Entry  Mon Sep 30 11:04:15 2019, Cristina, leak check, Cryo collimator 11-1-18-8, , , , 24.09.2019, DONE, Accepted, 25.09.2019, Customised, 25.09.2019, Accepted, 26.09.2019, L. Bozyk 
 
Entry  Mon Sep 30 11:11:26 2019, Cristina, test with bakeout, Laser chamber -Winters, Beginning 2019, Delayed, , 16.08.2019, DONE, Accepted, 30.08.2019, Customised, 12.02.2020, Accepted, KW10, D.Winters Laser_chamber.jpg
The measurement was stopped because of the wrong heating jackets
Entry  Mon Sep 30 11:15:47 2019, Cristina , test with bakeout, Detector Recoil chamber ESR, , , , 2.09.2019, DONE, Accepted, 9.09.2019, Customised, 29.10.2019, Cond. Accep., 1.11.19, Hillenbrand Recoil_ESR_chamber.jpg
The chamber was brought in the lab without heating jackets, which where shipped on the 17.10. Conditionally Accepted because the RGA after bakeout does not fulfil the requirements.
Entry  Mon Sep 30 14:00:51 2019, Cristina, pumping speed, 800 l/s Agilent, , , , 20.09.2019, DONE, Accepted, 1Test:7.10.2019; 2Test: 14.11.2019, Fischer-Mommsen, 1.11.19, Cond. Accep., , Sent back to Agilent 
Pumping Speed measured a bit lower than stated
Entry  Mon Sep 30 14:04:43 2019, Cristina, pumping speed, Combi pump DN40, , , , 09.08.2019, DONE, Accepted, 20.08.2019, Fischer-Mommsen, 20.09.2019, Accepted, , Sent back to Agilent Agilent_combi_DN40.jpg
 
Entry  Mon Sep 30 14:06:07 2019, Cristina, pumping speed, Slim SIP 150, , , , 9.08.2019, DONE, Accepted, 07.02.2020, Fischer-Mommsen, 06.03.2020, Accepted, ,  Comparison.jpg
 
Entry  Wed Oct 9 07:55:47 2019, Phe, leak check, All metal gate valve (Bender), , , , 08.10.2019, DONE, Accepted, 21.10.2019, Customised, 24.10.2019, Accepted, 24.10.2019, M.Bender All_metal_valve.jpg
Leak check required by Markus Bender for a "all metal gate valve". The gate valve was received on the 08.10.2019. No deadline. The gate valve is on Edgar's desk - so Edgar can check it when he's back from holiday. 23.10.2019 Test DONE
Entry  Wed Oct 9 07:57:44 2019, Phe, test with bakeout, Cryring Detector Tube , , , , 09.10.2019, DONE, Accepted, 10.10.2019, Setup 1, 22.10.2019, Accepted, 24.10.2019, Spillmann 20191008_094940.jpg
Detector tube has been received from Grossmontage (given to Andreas Kraemer). This Detector tube is for Cryring - measurement request from Dr. Uwe Spillmann. The Detector tube needs to have some additional components, which will be assembled by Alexander Borovik (from Giessen University). Email has been sent to Alexander Borovik and he might pick the Detector Tube on 09.010.2019. The Detector Tube is on Phe's desk. The detector tube has been picked up by Alexander Borovik (09.10.2019). The additional component has been assembled to the Detector tube (09.10.2019)
Entry  Wed Oct 9 08:01:51 2019, Phe, test with bakeout, Macor Samples from Tino Giacomini, , , , 02.10.2019, DONE, Accepted, 10.10.2019, Mobile 2, 6.11.19, Accepted, 8.11.19, Giacomini 
Macor samples have been received from Tino Giacomini on the 02.10.2019. These Macor samples will be used for IPM chamber. The test request is a vacuum acceptance test with bake-out.
Entry  Wed Oct 9 14:19:09 2019, Phe, test with bakeout, Scrapper for ESR (for Markus Steck), , , , 09.10.2019, DONE, Accepted, 14.10.2019, Setup 2, 18.10.2019, Accepted, 24.10.2019, Schwarz ESR-Scraper.jpg
Measurements asked as "urgent" for ESR. This piece was already measured in 2014, and then stored in an unkwon place.
Entry  Mon Oct 14 10:08:14 2019, Cristina, leak check, Dipole chamber SIS100 First charge, , , , 10.10.2019, DONE, Accepted, 11.10.2019, Customised, 29.11.2019, Accepted, , Stored in the TH 
6 dipole received on the KW41. Integral leak check and 1 test without bakeout After the vacuum test the chambers must be inserted on the magnet: 1 chamber was not fitting easy into the magnet. It will go today (15.11.19) in the technology lab for mechanical measurements.
Entry  Mon Oct 14 10:09:36 2019, Cristina, leak check, Roughing CWT 3 charge, , , , 10.10.2019, DONE, Accepted, 14.10.2019, Customised, 14.11.19, Accepted, , Stored in Weiterstadt CWT.jpg
Integral leak check to be done for all CWT. DONE: 07-51-23-0; 07-51-26-1; 07-51-30-8; 07-51-31-5; 07-51-17-9; 07-51-28-5;07-51-21-6 (Black-orange spots visible);07-51-36-0; 07-51-37-7; 07-51-32-2; 07-51-14-8;07-51-35-3;07-51-18-6; 07-51-29-2; 07-51-34-6
Entry  Wed Oct 16 08:24:29 2019, Toni, leak check, Kryokollimator , June 2019, Delayed, August, from September 2019, DONE, Not Needed, 02.09.2019, Customised, 09.12.2020, Accepted, ,  criocollimator.jpg
Collimator tested:11-1-02-7; 11-1-03-4; 11-1-4-01; 11-1-06-5; 11-1-09-6; 11-1-10-2; 11-1-11-9; 11-1-12-6; 11-1-14-0; 11-1-15-7; 11-1-16-4; 11-1-17-1; 11-1-18-8; 11-1-20-1;11-1-25-6; 11-1-22-5;11-01-24-4;11-1-28-7;11-1-27-0;11-1-29-4;11-1-26-3;11-1-13-3;11-1-21-8;11-1-40-9; 11-1-39-3;11-1-30-0;11-1-19-5 (LEAK!!!); 11-1-33-1;11-1-23-2; 11-1-43-0;11-1-42-3; 11-1-37-9; 11-1-63-8; 11-1-57-7; 11-1-45-4; 11-1-49-2; 11-1-44-7; 11-1-58-4; 11-1-24-9;11-1-36-2; 11-1-31-7; 11-1-38-6; 11-1-55-3; 11-1-53-9; 11-1-32-4;11-1-50-8; 11-1-34-8; 11-1-61-4;11-1-65-2; 11-1-64-5; 11-1-60-7;11-1-62-1;11-1-66-9; 11-1-51-5;11-1-59-1; 11-1-35-5; 11-1-52-2;11-1-48-5; 11-1-41-6; 11-1-46-1; 11-1-56-0; 11-1-54-6
Entry  Mon Oct 21 10:24:59 2019, Cristina, Other, Tube Heidelberg, , , , 17.10.2019, DONE, Accepted, First Test: 24.10.2019; Second Test:30.01.20 , Horizontal Coating Setup, 29.10.2019: Refused; Second Test: 05.02.2020, Accepted, 11.02.2020, C.Schröter HD_tube.jpg
Tube to be coated for HD. After the first coating: PEELING. STOP and waiting for the nextstep to be decided in HD. We cleaning the tubes many times, to try to remove all the film, and then we performes succesfully the second coating.
Entry  Thu Oct 24 14:55:28 2019, Toni, , , , , , , , , , , , , ,  
 
Entry  Thu Oct 24 14:58:25 2019, Toni, , , , , , , , , , , , , ,  
 
Entry  Fri Nov 1 10:41:45 2019, Cristina, test with bakeout, IPM Chamber, , , , 4.09.2019, DONE, Refused, , , , Refused, 1.11.19, Angelo 
Bellows to short
Entry  Fri Nov 8 10:52:43 2019, Cristina, test with bakeout, Macor 2 for IPM, , , , 8.11.19, DONE, Accepted, 11.11.2019, Mobile 2, 18.11.2019, Accepted, 04.12.19, T. Giacomini 
 
Entry  Mon Nov 11 08:06:09 2019, Phe, test without bakeout, Ref. Chamber for Beam Diagnostic Manipulator (Hackhalle), , , , unknown, DONE, Accepted, 11.11.2019; 10:15 am, stopped 12.11.2019, Customised, , Refused, ,  
Broken gauge (cold cathode gauge).
Entry  Thu Nov 14 14:00:28 2019, Phe, test without bakeout, Ref. Chamber for Beam Diagnostic Manipulator, , , , unknown, DONE, Accepted, 14.11.2019; 10:30 am, Customised, 22.11.2019, Cond. Accep., N/A, N/A 
Wide range gauge is now installed on the chamber. The previous test with cold cathode gauge failed due to broken gauge. Another complete new gauge is now installed on the chamber.
Entry  Fri Nov 22 11:07:36 2019, Phe, test without bakeout, Beam Diagnostic Chambers from India for HEBT - small one, , , , unknown, DONE, Refused, 09.01.2020, Customised, 10.01.2020 - still pumping, Accepted, 15.01.20, Mahr Rainer 
Inside of the chamber is dirty (black mark when wiped with tissue). At the moment (16.12.2019), the chamber is under cleaning. Chamber has been cleaned on the 18.12.2019, stored in the Testing Halle. Vacuum acceptance test on the chamber - started on the 09.01.2020.
Entry  Fri Nov 22 11:08:19 2019, Phe, test with bakeout, SEM-Monitor for Beam Diagnostic SIS18, , , , 02.12.2019, DONE, Accepted, 03.12.2019, Setup 2, 13.12.2019, Cond. Accep., 06.01.2020, Fiedler, Sebastian foto.jpg
 
Entry  Fri Nov 22 11:09:19 2019, Phe, test with bakeout, Grid for Beam Diagnostic SIS18, , , , 02.12.2019, DONE, Accepted, 03.12.2019, Setup 1, 13.12.2019, Cond. Accep., 06.01.2020, Fiedler, Sebastian 
 
Entry  Fri Nov 22 11:09:59 2019, Phe, Other, Septum SIS100 - NEG coated chamber, End 2019, Delayed, , unknown, TO COME, , , , , , ,  
 
Entry  Fri Nov 22 11:10:33 2019, Phe, test with bakeout, Dipole Chambers for SIS100 (2box), 25.11.19, Delayed, Unknown, 17.01.20, DONE, Accepted, 12.02.2020, , End februar, Accepted, ,  
All chambers are inserted with success into the magnet. Leak check for: 07-6-013-3; 07-6-009-6; 07-6-011-9
Entry  Fri Nov 22 11:11:00 2019, Phe, test with bakeout, Quad Chambers for SIS100, , , , unknown, TO COME, , , , , , ,  
 
Entry  Fri Nov 22 11:11:24 2019, Phe, leak check, 4th batch of roughing CWT for SIS100, , , , 06.01.20, DONE, Accepted, 10.02.2020, Customised, 13.03.20, Accepted, , Stored in Weiterstadt 
07-51-50-6; 07-51-38-4;07-51-47-6; 07-51-33-9; 07-51-02-5 (GEWINDEBOHRUNG IM KONTAKBLOCK WRONG);07-51-43-8; 07-51-41-4;07-51-44-5;07-51-42-1;04-51-39-1; 07-51-48-3; 07-51-40-7; 07-51-49-0;07-51-45-2; 07-51-46-9
Entry  Fri Nov 22 11:11:56 2019, Phe, test with bakeout, 'Spill-Cavitaet" ???, August 2019, Delayed, KW26, , TO COME, , , , , , ,  
 
Entry  Thu Nov 28 11:09:29 2019, Cristina, test with bakeout, Reference chamber for Grid for beam diagnostic SIS18, , , , 06.01.2020, DONE, Not Needed, 09.01.2020; , Setup 1, 19.01.20, Accepted, ----------, ---------- 
 
Entry  Thu Nov 28 11:11:16 2019, Cristina, test with bakeout, Reference chamber for Monitor for beam diagnostic, , , , 09.01.2020, on-going, Not Needed, 08.01.2020; 09:05 am; repeat due to leak - 13.01.2019, 07:00 am, Setup 2, , , ,  
 
Entry  Mon Dec 2 14:28:58 2019, Cristina, General, TS1MU1-test with magnet, August 2019 delayed to KW6 2020, Delayed, Unkwon, N/A, DONE, Accepted, 04.03.2020, Customised, , Accepted, , Grossmontage 
Test bakeout inside the magnet
Entry  Wed Dec 4 10:08:42 2019, Cristina, test with bakeout, Macor 3 charge, , , , 04.12.19, DONE, Accepted, 11.02.2020, Customised, 20.03.2020, Cond. Accep., 23.03.2020, T. Giacomini 
 
Entry  Thu Dec 12 09:20:54 2019, Cristina, test with bakeout, IPM SIS100-Giacomini, Jannuary 2020, Delayed, Unknown, 21.04.2020, DONE, Not Needed, 04.05.2020, Customised, 15.05.2020, Accepted, Mai/Juni, Brough to the TH 
 
Entry  Thu Dec 12 09:22:19 2019, Cristina, test without bakeout, Palmer PU Tank- Dimopoulou, January 2020, on schedule, January 2020, January 2020, DONE, Accepted, 28.01.20, Customised, 31.01.20, Accepted, 03.02.20, Grossmontage 
 
Entry  Thu Dec 12 10:19:06 2019, Cristina, test with bakeout, Pumping chamber SIS100 -Stefan, End 2019, Delayed, Beginning2020, 10.12.19, DONE, Accepted, January, Customised, 05.02.2020, Accepted, , Stored in the TH 
 
Entry  Fri Dec 13 09:03:27 2019, Christian, leak check, Fasersonde Unilac, , , , 12.12.19, DONE, Accepted, 12.12.19, Customised, 16.12.19, Refused, 16.12.19, Sthraldiagnose 
 
Entry  Mon Dec 16 15:27:50 2019, Phe, test without bakeout, Beam Diagnostic from Inida - big one, , , , 13.13.2019 , DONE, Refused, 15.01.20, Customised, 19.01.20, Accepted, 24.01.201, M.Müller 
The chamber has a dent. At the moment (16.12.2019), the chamber is under test for mechanical acceptance.
Entry  Tue Dec 17 13:39:20 2019, Phe, leak check, Fasersonde Unilac -2 test, , , , 17.12.2019, DONE, Not Needed, 17.12.2019, Customised, 17.12.2019, Accepted, 20.12.2019, Beam diagnostic 20191217_134243.jpg
This phase probe was tested by Christian Kolligs on the 12.12.2019 and it has leak rate of 1E-6 mbar.l/s.

The probe was then repaired by the Beam Diagnostic and tested again on the 17.12.2019 by Toni Coronato: it was leaky again. Repaired again and installed in the Unilac on the 20.12.19
Entry  Wed Dec 18 11:27:54 2019, Phe, leak check, Transistion tube for SIS100 string test, Beginning 2020, Delayed, February, 06.02.2020, DONE, Refused, , , , Refused, ,  
 
Entry  Thu Jan 16 09:05:12 2020, Cristina, test without bakeout, BPM SIS100- 2010-3, 27.01.20, Delayed, 30.01.20, 30.01.20, DONE, Accepted, 03.02.2020, Customised, 05.02.2020, Refused, 10.02.2020, M.Müller 
New mobile pumping station - the controller for the IMG did not work. The pressure is recorded from the gauge controller of Mobile pumping setup 2.
Entry  Mon Jan 20 10:40:00 2020, Cristina, test with bakeout, Ceramic Tube Diagnostic-Dorn 06-004-01376-3, KW4, On schedule, KW4, 20.01.20, DONE, Accepted, 21.01.2020, Setup 1, 27.01.20, Accepted, 29.01.20, M.Müller 
 
Entry  Thu Feb 6 10:33:17 2020, Cristina, test without bakeout, BPM 2010-17 (keept in the new cryostat), KW7, On schedule, KW7, 10.02.2020, DONE, Accepted, 12.02.2020, Mobile 3, 14.02.2020, Refused, 18.02.2020, M.Müller 
 
Entry  Thu Feb 6 10:34:00 2020, Cristina, test without bakeout, BPM 2010-15 (from the Company), KW8, On schedule, KW8, 18.02.2020, DONE, Refused, 19.02.2020, Mobile 3, 21.02.2020, Cond. Accep., 25.02.2020, M.Müller 
 
Entry  Thu Feb 6 10:34:25 2020, Cristina, test without bakeout, BPM 2010-16 (keep in the old cryostat), KW9, On schedule, KW9, 26.02.2020, DONE, Refused, 26.02.2020, Mobile 3, 28.02.2020, Cond. Accep., 27.02.2020, Müller 
 
Entry  Thu Feb 6 11:11:21 2020, Cristina, General, In kind contribution Sweden -Niko, March 2020, On schedule, , , , , , , , , ,  
 
Entry  Thu Feb 6 12:45:52 2020, Cristina, test without bakeout, Protoype BV CWT, March, On schedule, , 26.08.20, DONE, Not Needed, 14.09.20, Customised, 21.09.20, Accepted, 22.09.20, S. Wilfert 
 
Entry  Thu Feb 6 12:47:18 2020, Cristina, leak check, Interconnction bellows between Dipole and Quadrupole, October , On schedule, , 3.11.20, DONE, Accepted, 04.11.20, Customised, 04.11.20, Refused, 04.11.20, in Büro of S.Wilfert 
 
Entry  Thu Feb 6 12:48:46 2020, Cristina, leak check, 30 SIS 100 pumping chambers, May 20, Delayed, December 20, , , , , , , , ,  
1 chamber required: acceptance test without bakeout
Entry  Tue Feb 11 09:53:14 2020, Cristina, leak check, SIS100 Sextupole (6), September 2020, Delayed, , , , , , , , , ,  
 
Entry  Tue Feb 11 09:54:49 2020, Cristina, test with bakeout, SIS100 Injection Kicker , September 2020, Delayed, , , , , , , , , ,  
 
Entry  Tue Feb 11 09:57:17 2020, Cristina, test with bakeout, SIS100 diagnostic chambers, June 2020, Delayed, , 17.11.2020, DONE, Not Needed, 17.11.20, Customised, 25.11.20, Cond. Accep., 01.12.20, Grossmontage 
There are a total of 6 chambers. We have to do leak check to all 6, and a complete SAT (with bakeout) to 1 chamber
Entry  Tue Feb 11 09:59:48 2020, Cristina, leak check, SIS100 Quadrupole chambers, March 2020, Delayed, September 20, September 20, DONE, Accepted, 30.09.20, HEBT Setup, 06.10.20, Accepted, 8.10.20, I.Pongrac 
 
Entry  Fri Feb 14 13:34:54 2020, Cristina, test with bakeout, Berrilium Copper Stripes Dermati, 14.02.2020, On schedule, 14.02.2020, 14.02.2020, DONE, Not Needed, 17.02.2020; 11:30 am, Setup 1, 24.02.2020, Cond. Accep., 26.02.2020, Bardonner 
 
Entry  Wed Feb 19 11:42:59 2020, Cristina, pumping speed, TMP Cryring (Nikita), KW8, On schedule, KW8, 19.02.2020, DONE, Refused, 9.03.2020, Fischer-Mommsen, 16.03.2020, Accepted, 29.05.2020, Nikita pumpingspeed.jpg
 
Entry  Tue Mar 3 09:34:40 2020, Cristina, Coating, SPARC chambers , June 2019, Delayed, Febraury 2020, 12.02.2020, DONE, Accepted, 01.09.2020, Horizontal Coating Setup, 03.11.20, Accepted, 10.12.20, Track to Jülich 
HR11VU61 (21.09.20); HR18VU63 (06.10.20); HR19VU64 (26.10.20); HR12VU62(02.11.20)
Entry  Tue Mar 3 09:58:03 2020, Cristina, test with bakeout, Ferrite RI (as received), 15.March, On schedule, , 20.03.2020, DONE, Not Needed, 23.03.2020, Setup 1, 27.03.2020, Cond. Accep., --------, --------- 
 
Entry  Tue Mar 3 13:50:28 2020, Cristina, test with bakeout, Macor 4 -IPM Giacomini, KW10, On schedule, , 03.03.2020, DONE, Not Needed, 18.03.2020; 07:45 am, Mobile 2, 27.03.2020, Cond. Accep., 11.05.2020, T. Giacomini 
 
Entry  Wed Mar 4 10:06:09 2020, Phe, leak check, Transistion tube for SIS100 string test_Second test, Beginning 2020, Delayed, February, End of February, DONE, Accepted, 03.03.2020, Customised, 03.03.2020, Accepted, 5.03.2020, Ivan and Stefan (for integration @BNG) IMG-20200304-WA0001.jpg
 
Entry  Mon Mar 9 08:46:22 2020, Phe, test without bakeout, BPM SIS100 2010-3, repeat after long pumping @ Hackhalle, , On schedule, , 06.03.2020, DONE, Accepted, 09.03.2020; 07:00 am, Mobile 3, 10.03.2020, Accepted, 12.03.2020, M.Müller 
 
Entry  Thu Mar 12 13:47:38 2020, Phe, test without bakeout, BPM SIS100 2010-17 (only stainless steel after cleaning - no ceramic), Received , On schedule, , 12.03.2020, DONE, Not Needed, 12.03.2020; 11:55 am, Mobile 3, 17.03.2020; 11:00 am, Accepted, 19.03.2020, M.Müller 
 
Entry  Thu Mar 12 13:49:09 2020, Phe, test without bakeout, BPM SIS100 2010-17 (ceramic only), Received, On schedule, , 12.03.2020, DONE, Not Needed, 18.03.2020; 08:25, Setup 1, 19.03.2020; 11:00, Cond. Accep., 19.03.2020, M.Müller 
 
Entry  Thu Mar 19 11:23:38 2020, Phe, test without bakeout, BPM SIS100 2010-15 (after cryo), , On schedule, , 19.03.2020, DONE, Not Needed, 19.03.2020; 15:00, Mobile 3, 25.03.2020, Cond. Accep., 26.03.2020, M.Müller 
 
Entry  Wed Mar 25 14:22:40 2020, Phe, test without bakeout, Broken ceramic for BPM, , On schedule, , 25.03.2020, DONE, Not Needed, 26.03.2020, Setup 2, 27.03.2020, Cond. Accep., 28.03.2020, M.Müller 
 
Entry  Mon Apr 6 15:33:45 2020, Phe, test with bakeout, Unbaked Ferrites from RI (bigger size), , On schedule, , 06.04.2020, DONE, Not Needed, , Setup 1, 22.04.2020, Cond. Accep., ,  
 
Entry  Wed Apr 22 08:35:13 2020, Phe, test without bakeout, BPM 2010-15 - 2 weeks pump down in Hackhalle, , On schedule, , 21.04.2020, DONE, Not Needed, 21.04.2020; 17:00, Mobile 3, 24.04.2020, Accepted, 23.04.20, M.Müller 
 
Entry  Wed Apr 22 10:14:43 2020, Cristina, test with bakeout, Ceramic Tube for Cryring (Sieber, KW13, Delayed, 22.04.2020, 24.04.2020, DONE, Not Needed, 27.04.2020, Setup 2, 06.05.2020, Refused, 8.05.2020, T.Sieber 
 
Entry  Wed Apr 22 13:45:53 2020, Cristina, test without bakeout, p-linac dipoles, 20.04.2020, On schedule, , 20.04.2020, DONE, Accepted, 21.04.2020, HEBT Setup, 29.04.2020, Cond. Accep., 27.05.2020, Florian (Grossmontage) 
 
Entry  Fri Apr 24 09:56:27 2020, Cristina, test with bakeout, Be windows-Spillman, KW18, On schedule, , 28.04.2020, DONE, Not Needed, 26.05.2020, Setup 2, MEASUREMENTS STOPPED, , 02.10.20, Collegue Spillman 
 
Entry  Wed May 13 15:26:53 2020, Phe, test with bakeout, Big Baked Ferrites PLT 90/50/30 8C11 and Small baked Ferrites CMD5005, , On schedule, , 11.05.2020, DONE, Not Needed, 13.05.2020; 7:40 am, Setup 1, 25.05.2020, Cond. Accep., ---------, ----------- 
 
Entry  Tue May 19 09:20:24 2020, Cristina, test with bakeout, Ceramic parts Hillenbrand, 25.05.20, On schedule, , 25.05.2020, DONE, Accepted, 26.05.2020, Setup 1, 30.05.2020, Accepted, 09.06.2020, Hillenbrand 
 
Entry  Tue May 19 12:03:40 2020, Phe, Problem, Turbo Pump from Thomas Seiber, , On schedule, , KW19, DONE, Not Needed, 19.05.2020, Customised, 20.05.2020, Refused, 27.05.2020, Student from T.Sieber pump_Sieber.jpg
Die Pumpe hat den Fehlercode 088 und hat eine Störung des Axiallagersensors.(checked by Graziano)
Entry  Wed May 27 10:34:37 2020, Phe, test without bakeout, BPM SIS100 X2010-16, , , , KW21, DONE, Not Needed, 20.05.2020, Customised, 22.05.2020, Cond. Accep., 26.08.20, M.Müller 
 
Entry  Wed Jun 17 10:13:57 2020, Cristina, test with bakeout, IPM SIS18, End May, On schedule, , End May (the gewind had to be redone by Pfeiffer), DONE, Accepted, 17.06.2020 and restarted on the 22.06.2020 and restarted on 25.08.20, Customised, 31.08.20, Cond. Accep., 04.09.2020, Back to Tino G. 
 
Entry  Wed Jun 17 12:58:02 2020, Cristina, test without bakeout, SIS100 Dipole 07-6-016-4, ----, , ------, 17.06.2020, DONE, Accepted, 17.06.2020, HEBT Setup, 19.06.2020, Cond. Accep., 22.06.2020, brought back to the TH 
 
Entry  Fri Aug 28 11:51:30 2020, Phe, test without bakeout, SIS100 dipole 07-00009-020-01, , , , , DONE, Accepted, 26.08.20, HEBT Setup, 28.08.20, Refused, 1.09.20, in the TH 
 
Entry  Fri Aug 28 11:52:43 2020, Phe, test without bakeout, BPM SIS100 2010-61, , , , 26.08.20, DONE, Accepted, 26.08.20, Mobile 3, 28.08.20, Cond. Accep., 09.09.20, S. Fiedler 
 
Entry  Fri Sep 11 09:56:40 2020, Cristina, test without bakeout, BPM SIS100 X2010-63, , , , , DONE, Accepted, 31.08.2020, Mobile 3, 01.09.20, Accepted, 09.09.20, S. Fiedler 
 
Entry  Fri Sep 11 09:59:20 2020, Cristina, test without bakeout, Bellows IPM SIS18, , , , 01.09.2020, DONE, Refused, 02.09.2020, HEBT Setup, 03.09.2020, Refused, 11.09.2020, Zentrale Dienst (back to Giacomini) 
 
Entry  Fri Sep 11 10:07:46 2020, Cristina, test with bakeout, Nuts company TwinNut, , , , , DONE, Accepted, 01.09.2020, Mobile 2, 10.09.2020, Accepted, ------, -------- 
 
Entry  Fri Sep 11 10:13:59 2020, Cristina, test without bakeout, Cecom diagnostic chamber HEBT, , , , 01.09.2020, DONE, Accepted, 02.09.2020, Setup 1, 04.09.2020, Cond. Accep., 23.09.20, M.Müller 
 
Entry  Mon Sep 14 09:15:03 2020, Cristina, test without bakeout, BPM SIS100 2010-17, , , , 09.09.20, DONE, Accepted, 09.09.2020, Mobile 3, 10.09.2020, Cond. Accep., 17.09.2020, M. Müller 
 
Entry  Mon Sep 14 09:16:54 2020, Cristina, test with bakeout, Mirror Laser cooling SIS100, , , , 14.09.2020, DONE, Accepted, 6.10.20, Mobile 2, 21.10.20, Cond. Accep., KW47, D.Winters 
 
Entry  Mon Sep 14 10:38:59 2020, Cristina, test without bakeout, Test on Viton gasket, , , , 14.09.2020, TO DO, Not Needed, , , , , ,  
 
Entry  Tue Sep 15 11:14:44 2020, Cristina, leak check, SIS100 Dipole chambers, , , , , on-going, , July 2019, Customised, , , ,  
07-00006-001-0; 07-00006-002-7; 07-00006-003-4; 07-00006-004-1; 07-00006-005-8; 07-00006-006-5; 07-00006-007-2; 07-00006-009-6; 07-00006-010-2; 07-00006-011-9; 07-00006-012-6; 07-00006-013-3; 07-00006-014-0; 07-00006-016-4 (mit RGA); 07-00006-017-1; 07-00006-018-8; 07-00006-019-5; 07-00006-020-1 (mit RGA); 07-00006-022-5; 07-00006-023-2; 07-00006-024-9; 07-00006-026-3; 07-00006-028-7; 07-00006-033-1; 07-00006-048-5; 07-00006-036-2;07-00006-049-2; 07-00006-042-3; 07-00006-046-1;07-00006-040-9;07-00006-053-9;07-00006-039-3; 07-00006-050-8; 07-00006-047-8;07-00006-015-7; 07-00006-021-8;07-00006-025-6;07-00006-027-0;07-00006-034-8;07-00006-035-5;07-00006-049-2; 07-00006-046-1; 07-00006-047-8; 07-00006-045-4; 07-00006-044-7; 07-00006-055-3; 07-00006-054-6; 07-00006-051-5; 07-00006-059-1; 07-00006-041-6; 07-00006-065-2; 07-00006-038-6;07-00006-030-0; 07-00006-037-9; 07-00006-031-7;07-00006-032-4; 07-00006-056-0; 07-00006-057-7; 07-00006-052-2; 07-00006-069-0; 07-00006-060-7; 07-00006-072-0; 07-00006-058-4; 07-00006-067-6;07-00006-070-6; 07-00006-066-9;07-00006-062-1
Entry  Mon Sep 21 11:31:47 2020, Cristina, test without bakeout, HEBT BPM, KW39, On schedule, , 28.09.20, on-going, Accepted, 05.10.20. Test started again: 08.12.20, Mobile 3, , Refused, ,  
Since 19. Okt we wait for the decision of the diagnostic group on how(who has to clean the BPM. Since then the test is stopped. Meeting on the 2.12.20: The japanise company will clean a BPM and they will send us to be tested. Email from Dorn on the 07.12.20: we have to test the other 3 BPM, and later they will take care of the cleaning of the refused BPM. On the 7.12 we tested another BPM: dirty. We sent on the 14.12 an email to Dorn and Kowina, showing that the ceramic are dirty and that they make dirty also our reference chamber. Measurement stopped again.
Entry  Mon Sep 21 11:32:46 2020, Cristina, test with bakeout, Ferrite RI after firing, , , , 18.09.20, DONE, Accepted, 22.09.2020, Setup 1, 1.10.20, Accepted, ---------, --------- 
 
Entry  Mon Sep 21 11:39:27 2020, Cristina, test without bakeout, Steel with epoxy glue, August 20, Delayed, , 21.09.20, DONE, , 22.09.2020, , 03.10.20, Refused, ?, ? 
 
Entry  Mon Sep 21 14:26:53 2020, Cristina, leak check, Beam line CWT, , , , 21.08.20, , , 21.09.20, Customised, 23.09.2020, Accepted, 24.09.20, S.Wilfert 
 
Entry  Wed Sep 30 13:39:48 2020, Cristina, test with bakeout, Tube CCC Cryring, , , , 30.09.2020, DONE, Accepted, 5.10.20, Setup 1, 07.10.20, Accepted, 8.10.20, T. Sieber 
 
Entry  Tue Oct 13 07:54:31 2020, Phe, test without bakeout, Epoxy - baked in the oven @ 80 deg C, 09.10.2020, On schedule, , 09.10.2020, DONE, Not Needed, 22.10.20, Mobile 2, 29.10.20, Refused, ,  
 
Entry  Wed Oct 21 10:51:47 2020, Cristina, test with bakeout, IPM SIS18 mit diagnostic parts, , , , 25.09.2020, DONE, Refused, 20.10.20, , 29.10.20, Cond. Accep., 2.11.20, Grossmontage 
 
Entry  Tue Nov 3 09:55:20 2020, Cristina, test with bakeout, MCPs for IPM SIS18, September, Delayed, , 2.11.20, DONE, Accepted, 2.11.20, Setup 1, 09.11.2020, Cond. Accep., 10.11.2020, T.Giacomini 
 
Entry  Tue Nov 17 09:43:55 2020, Cristina, test without bakeout, BPM 2010-16, , , , ?, DONE, Accepted, 16.11.20, Mobile 3, 17.11.20, Cond. Accep., 01.12.20, Grossmontage 
 
Entry  Thu Nov 19 10:15:23 2020, Cristina, Coating, Parts for Cryring , , , , Beginning October 20, DONE, Accepted, 16.11.20, Horizontal Coating Setup, 17.11.20, Accepted, 26.11.20, David (Cryring) 
There are some parts which were not coated: 2 bellows (the Cryring people still did not receive them from the company) and a T-piece, which was brought to the cleaning on the 20 of October and it is not yet ready.
Entry  Thu Nov 19 10:17:06 2020, Cristina, Coating, Coating chamber Glorius, , , , 16.11.20, DONE, Accepted, 27.11.20, Horizontal Coating Setup, 3.12.20, Accepted, 14.12.20, Glorius 
 
Entry  Mon Nov 30 11:14:30 2020, Cristina, Coating, T-piece Cryring, Oct, , , KW48, DONE, Accepted, 26.11.20, Horizontal Coating Setup, 3.12.20, Accepted, 10.12.20, Nikita 
 
Entry  Mon Nov 30 11:15:48 2020, Cristina, test with bakeout, Antrieb for ESR-Beata, 1 Dec., Delayed, ?, 3.12.20, DONE, Not Needed, 3.12.20, Setup 1, 10.12.2020, Accepted, 11.12.20, Müller 
 
Entry  Mon Nov 30 11:17:49 2020, Cristina, leak check, 5 x SIS100 Diagnostic Chambers, KW 49, , , , DONE, Not Needed, 01.12.20, , 16.12.20, Accepted, ,  
06-00401-099-1 (abgeholt on the 07.12 M.Müller); 06-00401-100-4 (abgeholt 09.12.20 Müller); 06-00401-101-1; 06-00401-103-5
Entry  Tue Dec 1 11:49:07 2020, Cristina, test with bakeout, Bellows IPM SIS18-Second measurement after cleaning, , , , 12.10.20, DONE, Not Needed, 12.10.20, HEBT Setup, 14.10.20, Accepted, 15.10.20, Zentrale Dienst  
 
Entry  Tue Jan 12 12:48:45 2021, Cristina, test without bakeout, HEBT BPM-Cleaned @Kyocera, Beginning 21, On schedule, , 12.01.21, DONE, Accepted, 12.01.21, Mobile 3, 14.01.21, Accepted, 19.01.21, M.Müller 
 
Entry  Wed Jan 20 11:48:54 2021, Cristina, test without bakeout, HEBT BPM cleaned @GSI, , , , 19.01.21, DONE, Accepted, 20.01.21, Mobile 3, 21.01.21, Refused, 24.02.21, M.Müller 
 
Entry  Fri Jan 29 11:50:13 2021, Cristina, General, Pillow seals SFRS, , , , 14.01.21, DONE, Accepted, 18.01.21, Customised, 26.02.21, Cond. Accep., 12.03.21, Cristos 
 
Entry  Fri Jan 29 11:52:53 2021, Cristina, pumping speed, NEG strips CRYRing, , , , End Dec 20, DONE, Accepted, 25.01.21, Fischer-Mommsen, 17.02.2021, Accepted, 02.03.21, Nikos 
 
Entry  Fri Jan 29 11:54:20 2021, Cristina, leak check, Gate Valve, , , , 14.01.21, DONE, Accepted, 28.01.21, Customised, 28.01.21, Refused, 29.01.21, A.Tauschwitz 
 
Entry  Fri Jan 29 11:55:45 2021, Cristina, General, Lower pressure of primary pumps, , , , Dec 20, DONE, Accepted, 18.01.21, Customised, 22.01.21, Accepted, -----, G.Savino 
 
Entry  Mon Feb 1 16:04:00 2021, Phe, test with bakeout, Antriebe SIS100, , On schedule, , 01.02.2021, DONE, , 02.02.2021, Setup 1, 10.02.2021, Accepted, 11.02.21, M.Müller 
 
Entry  Wed Feb 3 11:47:32 2021, Cristina, leak check, CARME vacuum chamber, Dec 2020, Delayed, , 02.02.2021, DONE, Accepted, 02.02.2021, Customised, 02.202.2021, Accepted, 03.02.2021, N.Petridis 
 
Entry  Wed Feb 3 11:50:09 2021, Cristina, test with bakeout, Detector Pockets for scintillators SIS18, , , , 02.02.2021, on-going, , 08.02.21, HEBT Setup, 11.03.21, Cond. Accep., 12.03.21, M.Müller 
 
Entry  Wed Feb 17 11:30:26 2021, Cristina, test without bakeout, CECOM diagnostic chamber, 1.02.21, , , 17.02.21, DONE, Accepted, 18.01.21, Customised, 19.02.21, Cond. Accep., ,  
 
Entry  Wed Feb 17 11:31:08 2021, Cristina, test without bakeout, SIS100 BPM, , , , 15.02.21, DONE, Accepted, 16.02.21, , 18.02.21, Accepted, 24.02.21, M.Müller 
 
Entry  Wed Feb 17 11:50:45 2021, Cristina, leak check, SIS100 HF Cavities, , , , 15.02.21, DONE, Accepted, 15.02.21, Customised, 16.02.21, Accepted, 17.02.21, In Weitestadt 
 
Entry  Fri Feb 19 08:39:57 2021, Cristina, , HEBT BPM cleaned @GSI-second measurement, , , , 10.02.21, DONE, Accepted, 10.02.21, Customised, 18.02.21, Accepted, 24.02.21, M.Müller 
 
Entry  Fri Feb 19 08:41:46 2021, Cristina, leak check, 2x Cryostats-Kujouharov, 1.02.21, , 11.02.21, 11.02.21, DONE, , 12.02.21, Customised, 02.03.21, Cond. Accep., 09.03.21, Kojouharov 
 
Entry  Wed Feb 24 13:50:25 2021, Cristina, leak check, Cavity for DALINAC, 22.02.21, Delayed, 01.03.21, 09.03.21, DONE, Not Needed, 10.03.21, Customised, 11.03.21, Cond. Accep., 18.03.21, Dmytriiev D. 
The cavity is dirty und must be cleaned
Entry  Wed Feb 24 13:51:01 2021, Cristina, test with bakeout, 3D printed tube per pLinac, 01.03.21, , , 08.03.21, DONE, Accepted, 16.03.21, Setup 1, 18.03.21, Accepted, 18.01.21, Büro Andreas 
 
Entry  Wed Mar 10 12:11:04 2021, Cristina, test with bakeout, Viewports DN100 ESR, , , , 16.02.21, on-going, Not Needed, 16.02.21, Setup 1, 16.03.21, Cond. Accep., 26.03.21, R.Sanchez 
 
Entry  Thu Mar 18 11:40:02 2021, Cristina, test with bakeout, SIS100/HEBT Manipulator C.Dorn, , , , 17.03.21, DONE, Not Needed, 18.03.21, Setup 1, 24.03.21, Accepted, 29.03.21, M.Müller 
 
Entry  Wed Apr 28 10:05:13 2021, Cristina, test without bakeout, SIS100 pumping chambers -after cleaning by the Company, , , , 23.04.21, on-going, Accepted, 26.04., Customised, 21.05.21, Cond. Accep., ,  
5 chambers checked: 07-00052-05-3; 06-00052-06-0; 07-00052-02-2; 07-00052-03-9; 07-00052-04-6
Entry  Wed Apr 28 10:21:27 2021, Cristina, test without bakeout, Cecom after cleaning, , , , 06.04.21, DONE, Not Needed, 06.04.21, Customised, 08.04.21, Accepted, 12.05.21, M.Müller 
 
Entry  Wed Apr 28 10:23:18 2021, Cristina, test without bakeout, 3Dprinting Copper coated sample, , , , 25.03.21, DONE, Not Needed, 25.03.21, , 26.03.21, Cond. Accep., ,  
 
Entry  Wed Apr 28 10:28:18 2021, Cristina, test without bakeout, Ceramic for SIS100 BPM, , , , 22.03.21, DONE, , 22.03.21, Mobile 3, 29.03.21, Accepted, , M.Müller 
 
Entry  Wed Apr 28 10:30:54 2021, Cristina, test with bakeout, HEBT Antrieb (in-kind Slovenia) 06-0050-39-54, , , , 23.04.21, DONE, Not Needed, 26.04.21, Setup 1, 03.05.21, Accepted, 06.05.21, M.Müller 
 
Entry  Tue May 18 10:50:26 2021, Cristina, test with bakeout, HEBT Antrieb 06-0050-036-40, , , , 06.05.21, DONE, Not Needed, 06.05.21, Setup 1, 12.05.21, Accepted, 17.05.21, M.Müller 
 
Entry  Tue May 18 14:10:04 2021, Cristina, test without bakeout, Trafos BPM, , , , 12.05.21, DONE, Not Needed, 18.05.21, Customised, 21.05.21, Refused, 07.06.21, M.Müller 
 
Entry  Tue May 18 14:11:08 2021, Cristina, test without bakeout, BPM CID: 06005002605, , , , 18.05.21, DONE, , 19.05.21, Mobile 3, 21.05.21, Cond. Accep., 07.06.21, M.Müller 
 
Entry  Fri May 21 13:29:15 2021, Cristina, test with bakeout, 2xDN63 windows for ESR , , , , 20.05.21, DONE, Not Needed, 18.05.21, Setup 1, 02.06.21, Accepted, 18.06.21, R.Sanchez 
 
Entry  Tue Jun 8 10:19:14 2021, Cristina, test without bakeout, Dipole Module, , , , 25.05.21, DONE, Not Needed, 25.05.21, Customised, 27.07.21, Cond. Accep., TH, F.Kaether 
 
Entry  Tue Jun 8 10:27:49 2021, Cristina, test with bakeout, Mirror system ESR-Brandau, 07.06.21, Delayed, , 21.06.21, DONE, Not Needed, 25.06.21, Mobile 2, 13.07.21, Cond. Accep., 24.09.21, Brandau 
 
Entry  Tue Jun 8 10:28:46 2021, Cristina, test with bakeout, Pockets for ESR, KW25, , , 21.06.21, DONE, Not Needed, 24.06.21, Setup 1, 12.07.21, Accepted, 19.07.21, Glorious 
 
Entry  Mon Jun 14 11:48:43 2021, Cristina, test with bakeout, Antrieb für SIS100, , , , 07.06.21, DONE, Not Needed, 14.06.21, Setup 1, 22.06.21, Accepted, 28.06.21, M.Müller 
 
Entry  Thu Jun 24 12:05:07 2021, Cristina, test with bakeout, Bearings for HEBT-foil-stripper -Zeller, KW26, , , 01.07.21, DONE, Not Needed, 14.07.21, Mobile 2, 05.08.21, Refused, ,  
 
Entry  Thu Jun 24 12:06:49 2021, Cristina, test with bakeout, Test for polymide coated sample- Fischer, , , , , DONE, , 2.07.21, HEBT Setup, 6.07.21, Cond. Accep., 8.07.21, L.Fischer 
 
Entry  Thu Jun 24 12:07:27 2021, Cristina, test with bakeout, Injection Septa SIS100, , , , 21.06.21, DONE, Not Needed, 23.06.21, Customised, 14.07.21, Cond. Accep., 19.07.21, Report sent to I.Pongrac (Component in TH) 
 
Entry  Mon Jul 12 13:45:55 2021, Cristina, test with bakeout, BPM SIS100, , , , 09.07.21, DONE, Not Needed, 13.07.21, Mobile 3, 14.07.21, Cond. Accep., 20.07.21, R.Mahr 
 
Entry  Mon Jul 12 13:46:30 2021, Cristina, test without bakeout, Experimental Chamber, 5.07.21, , , 14.07.21, DONE, , 15.07.21, Customised, 22.07.21, Cond. Accep., 26.07.21, Bömsch 
 
Entry  Mon Jul 12 13:47:03 2021, Cristina, test without bakeout, Trafos for isolation vacuum-Piotr, , , , 02.07.21, DONE, Not Needed, 07.07.21, Mobile 3, 12.07.21, Refused, 19.08.21, P. Kowina 
 
Entry  Wed Jul 14 14:09:31 2021, Cristina, test with bakeout, Profil Gitter for HEBT, , , , 09.07.21, DONE, Not Needed, 14.07.21, Setup 1, 19.07.21, Cond. Accep., ,  
 
Entry  Thu Aug 19 09:53:54 2021, Cristina, test with bakeout, MCP for ESR-Giacomini, , , , 05.08.21, DONE, Not Needed, 11.08.21, Setup 1, 17.08.21, , 17.08.21, F. Wolf 
 
Entry  Thu Aug 19 09:58:04 2021, Cristina, , Profil Gitter for HEBT, , , , , DONE, Not Needed, 14.07.21, , 19.07.21, Refused, ,  
 
Entry  Thu Aug 19 10:00:46 2021, Cristina, , BPM Kyocera (8 pieces), 28.07.21, , , 30.07.21, DONE, Not Needed, 02.08.21, Mobile 3, 28.08.21, Accepted, 31.08.21, F.Wolf 
 
Entry  Fri Aug 20 09:21:08 2021, Cristina, test with bakeout, Diagnostic chambers (2), , , , 19.08.21, DONE, Not Needed, 14.09.21, Customised, 25.09.21, Cond. Accep., 02.11.2021, M. Mueller 
 
Entry  Wed Sep 15 10:29:42 2021, Cristina, test with bakeout, Al chamber, , , , , DONE, Not Needed, 02.09.21, Mobile 3, 13.09.21, Accepted, 16.09.21, N.Staldmann 
 
Entry  Tue Sep 21 11:38:16 2021, Phe, test without bakeout, Kyocera ceramics - 4x, , On schedule, , 21.09.2021, DONE, , 23.09.21, Mobile 3, 15.10.21, Accepted, ,  
 
Entry  Tue Sep 28 11:55:07 2021, Cristina, test without bakeout, BPM with ceramic, , , , 12.09.21, DONE, Not Needed, 14.09.21, Mobile 3, 16.09.21, Refused, 28.09.21, M.Müller 
 
Entry  Wed Oct 20 11:25:04 2021, Phe, test without bakeout, BPM Chambers - 2x, , On schedule, , 20.10.2021, DONE, Not Needed, 21.10.21, , 27.10.21, Cond. Accep., 02.11.21, M.Mueller 
 
Entry  Tue Nov 2 09:06:05 2021, Phe, test without bakeout, Cecom chamber for FAT K2030-1123, 06004016122, , On schedule, , , on-going, , , , , , ,  
 
Entry  Mon Nov 8 15:10:43 2021, Phe, test with bakeout, SIS100 bunch compressor with ceramic gap, , On schedule, , 08.11.2021, DONE, Not Needed, 25.11.21, Setup 1, 01.12.21, Accepted, ,  
 
Entry  Wed Nov 17 11:46:15 2021, Cristina, test with bakeout, Coated Al sheet metall bent (Brandau), , , , 5.11.21, DONE, Not Needed, 8.11.21, Setup 1, 15.11.21, Cond. Accep., 03.02.22, R.Sanchez 
 
Entry  Wed Nov 17 11:48:30 2021, Cristina, test without bakeout, Fluorescence chamber SIS100, , , , 12.11.21, DONE, Accepted, 17.11.21, Mobile 3, 18.11.21, Accepted, ,  
 
Entry  Wed Nov 17 11:50:00 2021, Cristina, leak check, SIS100 bunch compressor, , , , 15.11.21, DONE, Not Needed, 16.11.21, Customised, 17.11.21, Accepted, ,  
 
Entry  Wed Nov 17 11:51:00 2021, Cristina, test with bakeout, Second SIS100 injection Septa , , , , , DONE, Not Needed, 11.11.21, Customised, 19.11.21, Cond. Accep., ,  
 
Entry  Thu Dec 2 11:08:38 2021, Cristina, test without bakeout, BPM, , , , 30.11.21, DONE, Not Needed, 02.12.21, Mobile 3, 06.12.21, Accepted, 23.02.22, M.Müller 
 
Entry  Thu Dec 9 11:41:47 2021, Cristina, test with bakeout, Tube with ceramic gap- resistence study, , , , 03.12.21, DONE, Not Needed, 06.12.21, Setup 1, 09.12.21, , Dec 21,  
 
Entry  Thu Dec 9 11:42:50 2021, Cristina, test without bakeout, BPM, , , , 07.12.21, DONE, Not Needed, 09.12.21, Mobile 3, 13.12.21, Cond. Accep., 17.12.21, Müller 
 
Entry  Wed Jan 12 08:40:00 2022, Cristina, , Windows for ESR, , , , 10.01.22, DONE, Not Needed, 13.01.22, Setup 2, 21.10.22, Cond. Accep., 03.02.22, R.Sanchez 
 
Entry  Wed Jan 12 08:40:41 2022, Cristina, , XHU detector ESR, , , , 16.12.21, DONE, Not Needed, 12.01.22, Setup 1, 26.01.22, Cond. Accep., 24.02.22, D.Winters 
 
Entry  Tue Jan 18 08:50:13 2022, Cristina, test with bakeout, Mirror chamber ESR (Brandau), , , , 16.01.22, DONE, Not Needed, 17.01.22, Customised, 31.01.22, Cond. Accep., 31.01.22, ESR 
 
Entry  Tue Jan 18 08:51:15 2022, Cristina, test without bakeout, Grids for pLinac (Siebert), 07.01.22, , , 17.01.22, DONE, Not Needed, 19.01.22, HEBT Setup, 31.01.22, Cond. Accep., 31.01.22, T.Sieber 
 
Entry  Wed Feb 9 14:19:51 2022, Cristina, test without bakeout, CECOM chamber, , , , KW5, DONE, Not Needed, 08.02.2022, Customised, 09.02.22, Accepted, , M.Müller 
 
Entry  Tue Feb 15 09:56:13 2022, Cristina, test without bakeout, NTG chamber HEBT special installation, , , , 03.02.22, DONE, Not Needed, 10.02.22, Customised, 14.02.22, Cond. Accep., 25.06.22, S.Zeller 
 
Entry  Fri Feb 25 09:36:32 2022, Cristina, test with bakeout, Grid+manipolator, , , , KW7, DONE, , 23.02.22, Setup 1, 11.03.22, Accepted, ,  
 
Entry  Fri Feb 25 09:37:36 2022, Cristina, test without bakeout, 2 BMP, , , , 23.02.22, DONE, , 28.02.22, Mobile 3, 04.03.22, Accepted, 04.03.22, M.Müller 
 
Entry  Tue Mar 15 14:06:51 2022, Cristina, , Indian diagnostic chamber, , , , 11.03.22, DONE, Not Needed, 15.03.22, Customised, 16.03.22, Accepted, ,  
 
Entry  Tue Mar 22 11:27:51 2022, Cristina, test with bakeout, SIS100 Qpole, , , , , on-going, Not Needed, 22.03.22, Customised, , , ,  
 
Entry  Mon Mar 28 11:50:59 2022, Cristina, test without bakeout, Missing dipole, , , , 28.03.22, TO DO, , , , , , ,  
 