedule, , 03.03.2020, DONE, Not Needed, 18.03.2020; 07:45 am, Mobile 2, 27.03.2020, Cond. Accep., 11.05.2020, T. Giacomini
|
Wed Mar 4 10:06:09 2020, Phe, leak check, Transistion tube for SIS100 string test_Second test, Beginning 2020, Delayed, February, End of February, DONE, Accepted, 03.03.2020, Customised, 03.03.2020, Accepted, 5.03.2020, Ivan and Stefan (for integration @BNG)
|
Mon Mar 9 08:46:22 2020, Phe, test without bakeout, BPM SIS100 2010-3, repeat after long pumping @ Hackhalle, , On schedule, , 06.03.2020, DONE, Accepted, 09.03.2020; 07:00 am, Mobile 3, 10.03.2020, Accepted, 12.03.2020, M.Müller
|
Thu Mar 12 13:47:38 2020, Phe, test without bakeout, BPM SIS100 2010-17 (only stainless steel after cleaning - no ceramic), Received , On schedule, , 12.03.2020, DONE, Not Needed, 12.03.2020; 11:55 am, Mobile 3, 17.03.2020; 11:00 am, Accepted, 19.03.2020, M.Müller
|
Thu Mar 12 13:49:09 2020, Phe, test without bakeout, BPM SIS100 2010-17 (ceramic only), Received, On schedule, , 12.03.2020, DONE, Not Needed, 18.03.2020; 08:25, Setup 1, 19.03.2020; 11:00, Cond. Accep., 19.03.2020, M.Müller
|
Thu Mar 19 11:23:38 2020, Phe, test without bakeout, BPM SIS100 2010-15 (after cryo), , On schedule, , 19.03.2020, DONE, Not Needed, 19.03.2020; 15:00, Mobile 3, 25.03.2020, Cond. Accep., 26.03.2020, M.Müller
|
Wed Mar 25 14:22:40 2020, Phe, test without bakeout, Broken ceramic for BPM, , On schedule, , 25.03.2020, DONE, Not Needed, 26.03.2020, Setup 2, 27.03.2020, Cond. Accep., 28.03.2020, M.Müller
|
Mon Apr 6 15:33:45 2020, Phe, test with bakeout, Unbaked Ferrites from RI (bigger size), , On schedule, , 06.04.2020, DONE, Not Needed, , Setup 1, 22.04.2020, Cond. Accep., ,
|
Wed Apr 22 08:35:13 2020, Phe, test without bakeout, BPM 2010-15 - 2 weeks pump down in Hackhalle, , On schedule, , 21.04.2020, DONE, Not Needed, 21.04.2020; 17:00, Mobile 3, 24.04.2020, Accepted, 23.04.20, M.Müller
|
Wed Apr 22 10:14:43 2020, Cristina, test with bakeout, Ceramic Tube for Cryring (Sieber, KW13, Delayed, 22.04.2020, 24.04.2020, DONE, Not Needed, 27.04.2020, Setup 2, 06.05.2020, Refused, 8.05.2020, T.Sieber
|
Wed Apr 22 13:45:53 2020, Cristina, test without bakeout, p-linac dipoles, 20.04.2020, On schedule, , 20.04.2020, DONE, Accepted, 21.04.2020, HEBT Setup, 29.04.2020, Cond. Accep., 27.05.2020, Florian (Grossmontage)
|
Fri Apr 24 09:56:27 2020, Cristina, test with bakeout, Be windows-Spillman, KW18, On schedule, , 28.04.2020, DONE, Not Needed, 26.05.2020, Setup 2, MEASUREMENTS STOPPED, , 02.10.20, Collegue Spillman
|
Wed May 13 15:26:53 2020, Phe, test with bakeout, Big Baked Ferrites PLT 90/50/30 8C11 and Small baked Ferrites CMD5005, , On schedule, , 11.05.2020, DONE, Not Needed, 13.05.2020; 7:40 am, Setup 1, 25.05.2020, Cond. Accep., ---------, -----------
|
Tue May 19 09:20:24 2020, Cristina, test with bakeout, Ceramic parts Hillenbrand, 25.05.20, On schedule, , 25.05.2020, DONE, Accepted, 26.05.2020, Setup 1, 30.05.2020, Accepted, 09.06.2020, Hillenbrand
|
Tue May 19 12:03:40 2020, Phe, Problem, Turbo Pump from Thomas Seiber, , On schedule, , KW19, DONE, Not Needed, 19.05.2020, Customised, 20.05.2020, Refused, 27.05.2020, Student from T.Sieber
|
Wed May 27 10:34:37 2020, Phe, test without bakeout, BPM SIS100 X2010-16, , , , KW21, DONE, Not Needed, 20.05.2020, Customised, 22.05.2020, Cond. Accep., 26.08.20, M.Müller
|
Wed Jun 17 10:13:57 2020, Cristina, test with bakeout, IPM SIS18, End May, On schedule, , End May (the gewind had to be redone by Pfeiffer), DONE, Accepted, 17.06.2020 and restarted on the 22.06.2020 and restarted on 25.08.20, Customised, 31.08.20, Cond. Accep., 04.09.2020, Back to Tino G.
|
Wed Jun 17 12:58:02 2020, Cristina, test without bakeout, SIS100 Dipole 07-6-016-4, ----, , ------, 17.06.2020, DONE, Accepted, 17.06.2020, HEBT Setup, 19.06.2020, Cond. Accep., 22.06.2020, brought back to the TH
|
Fri Aug 28 11:51:30 2020, Phe, test without bakeout, SIS100 dipole 07-00009-020-01, , , , , DONE, Accepted, 26.08.20, HEBT Setup, 28.08.20, Refused, 1.09.20, in the TH
|
Fri Aug 28 11:52:43 2020, Phe, test without bakeout, BPM SIS100 2010-61, , , , 26.08.20, DONE, Accepted, 26.08.20, Mobile 3, 28.08.20, Cond. Accep., 09.09.20, S. Fiedler
|
Fri Sep 11 09:56:40 2020, Cristina, test without bakeout, BPM SIS100 X2010-63, , , , , DONE, Accepted, 31.08.2020, Mobile 3, 01.09.20, Accepted, 09.09.20, S. Fiedler
|
Fri Sep 11 09:59:20 2020, Cristina, test without bakeout, Bellows IPM SIS18, , , , 01.09.2020, DONE, Refused, 02.09.2020, HEBT Setup, 03.09.2020, Refused, 11.09.2020, Zentrale Dienst (back to Giacomini)
|
Fri Sep 11 10:07:46 2020, Cristina, test with bakeout, Nuts company TwinNut, , , , , DONE, Accepted, 01.09.2020, Mobile 2, 10.09.2020, Accepted, ------, --------
|
Fri Sep 11 10:13:59 2020, Cristina, test without bakeout, Cecom diagnostic chamber HEBT, , , , 01.09.2020, DONE, Accepted, 02.09.2020, Setup 1, 04.09.2020, Cond. Accep., 23.09.20, M.Müller
|
Mon Sep 14 09:15:03 2020, Cristina, test without bakeout, BPM SIS100 2010-17, , , , 09.09.20, DONE, Accepted, 09.09.2020, Mobile 3, 10.09.2020, Cond. Accep., 17.09.2020, M. Müller
|
Mon Sep 14 09:16:54 2020, Cristina, test with bakeout, Mirror Laser cooling SIS100, , , , 14.09.2020, DONE, Accepted, 6.10.20, Mobile 2, 21.10.20, Cond. Accep., KW47, D.Winters
|
Mon Sep 14 10:38:59 2020, Cristina, test without bakeout, Test on Viton gasket, , , , 14.09.2020, TO DO, Not Needed, , , , , ,
|
Tue Sep 15 11:14:44 2020, Cristina, leak check, SIS100 Dipole chambers, , , , , on-going, , July 2019, Customised, , , ,
|
Mon Sep 21 11:31:47 2020, Cristina, test without bakeout, HEBT BPM, KW39, On schedule, , 28.09.20, on-going, Accepted, 05.10.20. Test started again: 08.12.20, Mobile 3, , Refused, ,
|
Mon Sep 21 11:32:46 2020, Cristina, test with bakeout, Ferrite RI after firing, , , , 18.09.20, DONE, Accepted, 22.09.2020, Setup 1, 1.10.20, Accepted, ---------, ---------
|
Mon Sep 21 11:39:27 2020, Cristina, test without bakeout, Steel with epoxy glue, August 20, Delayed, , 21.09.20, DONE, , 22.09.2020, , 03.10.20, Refused, ?, ?
|
Mon Sep 21 14:26:53 2020, Cristina, leak check, Beam line CWT, , , , 21.08.20, , , 21.09.20, Customised, 23.09.2020, Accepted, 24.09.20, S.Wilfert
|
Wed Sep 30 13:39:48 2020, Cristina, test with bakeout, Tube CCC Cryring, , , , 30.09.2020, DONE, Accepted, 5.10.20, Setup 1, 07.10.20, Accepted, 8.10.20, T. Sieber
|
Tue Oct 13 07:54:31 2020, Phe, test without bakeout, Epoxy - baked in the oven @ 80 deg C, 09.10.2020, On schedule, , 09.10.2020, DONE, Not Needed, 22.10.20, Mobile 2, 29.10.20, Refused, ,
|
Wed Oct 21 10:51:47 2020, Cristina, test with bakeout, IPM SIS18 mit diagnostic parts, , , , 25.09.2020, DONE, Refused, 20.10.20, , 29.10.20, Cond. Accep., 2.11.20, Grossmontage
|
Tue Nov 3 09:55:20 2020, Cristina, test with bakeout, MCPs for IPM SIS18, September, Delayed, , 2.11.20, DONE, Accepted, 2.11.20, Setup 1, 09.11.2020, Cond. Accep., 10.11.2020, T.Giacomini
|
Tue Nov 17 09:43:55 2020, Cristina, test without bakeout, BPM 2010-16, , , , ?, DONE, Accepted, 16.11.20, Mobile 3, 17.11.20, Cond. Accep., 01.12.20, Grossmontage
|
Thu Nov 19 10:15:23 2020, Cristina, Coating, Parts for Cryring , , , , Beginning October 20, DONE, Accepted, 16.11.20, Horizontal Coating Setup, 17.11.20, Accepted, 26.11.20, David (Cryring)
|
Thu Nov 19 10:17:06 2020, Cristina, Coating, Coating chamber Glorius, , , , 16.11.20, DONE, Accepted, 27.11.20, Horizontal Coating Setup, 3.12.20, Accepted, 14.12.20, Glorius
|
Mon Nov 30 11:14:30 2020, Cristina, Coating, T-piece Cryring, Oct, , , KW48, DONE, Accepted, 26.11.20, Horizontal Coating Setup, 3.12.20, Accepted, 10.12.20, Nikita
|
Mon Nov 30 11:15:48 2020, Cristina, test with bakeout, Antrieb for ESR-Beata, 1 Dec., Delayed, ?, 3.12.20, DONE, Not Needed, 3.12.20, Setup 1, 10.12.2020, Accepted, 11.12.20, Müller
|
Mon Nov 30 11:17:49 2020, Cristina, leak check, 5 x SIS100 Diagnostic Chambers, KW 49, , , , DONE, Not Needed, 01.12.20, , 16.12.20, Accepted, ,
|
Tue Dec 1 11:49:07 2020, Cristina, test with bakeout, Bellows IPM SIS18-Second measurement after cleaning, , , , 12.10.20, DONE, Not Needed, 12.10.20, HEBT Setup, 14.10.20, Accepted, 15.10.20, Zentrale Dienst
|
Tue Jan 12 12:48:45 2021, Cristina, test without bakeout, HEBT BPM-Cleaned @Kyocera, Beginning 21, On schedule, , 12.01.21, DONE, Accepted, 12.01.21, Mobile 3, 14.01.21, Accepted, 19.01.21, M.Müller
|
Wed Jan 20 11:48:54 2021, Cristina, test without bakeout, HEBT BPM cleaned @GSI, , , , 19.01.21, DONE, Accepted, 20.01.21, Mobile 3, 21.01.21, Refused, 24.02.21, M.Müller
|
Fri Jan 29 11:50:13 2021, Cristina, General, Pillow seals SFRS, , , , 14.01.21, DONE, Accepted, 18.01.21, Customised, 26.02.21, Cond. Accep., 12.03.21, Cristos
|
Fri Jan 29 11:52:53 2021, Cristina, pumping speed, NEG strips CRYRing, , , , End Dec 20, DONE, Accepted, 25.01.21, Fischer-Mommsen, 17.02.2021, Accepted, 02.03.21, Nikos
|
Fri Jan 29 11:54:20 2021, Cristina, leak check, Gate Valve, , , , 14.01.21, DONE, Accepted, 28.01.21, Customised, 28.01.21, Refused, 29.01.21, A.Tauschwitz
|
Fri Jan 29 11:55:45 2021, Cristina, General, Lower pressure of primary pumps, , , , Dec 20, DONE, Accepted, 18.01.21, Customised, 22.01.21, Accepted, -----, G.Savino
|
Mon Feb 1 16:04:00 2021, Phe, test with bakeout, Antriebe SIS100, , On schedule, , 01.02.2021, DONE, , 02.02.2021, Setup 1, 10.02.2021, Accepted, 11.02.21, M.Müller
|
Wed Feb 3 11:47:32 2021, Cristina, leak check, CARME vacuum chamber, Dec 2020, Delayed, , 02.02.2021, DONE, Accepted, 02.02.2021, Customised, 02.202.2021, Accepted, 03.02.2021, N.Petridis
|
Wed Feb 3 11:50:09 2021, Cristina, test with bakeout, Detector Pockets for scintillators SIS18, , , , 02.02.2021, on-going, , 08.02.21, HEBT Setup, 11.03.21, Cond. Accep., 12.03.21, M.Müller
|
Wed Feb 17 11:30:26 2021, Cristina, test without bakeout, CECOM diagnostic chamber, 1.02.21, , , 17.02.21, DONE, Accepted, 18.01.21, Customised, 19.02.21, Cond. Accep., ,
|
Wed Feb 17 11:31:08 2021, Cristina, test without bakeout, SIS100 BPM, , , , 15.02.21, DONE, Accepted, 16.02.21, , 18.02.21, Accepted, 24.02.21, M.Müller
|
Wed Feb 17 11:50:45 2021, Cristina, leak check, SIS100 HF Cavities, , , , 15.02.21, DONE, Accepted, 15.02.21, Customised, 16.02.21, Accepted, 17.02.21, In Weitestadt
|
Fri Feb 19 08:39:57 2021, Cristina, , HEBT BPM cleaned @GSI-second measurement, , , , 10.02.21, DONE, Accepted, 10.02.21, Customised, 18.02.21, Accepted, 24.02.21, M.Müller
|
Fri Feb 19 08:41:46 2021, Cristina, leak check, 2x Cryostats-Kujouharov, 1.02.21, , 11.02.21, 11.02.21, DONE, , 12.02.21, Customised, 02.03.21, Cond. Accep., 09.03.21, Kojouharov
|
Wed Feb 24 13:50:25 2021, Cristina, leak check, Cavity for DALINAC, 22.02.21, Delayed, 01.03.21, 09.03.21, DONE, Not Needed, 10.03.21, Customised, 11.03.21, Cond. Accep., 18.03.21, Dmytriiev D.
|
Wed Feb 24 13:51:01 2021, Cristina, test with bakeout, 3D printed tube per pLinac, 01.03.21, , , 08.03.21, DONE, Accepted, 16.03.21, Setup 1, 18.03.21, Accepted, 18.01.21, Büro Andreas
|
Wed Mar 10 12:11:04 2021, Cristina, test with bakeout, Viewports DN100 ESR, , , , 16.02.21, on-going, Not Needed, 16.02.21, Setup 1, 16.03.21, Cond. Accep., 26.03.21, R.Sanchez
|
Thu Mar 18 11:40:02 2021, Cristina, test with bakeout, SIS100/HEBT Manipulator C.Dorn, , , , 17.03.21, DONE, Not Needed, 18.03.21, Setup 1, 24.03.21, Accepted, 29.03.21, M.Müller
|
Wed Apr 28 10:05:13 2021, Cristina, test without bakeout, SIS100 pumping chambers -after cleaning by the Company, , , , 23.04.21, on-going, Accepted, 26.04., Customised, 21.05.21, Cond. Accep., ,
|
Wed Apr 28 10:21:27 2021, Cristina, test without bakeout, Cecom after cleaning, , , , 06.04.21, DONE, Not Needed, 06.04.21, Customised, 08.04.21, Accepted, 12.05.21, M.Müller
|
Wed Apr 28 10:23:18 2021, Cristina, test without bakeout, 3Dprinting Copper coated sample, , , , 25.03.21, DONE, Not Needed, 25.03.21, , 26.03.21, Cond. Accep., ,
|
Wed Apr 28 10:28:18 2021, Cristina, test without bakeout, Ceramic for SIS100 BPM, , , , 22.03.21, DONE, , 22.03.21, Mobile 3, 29.03.21, Accepted, , M.Müller
|
Wed Apr 28 10:30:54 2021, Cristina, test with bakeout, HEBT Antrieb (in-kind Slovenia) 06-0050-39-54, , , , 23.04.21, DONE, Not Needed, 26.04.21, Setup 1, 03.05.21, Accepted, 06.05.21, M.Müller
|
Tue May 18 10:50:26 2021, Cristina, test with bakeout, HEBT Antrieb 06-0050-036-40, , , , 06.05.21, DONE, Not Needed, 06.05.21, Setup 1, 12.05.21, Accepted, 17.05.21, M.Müller
|
Tue May 18 14:10:04 2021, Cristina, test without bakeout, Trafos BPM, , , , 12.05.21, DONE, Not Needed, 18.05.21, Customised, 21.05.21, Refused, 07.06.21, M.Müller
|
Tue May 18 14:11:08 2021, Cristina, test without bakeout, BPM CID: 06005002605, , , , 18.05.21, DONE, , 19.05.21, Mobile 3, 21.05.21, Cond. Accep., 07.06.21, M.Müller
|
Fri May 21 13:29:15 2021, Cristina, test with bakeout, 2xDN63 windows for ESR , , , , 20.05.21, DONE, Not Needed, 18.05.21, Setup 1, 02.06.21, Accepted, 18.06.21, R.Sanchez
|
Tue Jun 8 10:19:14 2021, Cristina, test without bakeout, Dipole Module, , , , 25.05.21, DONE, Not Needed, 25.05.21, Customised, 27.07.21, Cond. Accep., TH, F.Kaether
|
Tue Jun 8 10:27:49 2021, Cristina, test with bakeout, Mirror system ESR-Brandau, 07.06.21, Delayed, , 21.06.21, DONE, Not Needed, 25.06.21, Mobile 2, 13.07.21, Cond. Accep., 24.09.21, Brandau
|
Tue Jun 8 10:28:46 2021, Cristina, test with bakeout, Pockets for ESR, KW25, , , 21.06.21, DONE, Not Needed, 24.06.21, Setup 1, 12.07.21, Accepted, 19.07.21, Glorious
|
Mon Jun 14 11:48:43 2021, Cristina, test with bakeout, Antrieb für SIS100, , , , 07.06.21, DONE, Not Needed, 14.06.21, Setup 1, 22.06.21, Accepted, 28.06.21, M.Müller
|
Thu Jun 24 12:05:07 2021, Cristina, test with bakeout, Bearings for HEBT-foil-stripper -Zeller, KW26, , , 01.07.21, DONE, Not Needed, 14.07.21, Mobile 2, 05.08.21, Refused, ,
|
Thu Jun 24 12:06:49 2021, Cristina, test with bakeout, Test for polymide coated sample- Fischer, , , , , DONE, , 2.07.21, HEBT Setup, 6.07.21, Cond. Accep., 8.07.21, L.Fischer
|
Thu Jun 24 12:07:27 2021, Cristina, test with bakeout, Injection Septa SIS100, , , , 21.06.21, DONE, Not Needed, 23.06.21, Customised, 14.07.21, Cond. Accep., 19.07.21, Report sent to I.Pongrac (Component in TH)
|
Mon Jul 12 13:45:55 2021, Cristina, test with bakeout, BPM SIS100, , , , 09.07.21, DONE, Not Needed, 13.07.21, Mobile 3, 14.07.21, Cond. Accep., 20.07.21, R.Mahr
|
Mon Jul 12 13:46:30 2021, Cristina, test without bakeout, Experimental Chamber, 5.07.21, , , 14.07.21, DONE, , 15.07.21, Customised, 22.07.21, Cond. Accep., 26.07.21, Bömsch
|
Mon Jul 12 13:47:03 2021, Cristina, test without bakeout, Trafos for isolation vacuum-Piotr, , , , 02.07.21, DONE, Not Needed, 07.07.21, Mobile 3, 12.07.21, Refused, 19.08.21, P. Kowina
|
Wed Jul 14 14:09:31 2021, Cristina, test with bakeout, Profil Gitter for HEBT, , , , 09.07.21, DONE, Not Needed, 14.07.21, Setup 1, 19.07.21, Cond. Accep., ,
|
Thu Aug 19 09:53:54 2021, Cristina, test with bakeout, MCP for ESR-Giacomini, , , , 05.08.21, DONE, Not Needed, 11.08.21, Setup 1, 17.08.21, , 17.08.21, F. Wolf
|
Thu Aug 19 09:58:04 2021, Cristina, , Profil Gitter for HEBT, , , , , DONE, Not Needed, 14.07.21, , 19.07.21, Refused, ,
|
Thu Aug 19 10:00:46 2021, Cristina, , BPM Kyocera (8 pieces), 28.07.21, , , 30.07.21, DONE, Not Needed, 02.08.21, Mobile 3, 28.08.21, Accepted, 31.08.21, F.Wolf
|
Fri Aug 20 09:21:08 2021, Cristina, test with bakeout, Diagnostic chambers (2), , , , 19.08.21, DONE, Not Needed, 14.09.21, Customised, 25.09.21, Cond. Accep., 02.11.2021, M. Mueller
|
Wed Sep 15 10:29:42 2021, Cristina, test with bakeout, Al chamber, , , , , DONE, Not Needed, 02.09.21, Mobile 3, 13.09.21, Accepted, 16.09.21, N.Staldmann
|
Tue Sep 21 11:38:16 2021, Phe, test without bakeout, Kyocera ceramics - 4x, , On schedule, , 21.09.2021, DONE, , 23.09.21, Mobile 3, 15.10.21, Accepted, ,
|
Tue Sep 28 11:55:07 2021, Cristina, test without bakeout, BPM with ceramic, , , , 12.09.21, DONE, Not Needed, 14.09.21, Mobile 3, 16.09.21, Refused, 28.09.21, M.Müller
|
Wed Oct 20 11:25:04 2021, Phe, test without bakeout, BPM Chambers - 2x, , On schedule, , 20.10.2021, DONE, Not Needed, 21.10.21, , 27.10.21, Cond. Accep., 02.11.21, M.Mueller
|
Tue Nov 2 09:06:05 2021, Phe, test without bakeout, Cecom chamber for FAT K2030-1123, 06004016122, , On schedule, , , on-going, , , , , , ,
|
Mon Nov 8 15:10:43 2021, Phe, test with bakeout, SIS100 bunch compressor with ceramic gap, , On schedule, , 08.11.2021, DONE, Not Needed, 25.11.21, Setup 1, 01.12.21, Accepted, ,
|
Wed Nov 17 11:46:15 2021, Cristina, test with bakeout, Coated Al sheet metall bent (Brandau), , , , 5.11.21, DONE, Not Needed, 8.11.21, Setup 1, 15.11.21, Cond. Accep., 03.02.22, R.Sanchez
|
Wed Nov 17 11:48:30 2021, Cristina, test without bakeout, Fluorescence chamber SIS100, , , , 12.11.21, DONE, Accepted, 17.11.21, Mobile 3, 18.11.21, Accepted, ,
|
Wed Nov 17 11:50:00 2021, Cristina, leak check, SIS100 bunch compressor, , , , 15.11.21, DONE, Not Needed, 16.11.21, Customised, 17.11.21, Accepted, ,
|
Wed Nov 17 11:51:00 2021, Cristina, test with bakeout, Second SIS100 injection Septa , , , , , DONE, Not Needed, 11.11.21, Customised, 19.11.21, Cond. Accep., ,
|
Thu Dec 2 11:08:38 2021, Cristina, test without bakeout, BPM, , , , 30.11.21, DONE, Not Needed, 02.12.21, Mobile 3, 06.12.21, Accepted, 23.02.22, M.Müller
|
Thu Dec 9 11:41:47 2021, Cristina, test with bakeout, Tube with ceramic gap- resistence study, , , , 03.12.21, DONE, Not Needed, 06.12.21, Setup 1, 09.12.21, , Dec 21,
|
Thu Dec 9 11:42:50 2021, Cristina, test without bakeout, BPM, , , , 07.12.21, DONE, Not Needed, 09.12.21, Mobile 3, 13.12.21, Cond. Accep., 17.12.21, Müller
|
Wed Jan 12 08:40:00 2022, Cristina, , Windows for ESR, , , , 10.01.22, DONE, Not Needed, 13.01.22, Setup 2, 21.10.22, Cond. Accep., 03.02.22, R.Sanchez
|
Wed Jan 12 08:40:41 2022, Cristina, , XHU detector ESR, , , , 16.12.21, DONE, Not Needed, 12.01.22, Setup 1, 26.01.22, Cond. Accep., 24.02.22, D.Winters
|
Tue Jan 18 08:50:13 2022, Cristina, test with bakeout, Mirror chamber ESR (Brandau), , , , 16.01.22, DONE, Not Needed, 17.01.22, Customised, 31.01.22, Cond. Accep., 31.01.22, ESR
|
Tue Jan 18 08:51:15 2022, Cristina, test without bakeout, Grids for pLinac (Siebert), 07.01.22, , , 17.01.22, DONE, Not Needed, 19.01.22, HEBT Setup, 31.01.22, Cond. Accep., 31.01.22, T.Sieber
|
Wed Feb 9 14:19:51 2022, Cristina, test without bakeout, CECOM chamber, , , , KW5, DONE, Not Needed, 08.02.2022, Customised, 09.02.22, Accepted, , M.Müller
|
Tue Feb 15 09:56:13 2022, Cristina, test without bakeout, NTG chamber HEBT special installation, , , , 03.02.22, DONE, Not Needed, 10.02.22, Customised, 14.02.22, Cond. Accep., 25.06.22, S.Zeller
|
Fri Feb 25 09:36:32 2022, Cristina, test with bakeout, Grid+manipolator, , , , KW7, DONE, , 23.02.22, Setup 1, 11.03.22, Accepted, ,
|
Fri Feb 25 09:37:36 2022, Cristina, test without bakeout, 2 BMP, , , , 23.02.22, DONE, , 28.02.22, Mobile 3, 04.03.22, Accepted, 04.03.22, M.Müller
|
Tue Mar 15 14:06:51 2022, Cristina, , Indian diagnostic chamber, , , , 11.03.22, DONE, Not Needed, 15.03.22, Customised, 16.03.22, Accepted, ,
|
Tue Mar 22 11:27:51 2022, Cristina, test with bakeout, SIS100 Qpole, , , , , on-going, Not Needed, 22.03.22, Customised, , , ,
|
Mon Mar 28 11:50:59 2022, Cristina, test without bakeout, Missing dipole, , , , 28.03.22, TO DO, , , , , , ,
|
|