1
|
Fri Jul 30 10:21:27 2021 |
Rodolfo | Laser | Kink |
The laser beamline in the ESR north arc has a knik, therefore the laser beam can not get the "laser tower" in the north east arc. This path is used to get the laser beam up to the electron-cooler side, such that the laser beam co-propagates the ion beam.
In order to try fix this, Markus suggested to get in contact with Herr Kredel (Groß Montage). He will be back from holidays on August 11th (2021). |
Attachment 1: Laser_beamline_ESR_NordBogen.jpg
|
|
2
|
Fri Apr 22 09:38:24 2022 |
Rodolfo | Laser | getting ready for Fluorescein548 |
We are going to change dye. Therefore I have take out the DCM-dye-solution* out of the dye circulators, rinsed them with Ethanol (5 times) and put new filters.
* This was a solution of 0.3 g/l in 1:1 solvent mixture of Ethanol and DMSO. |
3
|
Mon Apr 25 18:47:12 2022 |
Rodolfo | Laser | New dye circulators |
I have put into operation the new circulators (SN. 182231, 182201) for our dye laser (the Cobra). I have rinsed them with pure Ethanol first and I have not seen any leaks.
The idea is to use these circulators with either Pyrromethene 597 or a combination of (Rhodamin B + Rhodamin 101).
The "old circulators" (SN. 104830, 104801) will be used together with (Fluorescein 27 + NaOH). |
Attachment 1: Neue_Cobra-Farbstoffpumpe.jpg
|
|
4
|
Mon Apr 25 21:47:28 2022 |
Rodolfo | Laser | green instead UV |
I am exchanging the optical elements (mirrors and lenses) for the laser spectroscopy on bismuth. At some places I am also exchanging the 3"-mirror holders and installing 2"-mirror holders instead.
* Just in case. The "nice" laser profile comes from a laser pointer from Thorlabs (CPS532). The Cobra is still under construction. |
Attachment 1: Libelle_Umtausch_GrüneOptik.jpg
|
|
Attachment 2: Umtausch_Spiegel_2statt3.jpg
|
|
5
|
Tue Apr 26 16:28:14 2022 |
Carsten | DAQ | Cable of Bunch HF disconnected and 1.995Mhz signal connected for DAQ tests |
see subject. |
6
|
Tue Apr 26 18:15:19 2022 |
Rodolfo | Detectors | XUV-Detector and Cu-Mirror |
Concerning the moveable detectors:
- I have switched off the power supply and cooling (heat exchanger) for the Cu-mirror.
- The heat exchanger for the XUV-detector is still ON. The water level in the heat exchanger is still OK. |
7
|
Fri Apr 29 21:18:12 2022 |
Rodolfo & Max | Laser | Fluorescein 27, Rh 610 + Rh 640 |
We (Max and Rodolfo) have tested the dyes. I have prepared the dye-solutions according to the recipes given in Sirah's User Manual.
The seed energy for the Cobra was 520 mJ @ 532 nm. The output energy after the Cobra's main amplifier was:
Fluorescein 27 (to be used for 208Bi):
Wavelength [nm] | Energy [mJ]
|
545 | 58
|
548 | 64
|
550 | 62
|
555 | 58
|
560 | 51
|
Rhodamin 610 + Rhodamin 640 (potential candidate to be used for 209Bi):
Wavelength [nm] | Energy [mJ]
|
600 | 65
|
605 | 98
|
610 | 104
|
615 | 103
|
620 | 97
|
625 | 82
|
* All values averaged over 500 laser pulses. |
8
|
Wed May 4 22:45:12 2022 |
Carsten, Sebastian | DAQ | Q-Switch Signal (ch15) fixed |
The "dead" Q-Switch signal was converted
two times... This explains why in the
Thorium experiment the Q-Switch signal
(ch15) was empty.
First conversion from TTL to NIM in the
ESR Laserlab and unfortunately the signal
was plugged in a second Level Adapter as
TTL in
the Messhütte and was "again" converted
into a NIM for DAQ1/2.
Now the Q-Switch is converted from TTL to
NIM in the ESR Laserlab. The NIM is
afterwards guided through a Logic Fan
In/Out to the 2 DAQs. |
9
|
Wed May 4 22:55:37 2022 |
Rodolfo, Sebastian | Laser | FCU / Temp Control Bug |
We found a "Bug" in the control of the Sirah dye system.
Due that we don't use the FCU and the temperature control unit we could not start the Sirah software without getting numerous errors.
The fix was to plug in the BBO oven again, move the FCU to "origin", than move to a specific location that the FCU goes in an "idle" mode.
Than the Sirah software can be started again without getting erros. |
10
|
Wed May 4 22:56:22 2022 |
Rodolfo, Sebastian, Konstantin | Laser | Laser step complete, scan complete fixed |
"Laser step complete" and "laser scan complete" are working again.
Problems:
1) Connections were wrong in the Software.
2) Sometimes the connection to "laser scan complete" was lost (Wackelkontakt).
3) The VI was initialized with the wrong LabJack Channels.
Now:
1) fixed connections in the software.
2) switch to an other "channel" of the LabJack device for "laser scan complete".
3) The channels in the Cobra VI are for...
laser scan complete -> Channel 5
laser step complete -> 6
We definetely should keep an eye and check frequently the signals, that we do not have a lost connection (Wackelkontakt) again of these 2 channels. |
11
|
Thu May 5 15:24:34 2022 |
Sebastian | Laser | laser busy problem |
Current status:
Laser busy signal works correctly (5V if the grating moves, 0V if not) if the laser is operated by the Sirah software.
When the laser is controled by the "Thorium Main VI" the laser busy signal is always 0V. |
12
|
Fri May 6 10:30:23 2022 |
Sebastian | DAQ | laser busy / dye out signal fixed |
Solution for a working laser busy / dye out signal was to disable the FCU and set the FCU status to "False" (see attached picture).
Remark: FCU unit will not be used for Bismuth experiment! |
Attachment 1: CobraFix_LaserBusy.PNG
|
|
13
|
Fri May 6 10:35:06 2022 |
Sebastian | DAQ | laser step complete cabling changed |
I changed the laser step complete cabling from a quad coinc (see attached picture) to a Logic Fan In / Fan out (same as laser scan complete).
The "detour" through the quad coinc yielded to a very short laser step complete signal of ~500ns...
Due to the change it is now ~15µs long and has the same length as the laser scan complete signal (~15µs). |
Attachment 1: stepComplete_beforeChange_QuadCoincCabling.PNG
|
|
14
|
Fri May 6 16:29:03 2022 |
Simon, Patrick | Detectors | PMT preparation |
We changed PMT north and PMT south and tested them at 1500 V.
Both new PMTs are broadband.
PMT north and middle see between 2 and 7 kHz signal rate with a threshold close to the background noise.
PMT south still has the plastic cap on and is intended to be used as a reference for electro-magnetic disruptions. No signal was seen at 1500 V.
We fixed the signal cable of PMT south to the NIM-crate to get rid of background noise picked up by the cable. |
15
|
Fri May 6 16:41:57 2022 |
Patrick, Rodolfo | Laser | Wavemeter |
We coupled the laser through a multi-mode fiber into the wavemeter.
With the main amplifier enabled, we got enough power behind the fiber (0.5 - 1.5 mW) to use the wavemeter with 34 ms exposure time (1s / 30Hz to prevent jumps in the wavemeter readout).
Pictures below:
1: First test scan with 34ms exp. time.
2: Comp. too large laser power (2. scan duoblet) vs. attenuated power (right scan doublet). The latter has less hickups.
3: Laser scan with attenuated power in go4.
The measured frequencies in the first scan step are unstable in any case.
Spikes (rather "second wavelength the laser is regulrarly jumping to") can be removed by adjusting the fiber coupling with the mirrors (change of interference pattern) or the L/2-waveplate (change of coupled power).
However, during (and after) the scan the spikes seem to reappear. |
Attachment 1: Screenshot_(4).png
|
|
Attachment 2: Bi2022_laserscan_test.PNG
|
|
16
|
Mon May 9 09:43:08 2022 |
Zoran | Accelerator | ESR Beam |
The main control room started setting up the Bi beam this morning, but quickly stopped in order to solve some problems around the UNILAC. Therefore we
should not plan to receive ions earlier than late in the evening on Monday, or probably Tuesday during the day. |
17
|
Mon May 9 11:45:57 2022 |
Wilfried, Jon, Sebastian | General | HV Divider position & DMM calibration |
We performed an autocalibration (attached picture 1) of the Keysight 34465A DMM (TUD Keysight).
The position and the "cabling" to the cooler platform was also adjusted (picture 2,3). |
Attachment 1: DMM_calibration.PNG
|
|
Attachment 2: dividerPosition.PNG
|
|
Attachment 3: dividerPosition1.PNG
|
|
18
|
Mon May 9 13:48:20 2022 |
Rodolfo | Laser | Laser for H-like 209Bi |
I have changed the dye to Rhodamin 610 + Rhodamin 640. The Cobra wavelength can be tuned now from 600 to 630 nm.
The current wavelength is set to 605 nm. |
19
|
Mon May 9 16:58:41 2022 |
Carsten | Detectors | Voltage particle dectectors NA_SZ und SA_SZ switched on |
Voltage SA_SZ (capture behind cooler): 1500 V (thin plastic scintillator)
Voltage NA_SZ (capture behind target): 750V (thick plastic, short absorption length)
Voltages and thershholds from thorium run, still to be verified. |
20
|
Mon May 9 17:01:02 2022 |
Carsten | DAQ | directories / paths / comments / reduction factors /startup.scom files for the 2 DAQs |
DAQ1 (original):
-user atplaser
-runs on lxg1050
-data in lxg1297:/data.lcoal2/208Bi
-go4 in ~/go4/208Bi
-mbs /esr/usr/atplaser/mbsrun/208Bi
Since the Go4 Code is still under development (clean up etc.), I still plan to submit regular updates, the last version before is always in ~go4/208Bi
It is planne that all essentialy settings can be done via the automatically loaded script files SetParamters.C and SetConditions.C, so that no recompilation (and change of code) is required (work in progress).
DAQ2 (new / enhanced):
additional 25ps TDC and ADC
-user stoe_exp
-runs on lxg0155
-data in lxg0155:/data.lcoal2/E128
-go4 in ~/E128
-mbs /esr/usr/stoe_exp/E128
There are no two different startup-files on each system (startup.scom and startup0.scom)
i.e. @startup0 in mbs -> Starts everything WITHOUT file writing
and @startup in mbs -> Starts everything WITH file writing (including onnect rfio and open file). For this, rawDispRFIO64, has to be started (locally __IN__ the data directory).
Please note that the different path and file names are on purpose, so that they can be distinguished after the run. |
21
|
Mon May 9 17:14:02 2022 |
Carsten | DAQ | NTCAP DAQ |
The NTCap DAQ computer in the HKR (Schottky logbook) is started, and all preparations for data taking (mounting of NAS etc.) are done.
Parameters for NTCAP DAQ will be adjusted as soon as beam is available. |
22
|
Mon May 9 17:16:34 2022 |
Carsten | Accelerator | Important: New ESR pattern - requies action for XUV detector in/out |
The ESR pattern is enhanced compared to the thorium experiment by additional machines that can be used for cooling/waiting in order to optimize 208Bi yield.
As a consequence, the sub chain numbers (previous: virtuelle Beschleuniger) are changed. The new numbers still have to be dialed in into the devices in the Messhütte and the automatic in/out of the XUV-detector tested- |
23
|
Mon May 9 19:05:17 2022 |
Wilfried | DAQ | Q-Switch signals + 0.5 ms and +1 ms in VUPROM |
We have generated two additional signals which are fed into two VUPROM channels:
Q-Switch + 0.5 ms --> channel 9
Q-Switch + 1.0 ms --> channel 10
(channel numbering 0-15)
The delays are generated by the two channels of a DGG222 |
24
|
Mon May 9 19:56:41 2022 |
Zoran | Accelerator | status Monday evening |
The main control room is setting up the SIS for extraction. At the moment there are 2.5E8 particles in the SIS. Later they will check the transport and the devices for the
ESR injection. The ESR operators might (! no info available) take over later in the evening, but there will definitely be no beam for the experiment before tomorrow morning.
=> the night shift will not take place, unless some laser adjustments need to be done (so far we see no problems)
=> the morning shift does not need to come at 6AM. My guess is that before the morning briefing at 8:30 there will be no news.
The ESR cave is closed again. Talk to the main control room if you need access. |
25
|
Tue May 10 09:05:19 2022 |
Zoran | Accelerator | status Monday evening |
> The main control room is setting up the SIS for extraction. At the moment there are 2.5E8 particles in the SIS. Later they will check the transport
and the devices for the
> ESR injection. The ESR operators might (! no info available) take over later in the evening, but there will definitely be no beam for the experiment
before tomorrow morning.
>
> => the night shift will not take place, unless some laser adjustments need to be done (so far we see no problems)
> => the morning shift does not need to come at 6AM. My guess is that before the morning briefing at 8:30 there will be no news.
>
> The ESR cave is closed again. Talk to the main control room if you need access.
Status SIS on Monday evening. ESR setting up starting on Tuesday morning. There is some prospect of getting more ions by setting up multi-multiturn
injection, however still uncertain. |
Attachment 1: 22-05-09_200006_20220509_170137_tcl1024_dcct.png
|
|
26
|
Tue May 10 11:40:55 2022 |
Sebastian | Accelerator | still no beam @ESR |
There is still no Beam in the ESR.
The beam is currently at TE3 - between SIS and ESR |
27
|
Tue May 10 11:59:45 2022 |
Simon, Christopher, Kristian, Sebastian | Laser | Labview VI checkups |
The lower limit (to position) of the Cobra control VI has to be one increment smaller.
This means for moving from 601,95 to 601,74 the "to position" has to be 601.735.
We also checked the displayed HV values in Go4 with the shown values of the HV VI.
Both values in go4 and in the VI show the same value and are changing "simultaneously" (depending on the refresh time of go4 and Labview). |
28
|
Tue May 10 15:26:35 2022 |
Rodolfo, Max | Laser | Laser stabilisation running |
It is now possible to stabilize and move the laser with both stages.
The software and hardware settings are attached.
For synchronizing with the laser pulse we use following frequency generator settings:
period: 200us
high: 5V
low: 0V
duty: 50%
The frequency generator is triggered with the external Q-switch trigger signal, that is in coincidence with the ESR HF.
To use the stabilization one has to use the external and NOT the q-switch mode of the laser. |
Attachment 1: MRC_Settings_for_Bismuth_10-05-2022.PNG
|
|
Attachment 2: MRC_hardware_Setting.PNG
|
|
29
|
Tue May 10 20:35:42 2022 |
Phillip, Wilfried, Max | Detectors | PMT Threshold |
Since we have ions in the ring now, we looked at the PMT thresholds and the widths. In order to do so we looked at the Raw Signal directly before the CFD and its output simultaneously. You can now set the threshold just above the noise. If the threshold is too low you will also see flat lines in the oscilloscope when triggered on the CFD output. New values:
PMT Mitte
---
Width: 200 -> 220 (60ns -> 90ns)
Threshold: 20 -> 5
PMT Nord
---
Width: 200 -> 220 (60ns -> 90ns)
Threshold: 12 -> 10
PMT Süd
---
blind. |
30
|
Tue May 10 21:41:17 2022 |
Rodolfo | Accelerator | T-Scraper |
The T-Scrapers at the electron cooler have an issue. They can't be moved in the horizontal direction using the DeviceControl. |
31
|
Tue May 10 22:29:45 2022 |
Jan Glorius | DAQ | DAQ2 shaper settings |
Attached are the MSCF shaper settings applied on Tue May 10 at 22:30. |
Attachment 1: setting_e128.v1
|
1652214506
Tue May 10 22:28:26 CEST 2022
e127pi:mrcc:mscf2:getGainCommon 15
e127pi:mrcc:mscf2:getShapingTimeCommon 0
e127pi:mrcc:mscf2:getThresholdCommon 200
e127pi:mrcc:mscf2:getPzCommon 255
e127pi:mrcc:mscf2:getGain1 15
e127pi:mrcc:mscf2:getGain2 10
e127pi:mrcc:mscf2:getGain3 15
e127pi:mrcc:mscf2:getGain4 15
e127pi:mrcc:mscf2:getShapingTime1 0
e127pi:mrcc:mscf2:getShapingTime2 0
e127pi:mrcc:mscf2:getShapingTime3 0
e127pi:mrcc:mscf2:getShapingTime4 1
e127pi:mrcc:mscf2:getThreshold1 255
e127pi:mrcc:mscf2:getThreshold2 3
e127pi:mrcc:mscf2:getThreshold3 4
e127pi:mrcc:mscf2:getThreshold4 255
e127pi:mrcc:mscf2:getThreshold5 222
e127pi:mrcc:mscf2:getThreshold6 2
e127pi:mrcc:mscf2:getThreshold7 20
e127pi:mrcc:mscf2:getThreshold8 255
e127pi:mrcc:mscf2:getThreshold9 2
e127pi:mrcc:mscf2:getThreshold10 10
e127pi:mrcc:mscf2:getThreshold11 255
e127pi:mrcc:mscf2:getThreshold12 255
e127pi:mrcc:mscf2:getThreshold13 100
e127pi:mrcc:mscf2:getThreshold14 255
e127pi:mrcc:mscf2:getThreshold15 255
e127pi:mrcc:mscf2:getThreshold16 255
e127pi:mrcc:mscf2:getPz1 100
e127pi:mrcc:mscf2:getPz2 100
e127pi:mrcc:mscf2:getPz3 100
e127pi:mrcc:mscf2:getPz4 100
e127pi:mrcc:mscf2:getPz5 100
e127pi:mrcc:mscf2:getPz6 100
e127pi:mrcc:mscf2:getPz7 100
e127pi:mrcc:mscf2:getPz8 100
e127pi:mrcc:mscf2:getPz9 100
e127pi:mrcc:mscf2:getPz10 100
e127pi:mrcc:mscf2:getPz11 100
e127pi:mrcc:mscf2:getPz12 100
e127pi:mrcc:mscf2:getPz13 100
e127pi:mrcc:mscf2:getPz14 100
e127pi:mrcc:mscf2:getPz15 100
e127pi:mrcc:mscf2:getPz16 100
e127pi:mrcc:mscf2:getSingleChMode 1
e127pi:mrcc:mscf2:getRcMode 1
e127pi:mrcc:mscf2:getAutoPZ 18
e127pi:mrcc:mscf2:getMultiplicityHi 8
e127pi:mrcc:mscf2:getMultiplicityLo 0
e127pi:mrcc:mscf2:getSumTrgThresh 18
e127pi:mrcc:mscf2:getBlrOn 1
e127pi:mrcc:mscf2:getCoincTime 121
e127pi:mrcc:mscf2:getThreshOffset 70
e127pi:mrcc:mscf2:getShaperOffset 35
e127pi:mrcc:mscf2:getBlrThresh 25
e127pi:mrcc:mscf2:getECLDelay 18
|
32
|
Tue May 10 22:37:10 2022 |
Jan Glorius | DAQ | DAQ2 cabling docu |
|
Attachment 1: e128_daq2_cabling.ods
|
33
|
Tue May 10 23:10:25 2022 |
Sebastian, Patrick, Volker, Guy | Accelerator | T-Scraper Reloaded |
We have established a Control to "manually" move the T-Scrapers via a "remote desktop". We can now move both scrapers in the horizontal direction too.
We are now T-scraping the ion beam for determining its position in the vertical and horizontal directions. |
34
|
Tue May 10 23:53:42 2022 |
Rodolfo | General | shift change |
The night shift took over. They are trying now to overlap the ion and laser beams. |
35
|
Wed May 11 01:09:07 2022 |
Patrick, Sebastian, Volker, Guy | Laser | Beam overlap |
We overlapped the laser with the ion beam.
The ion beam positions are:
device | move in dir. | scratch (mm) | gone (mm) | gone + 4.5 (mm) | x0 (mm)
|
GECEDS1VU | up | -3.0 | -2.7 | 1.8 |
|
| | | | |
|
GECEDS1HA | right | -21.9 | -20.9 | -16.4 | -4.7
|
| left | -12.0 | -13.1 | |
|
| | | | |
|
GECEDS2VU | up | -3.8 | -2.9 | 1.6 |
|
| | | | |
|
GECEDS2HA | right | -19.2 | -18.4 | -13.9 | in [-0.1, 4.3]
|
| left | -9.0 | -9.7 | |
|
We used the "gone + 4.5" column where the scraper is in the middle of the ion beam to adjust the laser.
Picture 1: Final beam position.
Picture 2: Final MRC settings.
Note 1: By switching to the "real" bunching frequency, the laser went out of the stabilization. We restarted the MRC system and shifted the laser back into position with the piezo mirror, looking at the first screen (without amplifiers!).
After enabling everything again, the before found settings did not correspond to the correct beam position anymore, so we overlapped again.
Note 2: After the repositioning, the horizontal screw was at its limit and the beam stabilization failed. We moved the screw away from the limit while still hitting the screen and restarted the MRC system. The laser could then be stabilized again. |
Attachment 1: 2022-05-11_final_laser_spot.PNG
|
|
Attachment 2: 2022-05-11_final_MRC_settings_2.PNG
|
|
36
|
Wed May 11 03:10:55 2022 |
Patrick, Sebastian, Volker, Guy | Laser | Laser - bunch timing |
We added the delay and gate generator in between the bunch trigger and the CFD to move the timing of the PMT middle signal relative to the photodiodes north and south.
The center value of PD-North is at 19 bins, PD-South at 55 bins, the middle is therefore at 37 bins. The PMT peak should be half a revolution, ie 75 bins further in the histogram, giving a peak position of 112, from which then 3 bins are subtracted to account for the distance of the PMT-middle from the center of the straight section. So all in all the delay is adjusted so the PMT-middle peak appears at 109 bins (see attached plot). |
Attachment 1: 2022-05-06_Bi2023_laserscan_test.png
|
|
37
|
Wed May 11 03:17:14 2022 |
Patrick, Volker, Guy | Runs | Start laser scanning |
Runs of the night shift. The wavelength range is 601.95 - 601.735 nm.
We started the wavemeter python script on atppc023 located in Desktop/wavemeter_Bi.
We changed the wavelength range in go4 to the actual scan range.
Questions:
There are many other masses/isotopes/etc. visible in the Shottky spectrum. Is this wanted?
Are the vacuum gauges turned off?
Laser timing correct? +- 3 bins?
Time | SIS-intensity | cooler-HV | LMD-DAQ2 file nr | LMD-DAQ1 file nr | scan range(nm) | step width(nm) | dwell time(s) | comments
|
03:30 | ?e7 | 223218 | 373 | 8073 | 601.95 - 601.735 | 0.005 | 5s | 2 loops
|
03:38 | 9.0e7 | 223218 | 374-377 | 8074 | 601.95 - 601.735 | 0.005 | 5s | 8 loops from now on
|
04:15 | 8.4e7 | 223218 | 378 - 381 | 8075 | 601.95 - 601.735 | 0.005 | 5s |
|
04:49 | 7.4e7 | 223217 | 382 - 385 | 8076 | 601.95 - 601.735 | 0.005 | 5s |
|
05:23 | 6.4e7 | 223216 | 386 - 388 | 8078 | 601.95 - 601.735 | 0.005 | 5s | 8077 was skipped due to some "server socket locked"-error
|
05:59 | 8.9e7 | 223218 | 389 - 391 | 8079 | 601.95 - 601.735 | 0.005 | 5s |
|
|
39
|
Wed May 11 06:41:32 2022 |
Simon, Christopher, Shahab | Runs | shifts |
new shift started. |
40
|
Wed May 11 06:47:58 2022 |
Simon, Christopher, Shahab | Runs | restart laser scan |
Time | SIS-intensity | ESR-intensity after orbit change | cooler-HV | LMD-DAQ2 file nr | LMD-DAQ1 file nr | scan range(nm) | step width increment (nm) | dwell time(s) | comments
|
06:37 | 7.8e7 | ? | 223217 | 392-395 | 8080 | 601.95 - 601.735 | 0.005 | 5s | 8 loops
|
07:10 | 4.8e7 | ? | 223217 | 396-399 | 8081 | 601.95 - 601.735 | 0.005 | 5s | 8 loops
|
07:48 | 1.3E8 | ? | 223219 | 400-403 | 8082 | 601.95 - 601.735 | 0.005 | 5s | 8 loops
|
08:25 | 3.9E7 | ? | 223219 | 404- 406 | 8083 | 601.95 - 601.735 | 0.005 | 5s | 8 loops
|
08:59 | 5.8E7 | ? | 223219 | 407 | 8084 | 601.95 - 601.735 | 0.005 | 5s | 8 loops
|
09:38 | 7.2E7 | 3.1E6 | 223219 | 408-411 | 8085 | 601.95 - 601.735 | 0.005 | 5s | 8 loops
|
10:24 | 6.4E7 | 3.1E6 | 223219 | 412-415 | 8086 | 601.95 - 601.735 | 0.005 | 5s | 8 loops
|
11:05 | 7E7 | 2.2E6 | 223219 | 416-418 | 8087 | 601.95 - 601.735 | 0.005 | 5s | 8 loops
|
11:36 | 6E7 | 2.2E6 | 223219 | 419-420 | 8088 | 601.95 - 601.735 | 0.005 | 5s | number of loops now 4
|
11:56 | 2E8 | 6.9E6 | 223219 | 421-423 | 8089 | 601.62 - 601.405 | 0.005 | 5s | 4 loops, changed scan range
|
12:28 | 1.1E8 | 5E6 | 223219 | 424-426 | 8090 | 601.62 - 601.405 | 0.005 | 5s | 4 loops
|
12:43 | 6.5E7 | 2.6E6 | 223219 | 427-429 | 8091 | 601.62 - 601.405 | 0.005 | 5s | 4 loops
|
13:11 | 1.3E8 | 5.8E6 | 223219 | 430-432 | 8092 | 601.62 - 601.405 | 0.005 | 5s | 4 loops
|
|
41
|
Wed May 11 07:28:39 2022 |
Simon, Christopher, Shahab | General | DAQ Loop for shifters |
Procedure:
- Scanning phase ends (on LabView wait until "Idle Status" blinks. it will show e.g. 8 loops and 44 scans)
- on DAQ2 (Carsten) and DAQ1 type (simultaneously):
sto ac
- on DAQ2 (Carsten) and DAQ1 type:
clo fi
exit
- on DAQ1 computer, stop GO4 and close it
- on DAQ2 (Carsten) and DAQ1 type:
resl
mbs
@startup
- on DAQ1 computer, start GO4
go4&
- request new injection (move the green slider to red, wait for machine to go further, then move it back to green)
ESR_EXP22_03_209Bi83_Laser_06May.C1.9_WAIT_FOR_MANIP_BY_OP
- in Lassie Monitor, remember the value of SIS-Trafo (GS09DT_ML) after injection, and put it later in the elog table
- wait until the ion beam is cooled (look at the Schottky monitor)
- on DAQ2 (Carsten) and DAQ1 type (simultaneously):
sta ac
- on LabView press on button
Start Scan
- Scanning phase starts.
- you can show the status (and also the current filename) by using the command
sh ac
- update elog with SIS Current, Filenames, and time
- restart from top |
42
|
Wed May 11 08:01:44 2022 |
Zoran | Runs | Start laser scanning |
Quote: |
Questions:
There are many other masses/isotopes/etc. visible in the Shottky spectrum. Is this wanted?
Are the vacuum gauges turned off?
Laser timing correct? +- 3 bins?
|
No, this is not wanted and yes, the machine is aware of the problem. The decision on Tuesday evening was to leave the ESR in that state in order to start the measurement and continue setting on Wednesday. Otherwise the night shift could not take place.
The additional isotopes are only a few percent and should contribute insignificantly to the background rate. |
43
|
Wed May 11 14:48:31 2022 |
Konstantin | DAQ | Voltage range of the Keysight DMM changed from 10V to 1V |
During the setup of the ion beam the voltage range of the Keysight DMM was changed from 10V to 1V. Additionally, the name of the high-voltage divider was adjusted (this changes only the filename of the file, which is stored at the local pc decpc003). |
Attachment 1: VoltageRangeChanged.png
|
|
44
|
Wed May 11 14:59:01 2022 |
Rodolfo | Laser | Laser status |
I have measured the output energy of the laser system. All values in [mJ] and over 500 laser-pulses average
Date | Out of Quanta Ray @ 532 nm | Seed energy for Cobra @ 532 nm | Out of Cobra @ 601 nm
|
10.05.2022 | 533 | 485 | 71
|
11.05.2022 | 484 | 480 | 67
|
|
45
|
Wed May 11 18:00:40 2022 |
Wilfried, Phillip, Max | Detectors | double PD NO peak problem solved |
In entry 36 one finds an additional PD NO peak around bin 100.
This was caused by signal reflection in the cable.
The problem was solved by adjusting the CFD threshold from 10 to 30.
|
46
|
Wed May 11 18:13:04 2022 |
Wilfried, Phillip, Max | DAQ | laser scan/step complete |
The scaler channel laser scan complete and laser step complete is interchanged in go4. Carsten will fix this on the software side.
Additionally the laser scan complete signal was not there in the first place. After checking the signal on multiple points, the signal was suddenly back in the DAQ.
Possibly there is a bad cable/contact somewhere (on the Labjack?). The signal should be checked in go4 from time to time. |
47
|
Wed May 11 20:47:54 2022 |
Zoran | Accelerator | beam lost in SIS |
For some reason the beam was lost in the SIS soon after taking the ESR beam this evening, reason unknown. Solved by sending teh full context to the SIS machine and having
operators to manually set the voltage of the SIS extraction kicker. Afterwards a slight readjustment of the transfer beamline was necessary:
In the SIS: GTE5 KY1, MU0, QD21, QD22 as well as in the ESR: GE01MU4I (5 -> 6 mrad)
This brought back around 1E7 particle in the ESR after 5 accumulated SIS injections. |
48
|
Wed May 11 22:04:30 2022 |
Phillip, Wilfried, Max | General | spacial laser - ion overlap verified |
After the SIS/ESR optimization we checked the spatial overlap with the T-scrapers again.
The values are:
device | move in dir. | scratch (mm) | gone (mm)
|
GECEDS1VU | up | -3.0 | -2.2 |
|
| | | |
|
GECEDS1HA | right | -22.9 | -22.0 |
|
| left | -11.0 | -13.0 |
|
| | | |
|
GECEDS2VU | up | -4.5 | -2.7 |
|
| | | |
|
GECEDS2HA | right | -21.0 | -19.6 |
|
| left | -7.8 | -8.4 |
|
The beam position is approx. as before. The laser position is still good and we have spatial overlap. |
49
|
Wed May 11 22:19:17 2022 |
Max, Wilfried, Volker | Laser | laser bunch timing |
We overlapped the laser and ion bunch in the time domain. The delay has to be set on the module above the laser and NOT in the ESR Messhütte!
The values are:
PD NO: 63
PD SO: 98.5
Ion bunch: 150 |
Attachment 1: timing10_5_22.png
|
|
50
|
Wed May 11 22:45:22 2022 |
Max, Wilfried, Patrick | General | scanning wavelength |
The scan parameters for the next shift are:
in COBRACONTROL:
increment: 0,005nm
from position: 601,62nm
to position: 601,405nm
These are the wavelengths in air!
The wavelength in vacuum we expect is: 601.832nm
You can check the current wavelength in vacuum on the wavemeter in the LabView GUI.
edit: In the night shift, we checked the scanned vacuum wavelengths in the wavemeter and also checked the expected transition wavelength.
The resonance should be very much in the center of the above mentioned scan range.
The increment corresponds to 4.1 GHz steps. Is this small enough? |
51
|
Wed May 11 23:34:39 2022 |
Patrick, Carsten | Detectors | Particle Detectors / Scraper positions |
Voltages of particle detectors off.
Scraper positions:
GE02DS3HG: -8
GE01DD2AG: -25
GE01DD2IG: 6
GE02DD2_G: -30 |
52
|
Wed May 11 23:36:24 2022 |
Ruijiu Chen, Carsten, Guy | DAQ | start NTCAP. |
Carrier frequency:244MHz
IQ rate: 10M Samples/seconds
Reference level: -25
RF-Attenuation(dB):40
IF-Attenuation(dB):19.9288
Samples/Record:2^18=262144
Records/File:2^12=4096
Masterpath:p:\208Bi\iq\IQ_2022-05-10_17-06-29
p:\208Bi\sc\IQ_2022-05-10_17-06-29
Free space of hard disk: 34.9TB. |
53
|
Thu May 12 00:16:13 2022 |
Patrick, Volker, Guy, Rui-Jiu | Runs | Runs night shift |
Time | SIS-intensity | ESR-intensity after orbit change | cooler-HV | LMD-DAQ2 file nr | LMD-DAQ1 file nr | scan range(nm) | step width increment (nm) | dwell time(s) | n loops | comments
|
00:15 | ~1.0e8 | 1.0e7 | 223219 | 433 - 435 | 8094 | 601.62 - 601.405 | 0.005 | 5s | 4 |
|
00:47 | 3.7e8 | 2.0e7 | 223219 | 436 - 440 | 8095 - 8096 | 601.62 - 601.405 | 0.005 | 5s | 8 | increased to 15 injections, still not saturated
|
| | | | | | | | | | Tried 20 injections, got no injection into ESR, so moved back to 15. The scrapers were not moving for quiet some time, even after fixing them.
The problem may have been that two ParamModi windows were opened. The injection into the SIS does not work when there are other users performing special operations with the machines.
|
02:28 | 1.0e8 | 1.0e7 | 223220 | 441 - 444 | 8097 | 601.62 - 601.405 | 0.005 | 5s | 6 |
|
02:54 | 2.8e8 | 1.7e7 | 223219 | 445 - 449 | 8098 - 8099 | 601.62 - 601.405 | 0.005 | 5s | 6 |
|
03:21 | ~3e8 | ~2e7 | 223219 | DAQ did not write | 8100 - 8101 | 601.62 - 601.405 | 0.005 | 5s | 6 |
|
| | | | | | | | | | The vacuum gauge of the e-cooler failed. It was restarted. Apparently, upon changing/fixing anything related to our accelerator pattern, the scrapers forget to move.
Then they have to be disabled and enabled again in ParamModi. Also, the injection does not work very well. Either the transition from SIS to ESR fails or we are just skipped completely.
After fixing the injection, again the scrapers failed as expected. We keep the scrapers out now.
|
04:34 | 2.8e8 | 1.8e7 | 223219 | DAQ failed, started late 454 - 458 | 8102 - 8103 | 601.62 - 601.405 | 0.005 | 5s | 6 | Set max.counts in PMT middle and north to 15 (In file 'SetConditions.C', applied when starting go4). No scrapers used.
|
05:02 | 2.5e8 | 1.7e7 | 223219 | DAQ late, 461 - 464 | 8104 - 8105 | 601.62 - 601.405 | 0.005 | 5s | 6 |
|
05:30 | 2.5e8 | 1.8e7 | 223219 | 465 - 469 | 8106 - 8107 | 601.62 - 601.405 | 0.005 | 5s | 6 | Set max.counts in PMT middle and north to 20.
|
05:57 | 2.5e8 | 1.7e7 | 223219 | 470 - 474 | 8108 - 8109 | 601.62 - 601.405 | 0.005 | 5s | 6 |
|
06:25 | 2.6e8 | 1.7e7 | 223219 | 475 - 479 | 8110 - 8111 | 601.62 - 601.405 | 0.005 | 5s | 6 |
|
06:50 | 2.4e8 | 1.6e7 | 223219 | 480 - 484 | 8112 - 8113 | 601.62 - 601.405 | 0.005 | 5s | 6 |
|
07:24 | 2.2e8 | 1.5e7 | 223219 | 485 - 489 | 8114 - 8115 | 601.62 - 601.405 | 0.005 | 5s | 6 |
|
07:49 | - | 6.5e6 | 223219 | 490 - 493 | 8116 | 601.62 - 601.405 | 0.005 | 5s | 6 | UNILAC tunnel will be open for ~1h -> no new beam from SIS available
|
08:15 | - | 2.6e6 | 223219 | 494 - 496 | 8117 | 601.62 - 601.405 | 0.005 | 5s | 6 | UNILAC tunnel will be open for ~1h -> no new beam from SIS available
|
|
54
|
Thu May 12 03:25:37 2022 |
Patrick | DAQ | Laser scan complete signal off |
As in ID:46, the 'laser scan complete' again is not coming in.
It is not very useful to repeatedly fix cable contact problems.
Therefore, Carsten is adding a 'number of steps' line to the config file to "repeat" the x-axis. |
55
|
Thu May 12 10:10:35 2022 |
Simon, Christopher, Wilfried, Sebastian | DAQ | 1ms gated PMT north / middle added to DAQ |
We added on DAQ1 and DAQ2 1ms gated PMT North and PMT Middle signals.
Now we "supress" the signal by a factor of ~30.
DAQ1:
Channel 11 --> 1ms gated PMT North
Channel 12 --> 1ms gated PMT Middle
DAQ2:
Channel 12 --> 1ms gated PMT North
Channel 13 --> 1ms gated PMT Middle
Update: the same gate has been added to the XUV anode and anode delayed signals, but on their original TDC channels not on new ones, in order to not only reduce the background in the XUV signals but also reduce the load on the DAQ. |
56
|
Thu May 12 10:21:30 2022 |
Ragan, Shahab, Simon, Sebastian, Christopher, Wilfried | General | No Beam |
There is no beam in the ESR due to some problem in the UNILAC. |
Attachment 1: Screenshot_from_2022-05-12_09-21-38.png
|
|
57
|
Thu May 12 11:30:18 2022 |
Ragan, Shahab, Simon, Sebastian, Christopher, Wilfried | General | Beam is back |
Beam is back in the ESR. |
Attachment 1: Screenshot_from_2022-05-12_10-32-24.png
|
|
58
|
Thu May 12 11:31:11 2022 |
Simon, Christopher, Shahab, Wilfried, Sebastian, Ragan | General | Runs morning shift |
Time | SIS-intensity | ESR-intensity after orbit change | cooler-HV | LMD-DAQ2 file nr | LMD-DAQ1 file nr | scan range(nm) | step width increment (nm) | dwell time(s) | n loops | comments
|
11:30 | - | 8,2e6 | 223219 | 497 - 500 | 8119 - 8119 | 601.62 - 601.405 | 0.005 | 5s | 6 | after this run we had to give the ESR Group the beam
|
|
|
59
|
Thu May 12 12:02:56 2022 |
Ragan, Shahab, Simon, Sebastian, Christopher, Wilfried | General | No beam |
There is no beam in the ESR again. |
Attachment 1: Screenshot_from_2022-05-12_11-02-37.png
|
|
60
|
Thu May 12 12:51:30 2022 |
Ragan, Shahab, Simon, Sebastian, Christopher, Wilfried | General | Beam is back |
12:50 Beam is back again in the ring.
12:52-until now Kicker problem in the ESR. |
Attachment 1: Screenshot_from_2022-05-12_11-51-35.png
|
|
Attachment 2: Screenshot_from_2022-05-12_12-08-52.png
|
|
61
|
Thu May 12 14:04:09 2022 |
Konstantin | DAQ | Go4 Laserstep histograms adapted |
In order to correctly display the gated PMT signals PMT Middle and PMT North some modifications in the Go4 code were necessary. Affected files are TLdaAnlProc.cxx, TLdaAnlProc.h and TLdaInputDescription.h.
Modifications are indicated according to the scheme "//-- HH:MM mm-dd-yyyy: <description>" (an example is given in the attached screenshot). They were needed to
- Create relevant histograms (change of variable MAX_STEP from 10 to 13 and insertion of histogram names "QSWP1MS", "NORTH_GATED" and "MIDDLE_GATED" in the std::string array stepNames.
Both adaptions were made in TLdaInputDescription.h)
- Fill the respective histograms. Changed lines of files TLdaAnlProc.cxx, TLdaAnlProc.h are listed below.
filename | modified lines
|
TLdaAnlProc.h | 47 |
TLdaAnlProc.cxx | 258-261, 381-394, 442-443, 484-494, 536-542
|
|
Attachment 1: Go4Modifications.PNG
|
|
62
|
Thu May 12 15:21:23 2022 |
Sebastian, Simon | Laser | Flash lamps changed |
We (Sebastian and I) changed the flash lamps of the Quanta Ray Laser and measured the output energy of the laser system afterwards (still during warm up).
All values in [mJ] and over 500 laser-pulses average
Date | Out of Quanta Ray @ 532 nm | Seed energy for Cobra @ 532 nm | Out of Cobra @ 601 nm
|
10.05.2022 | 533 | 485 | 71
|
11.05.2022 | 484 | 480 | 67
|
12.05.2022 | 578 | 501 | 75
|
The lambda/2 is at 103°. Correction factor for the 532nm-monitor is 11.4 (exchanged broken monitor). |
63
|
Thu May 12 15:34:47 2022 |
Max, Kristian, Sebastian | DAQ | laser scan, laser step and laser busy checked |
We checked all three signals in the Messhütte. Laser scan and laser step are OK.
The Laser busy signal is for large increments (0.1nm) also fine. For short increments like our usual 0.005nm increment the signal is irregularly.
Likely the laser busy status is too short. |
64
|
Thu May 12 15:50:33 2022 |
Max | Accelerator | No ESR beam |
Since 13:30 we have no beam in the ESR. There is a problem with the ESR septum.
The magnets department is investigating. |
65
|
Thu May 12 16:35:17 2022 |
Max, Wilfried, Zoran | Accelerator | NO BEAM UNTIL TOMORROW MORNING |
The problem at the ESR septum is serious. They have to remove the broken part and try to repair it.
Maybe tomorrow in the morning briefing there will be more information about this.
The night shift will not take place!
The morning shift starts at 9:00 or on further notice!
The PMTs are switched off and the laser also. |
66
|
Fri May 13 08:32:41 2022 |
Zoran | Accelerator | NO BEAM UNTIL TOMORROW MORNING |
> The problem at the ESR septum is serious. They have to remove the broken part and try to repair it.
> Maybe tomorrow in the morning briefing there will be more information about this.
>
> The night shift will not take place!
> The morning shift starts at 9:00 or on further notice!
>
> The PMTs are switched off and the laser also.
Update from the morning briefing: the DCCT (power converter) of the injection septum was demounted and the EPS group is trying to fix it. There is no replacement available, so if they do not succeed this beamtime is over. They promised more information in the midday meeting at 12:45.
In the ESR Messhüte is some cake ("Trostkuchen"). |
67
|
Fri May 13 11:46:51 2022 |
Sebastian, Simon | | Laser energy |
We (Sebastian and I) measured the output energy of the laser system again.
All values in [mJ] and over 500 laser-pulses average
Date | Out of Quanta Ray @ 532 nm | Seed energy for Cobra @ 532 nm | Out of Cobra @ 601 nm
|
10.05.2022 | 533 | 485 | 71
|
11.05.2022 | 484 | 480 | 67
|
12.05.2022 | 578 | 501 | 75
|
13.05.2022 | 632 | 498 | 78
|
The lambda/2 is at 100°. Correction factor for the 532nm-monitor is 8.4. |
68
|
Fri May 13 16:55:58 2022 |
Danyal, Carsten, Phillip, Wilfried | General | End of E128 Beamtime |
Dear all,
unfortunately, the E128 experiment must now come to an early end.
The problem(s) with the injection septum are severe and no work around solution (with acceptable risks) could be found.
Several things were tried, but without hope.
Many thanks to everybody involved during the preparation time and the shifts during the beamtime.
Best wishes,
Wilfried |
69
|
Mon May 16 14:20:05 2022 |
Ragan, Danyal, Carsten, Phillip, Wilfried et al. | General | E128 Beamtime |
> Dear all,
>
> unfortunately, the E128 experiment must now come to an early end.
> The problem(s) with the injection septum are severe and no work around solution (with acceptable risks) could be found.
> Several things were tried, but without hope.
>
> Many thanks to everybody involved during the preparation time and the shifts during the beamtime.
>
> Best wishes,
>
> Wilfried
There is beam again in the ESR. The plan is to take beam until tomorrow morning. |
70
|
Mon May 16 15:57:37 2022 |
Rodolfo | Laser | Wavemeter calibration |
I have calibrated our Wavemeter WS7 using the temperature stabilized He-Ne Laser (SIOS EN60 825-1:2014). In the screenshots below you can see the readout of the wavemeter before (vor) and after (nach) calibration. |
Attachment 1: WS7_VorKalibrationMitHe-Ne_16-05-2022.PNG
|
|
Attachment 2: WS7_NachKalibrationMitHe-Ne_16-05-2022.PNG
|
|
71
|
Mon May 16 17:15:56 2022 |
Carsten | Analysis | DAQ /Analysis - shift of peaks in the accumulated spectra, changes in code |
After a phone call with Wilfried I implemented an offset to all hit channels of the stacked / accumulated spectra where one chekcs the timing peaks.
Therfore, I made a copy of the analysis in 208Bi1 (one "1" at the end). And here, in the file TLdaAnlProc.cxx I added an offset of +70 to the hit channel (variable UInt_t hit, around line 335 /336 of the code).
Pleasse note that I just inlcuded one line with a "magic" number here, since I cannnot test teh compiling and was afraid to introduce an error.
So the lines were
UInt_t hit =tdcSE[i][j];
changed to
UInt_t hit =tdcSE[i][j];
hit = hit + 70;
Plesaede note that you need to recompile and check and set all conditions for the time-preak window.
So , you now use the analysis in 208Bi1 |
72
|
Mon May 16 17:38:38 2022 |
Max, Danyal, Wilfried, Rodolfo | General | laser bunch timing |
We overlapped the laser and ion bunch in the time domain.
Therefore we delayed the bunching HF in order to see the PMT signal between bin 10 and 22. Before the signal Peak was in channel ~145-5 and difficult to gate on.
Afterwards we also have to shift the laser.
The new values are:
PD NO: 77.5
PD SO: 113
Ion bunch: 16.5 |
Attachment 1: timing1605.png
|
|
73
|
Mon May 16 18:01:23 2022 |
mbsMax, Danyal, Wilfried, Rodolfo, Patrick, Kristian, David, Ruijiu | Runs | runs afternoon/night shift 16.05 |
These are the runs after the septum was repaired on 16.05.
Time | ESR-intensity | ESR-intensity after orbit change | cooler-HV | LMD-DAQ2 file nr | LMD-DAQ1 file nr | scan range(nm) | step width increment (nm) | dwell time(s) | n loops | comments
|
ca. 18:00 | ? | ~3.0e7 | 223222 | 504-505 | 8121 | 601.62 - 601.405 | 0.005 | 5s | 4 | DAQ2 late start
|
18:11 | ? | ~3.3e7 | 223222 | 506 | 8122 | 601.62 - 601.405 | 0.005 | 5s | 4 | aborted, ions are rapidly lost after Bahnverlagerung
|
18:33 | 4.5e7 | ~3.7e7 | 223222 | 507-509 | 8123 | 601.62 - 601.405 | 0.005 | 5s | 4 | removed all scrapers, beam life time is better, high intensity, slight instability in bunching, ion intensity at the end: 1.4e7, DC Trafo was in saturation so ampl. was turned down
|
19:32 | ? | 3.7e7 | 223222 | 512 | 8125 | 601.62 - 601.405 | 0.005 | 5s | 4 | rf bunching amplitude decreased from 350V -> 280V
|
20:00 | ? | 3.6e7 | 223223 | 514 | 8127 | 601.745 - 601.32 | 0.01 | 5s | 4 | 43 steps of laser, therefore 1 step offset from loop to loop, laser already of ?
|
20:30 | ? | 2.9e7 | 223223 | 520-522 | 8129 | 601.760 - 601.320 | 0.01 | 5s | 6 | aborted after 3 loops, laserstabi was off, probably during hole measurement
|
21:01 | ? | 3.6e7 | 223223 | 524-528 | 8130 | 601.760 - 601.320 | 0.01 | 5s | 6 |
|
21:30 | ? | 3.4e7 | 223223 | 529-532 | 8131 | 601.760 - 601.320 | 0.01 | 5s | 6 | coasting beam now !!!
|
22:10 | ? | 3.7e7 | 223223 | 534-537 | 8132 | 601.760 - 601.320 | 0.01 | 5s | 6 | Night shift took over.
|
22:40 | 4.4e7 | 3.6e7 | 223223 | 539-542 | 8133 | 601.760 - 601.320 | 0.01 | 5s | 6 |
|
23:52 | 3.8e7 | 3.2e7 | 223223 | 545-548 | 8134 - 8135 | 601.760 - 601.320 | 0.01 | 5s | 6 | Switched off the nitrogen before this run, stopped acq. after 4 loops (laser gone), PMT north saw a lot of noise? (ID:78) -> larger files.
|
00:39 | 4.3e7 | 3.2e7 | 223222 | 552-555 | 8136 | 601.760 - 601.320 | 0.01 | 5s | 6 | The secondary DAC always requires 2-3 restarts until it is working.
|
01:10 | 3.8e7 | 3.0e7 | 223222 | 557-558 | 8137 | 601.760 - 601.320 | 0.01 | 5s | 6 | Laser moved away during the third loop, acq. stopped.
|
01:33 | 4.2e7 | 3.1e7 | 223222 | 561-564 | 8139 | 601.760 - 601.320 | 0.01 | 5s | 6 | The previous laser scan was still running, restarted the acq. once.
|
02:00 | > 4.0e7 | 3.4e7 | 223222 | 566-569 | 8140 | 601.760 - 601.320 | 0.01 | 5s | 6 |
|
02:30 | > 4.0e7 | 3.2e7 | 223222 | 573-576 | 8141 | 601.760 - 601.320 | 0.01 | 5s | 6 |
|
02:58 | 4.2e7 | 3.4e7 | 223222 | 579-582 | 8142 | 601.760 - 601.320 | 0.01 | 5s | 6 |
|
03:45 | 4.2e7 | 3.3e7 | 223222 | 585-589 | 8143 | 601.760 - 601.320 | 0.01 | 5s | 6 | Back to bunched beam mode
|
04:15 | 4.7e7 | 3.4e7 | 223222 | 594-598 | 8144 | 601.760 - 601.320 | 0.01 | 5s | 6 |
|
04:43 | 4.4e7 | 3.4e7 | 223222 | 600-604 | 8145 | 601.960 - 601.520 | 0.01 | 5s | 6 | We changed the scan range
|
05:10 | 4.3e7 | 3.3e7 | 223221 | 606-610 | 8146 | 601.960 - 601.520 | 0.01 | 5s | 6 | It looks like the "overWavel" plots actually work better now, because the laser steps somehow are counted wrongly, leading to shifts between loops.
|
05:37 | 4.2e7 | 3.7e7 | 223221 | 611-615 | 8147 | 601.960 - 601.520 | 0.01 | 5s | 6 |
|
06:27 | ? | ? | 223219 | 616-618 | 8148 | 601.960 - 601.520 | 0.01 | 5s | 6 | Since Go4 was still running during startup we were not able to look into the data during the scan. After reduction of particle number, the dc trafo is no longer capable to measure to number of ions.
|
06:56 | ? | ? | 223219 | 619-620 | 8149 | 601.960 - 601.520 | 0.01 | 5s | 6 |
|
07:25 | ? | ? | 223219 | 621-622 | 8150 | 601.9 - 601.7 | 0.01 | 5s | 6 | Changed the scan range t0 601.9-601.7 and reduced step increment to 0,005nm
|
07:56 | ? | ? | 223219 | 623-624 | 8151 | 601.9 - 601.7 | 0.01 | 5s | 6 |
|
08:20 | ? | ? | 223219 | 625-625 | 8152 | 601.9 - 601.7 | 0.01 | 5s | 6 | Restarted scan without new injection, DAQ2 was not running during this scan
|
08:44 | ? | ? | 223220 | 626-627 | 8153 | 601.9 - 601.7 | 0.01 | 5s | 6 | Reduced Loop number to 4 (aborted after 4 completed scans)
|
09:03 | ? | ? | 223220 | 628 | 8154 | 601.9 - 601.7 | 0.01 | 5s | 6 | Reduced Loop number to 3 (before starting a new scan)
|
09:17 | ? | ? | 223221 | 629 | 8155 | 601.9 - 601.7 | 0.01 | 5s | 6 |
| Since |
74
|
Mon May 16 19:20:55 2022 |
Max, Wilfried | Analysis | start go4 before laser scan |
It is necessary to start go4 before you start the laser scan. Otherwise you get an offset in the laser Step plots. |
75
|
Mon May 16 21:08:48 2022 |
Rodolfo & Max | Laser | Laser power |
We checked the energy of the laser and optimized it a bit
Time | Seed energy for Cobra @ 532 nm | Out of Cobra @ 601 nm
|
20:41 | 415 | 63
|
20:48 | 506 | 73
|
The lambda/2 is now at 108°. |
76
|
Mon May 16 22:19:54 2022 |
Patrick | DAQ | Keep go4 running (in theory), MBS |
To accumulate more data into the opened go4, do not restart MBS, but just
sto ac
clo fi
open file lxg1297:/data.local2/208Bi/208Bi -auto -rfio
sta ac
Note: This does not work, because go4 somehow accumulates ~5 extra laser steps when starting a new scan which results in an x-axis-offset between the runs. |
77
|
Mon May 16 22:57:40 2022 |
Patrick, Kristian, David, Ruijiu | Detectors | Switched off nitrogen |
Background counts with nitrogen and air.
Less multiphoton events with air (see pictures, histogram extended to 30 with nitrogen).
Read in 4_Lasersteps/Counts
nitrogen:
XUV: 15e4
Middle: 8e4
North: 9e4
air:
XUV: 13e4
Middle: 1.2e4
North: 0.7e4 |
Attachment 1: 2022-05-16_PMTs_after_nitrogen_off.png
|
|
78
|
Tue May 17 00:44:01 2022 |
Patrick, Kristian | DAQ | Changed PMT North CFD channel |
In run 8134 - 8135 PMT North showed a super high background rate. After the scan we checked the signal cables.
Incoming signal was still good until CFD. We changed channel from 2 to 12. New threshold is 36, was 10. |
79
|
Tue May 17 06:37:28 2022 |
YL, KM | Accelerator | Reduced beam intensity |
The resonance in 209Bi has been seen during the night.
Reducing the intensity by a factor~1000, to simulate 208Bi conditions
Running low intensity since ~6:15-6:20
The present intensity is so low that DCCT does not see the beam.
On Schottky the beam is clearly seen as ~30-40 dB over the background.
The real intensity is to be determined from the NTCap, which is running (checked). |
80
|
Tue May 17 10:38:44 2022 |
Konstantin | Detectors | PMT North changed |
PMT located at the northern window was again replaced by the narrow-band PMT (ET Enterprise type 9423 SB, SN: 650). |
81
|
Fri May 27 10:39:53 2022 |
Kristian | DAQ | PMT North noise |
During the last run, PMT North showed some weird noise.
The PMT was replaced by the deep UV PMT with small aceptance range (100-200nm) but there was still a lot of noise on the output channel in the Messhütte, see attached photo. The intensity of the noise signal was as strong as a normal signal count.
I replaced all cables and used other preamplifier channels. The noise is gone and the baseline is flat now. However, the timing of PMT north will be a bit different now, so we should use PMT middle for the laser/ion overlap as we did before.
Graziano opened the valves for the laser and turned off the vacuum gauges and emergency lights. The background of the UV PMT looks normal (Middle 10 Hz, North 1 Hz) so I think we are fine here. |
Attachment 1: IMG_20220527_095501.jpg
|
|
82
|
Fri May 27 14:57:23 2022 |
Rodolfo | Laser | Laser Energy |
I have started up the laser system (Q-Ray & Cobra) again. Here some parameters*:
- Q-Ray's output energy (@532 nm: 547 mJ.
- Seed energy for Cobra# (@532 nm): 504 mJ.
- Cobra's output energy (@ 601.7 nm): 71 mJ.
* all values averaged over 500 pulses.
# angle of lambda/2-plate: 107° |
83
|
Fri May 27 20:39:50 2022 |
Carsten | Analysis | Short Manual for updated Go4 DAQ (version 2022_05_27) |
Short descriptions of the most recent version of the GO4 code is attached. I will install the corresponding vesion early on sunday. |
Attachment 1: Short_Introduction_to_the_208Bi_Go4_Analysis.pdf
|
|
Attachment 2: Short_Introduction_to_the_208Bi_Go4_Analysis.odt
|
84
|
Mon May 30 00:56:33 2022 |
Max, Patrick | Laser | Beam overlap |
The ion beam positions are (+- 1mm):
device | move in dir. | scratch (mm) | gone (mm) | gone +- 4.5 (mm) | x0 (mm)
|
GECEDS1VU | up | -1.5 | 0.7 | 5.2 |
|
| | | | |
|
GECEDS1HA | right | -26 | -22 | -17.5 | -4.7
|
| left | -10.0 | -13.0 | -17.5 |
|
| | | | |
|
GECEDS2VU | up | -2.0 | 0.0 | 4.5 |
|
| | | | |
|
GECEDS2HA | right | -22.0 | -18.5 | -14.0 | 3.1
|
| left | -6.0 | -9.5 | -14.0 |
|
Notes:
- In between a measurement the scrapers stopped working in the device control. Therefore, we had to go into the electronics room.
- Position to scratch charge transferred beam: S1HA at -35.
- Beam diameter is roughly 6-7 mm (horizontally) and 4 mm vertically (as opposed to 1-2 mm).
- The charge transferred ion beam seems to shift the position of the main beam over time (1cm / 2h) as the main beam "transfers its intensity".
|
Attachment 1: 2022-05-30_laser_beam.png
|
|
Attachment 2: 2022-05-30_beamstab_settings.png
|
|
85
|
Mon May 30 01:13:40 2022 |
Konstantin, Max, Patrick | Detectors | XUV-Detector voltage off |
XUV-Detector shows up to 100 kHz and, therefore, was turned off. |
86
|
Mon May 30 02:12:20 2022 |
Max, Patrick, ~Konstantin, Ragan, Ken | Runs | runs night shift 30.05. |
These are the first runs of the substitute beamtime.
Time | ESR-intensity | ESR-intensity after orbit change | cooler-HV | LMD-DAQ2 file nr | LMD-DAQ1 file nr | scan range(nm) | step width increment (nm) | dwell time(s) | n loops | comments
|
02:00 | ? | 8.0e6 | 223217 | 632 | 8158 | 601.95 - 601.734 | 0.005 | 5s | 5 | Resonance found in first scan. The resonance is much broader due to a broader ion beam.
|
02:28 | ? | 7.0e6 | 223217 | 633 | 8159 | 601.9 - 601.7 | 0.005 | 5s | 5 | Same injection.
|
02:52 | ? | 6.3e6 | 223217 | 634 | 8160 | 601.9 - 601.7 | 0.005 | 5s | 5 | Same injection. Adjusted gates in go4.
|
03:14 | ? | 5.6e6 | 223439 | 637 | 8163 | 601.9 - 601.7 | 0.005 | 5s | 5 | Same injection. Auto-impedance enabled -> correct voltages. NTCAP started shortly after scan start.
|
03:35 | ? | 3.0e5 ? (under range) | 223439 | 639 | 8164 | 601.9 - 601.7 | 0.005 | 5s | 5 | Scraped the lower charge state beam by moving S1HA to pos. -30 (from the left).
|
04:50 | ? | 1.1e7 | 223439 | 640 | 8165 | 601.9 - 601.7 | 0.005 | 5s | 5 | Laser beam position slightly corrected for new ion beam position, see ID:84.
|
05:05 | ? | 1.0e7 | 223439 | 641 | 8166 | 601.9 - 601.7 | 0.005 | 5s | 5 | See picture (this + previous run)
|
05:21 | ? | 1.0e7 | 223439 | 642 | 8167 | 601.9 - 601.7 | 0.005 | 5s | 5 | Moved S1HA to -35 to get rid of the charge transferred beam.
|
05:33 | ? | 9.0e6 | 223439 | 644 | 8169 | 601.9 - 601.7 | 0.005 | 5s | 5 |
|
05:52 | ? | 9.0e5 | 223439 | 645 | 8170 | 601.9 - 601.7 | 0.005 | 5s | 5 | Scraped main beam for lower beam intensities.
|
| | | | | | | | | | There were some issue with the acquisition, and thus there are some empty files
|
06:08 | ? | 4.e5 | 223438 | 650- | 8172 | 601.9 - 601.7 | 0.005 | 3s | 25 |
|
07:11 | ? | 1.15e7 | 223438 | 653 | 8173 | 601.9 - 601.7 | 0.005 | 3s | 25 | laser scan was not started
|
07:17 | ? | 1.03e7 | 223438 | 654-656 | 8174 | 601.9 - 601.7 | 0.005 | 3s | 25 |
|
08:33 | ? | 6e6 | 223438 | 658-660 | 8176 | 601.9 - 601.7 | 0.005 | 3s | 25 | ESR scraper not in
|
09:27 | ? | 5.5e6 | 223438 | 661-667 | 8178 | 601.9 - 601.7 | 0.005 | 3s | 25 | XUV detector running again, signal of PMT north and middle in att. 2
|
10:15 | ? | <<1e6 | 223438 | 668 | 8179 | 601.9 - 601.7 | 0.005 | 3s | 25 | very low beam intensity
|
Note: PMT north does not see a resonance.
Note: PMT north does see a resonance after changing to the broadband PMT. |
Attachment 1: 2022-05-30_resonance_10_loops.png
|
|
Attachment 2: 48_AM.png
|
|
87
|
Mon May 30 02:33:45 2022 |
Patrick, MBS Max | DAQ | MBS procedure |
It is possible to keep go4 running now. Summary of the procedure:
DAC1: open file lxg1297:/data.local2/208Bi/208Bi -auto -rfio
DAC2: open file lxg0155:/data.local2/E128/Bi -auto -rfio
sta ac
start go4
measure
stop go4
sto ac
clo fi
repeat |
88
|
Mon May 30 08:35:41 2022 |
Kristian, Simon, Ken, Ragan | Detectors | Changed PMT North |
We did not see any signal at PMT North which was the narrowband PMT. Changed it to the old solar blind PMT. Now we see the resonance. It is about 3 times larger as PMT middle, most likely because of the larger window. CFD threshold was set. I also increased the CFD threshold for PMT middle slightly.
HV for PMT North: 1600 V |
89
|
Mon May 30 09:28:43 2022 |
Ken, Kristian, Simon, Ragan | Detectors | XUV-Detector |
9:27 XUV-Detector is running again.
-5V cathode, 8A main coil, 2.4A sec.coil
Rate without beam was:
Park position: ~300Hz
Pump beneath the detector is now shut down, new rate: <10Hz.
Threshold was adjusted to trigger only on "nice" signals.
Rate with beam in and laser:
Park position: ~400Hz
147mm: ~1.4kHz
with 2e6 ions |
90
|
Mon May 30 16:17:39 2022 |
Kristian, David, Wilfried, Carsten, Danyal, Rodolfo | Runs | Afternoon shift 30.05 |
These are the first runs after changing to the thick stripper foil.
Time | ESR-intensity | ESR-intensity after orbit change | cooler-HV | LMD-DAQ2 file nr | LMD-DAQ1 file nr | scan range(nm) | step width increment (nm) | dwell time(s) | n loops | comments
|
16:15 | ? | 5.0e6 | 223439 | 669-670 | 8180 | 601.95 - 601.734 | 0.005 | 5s | 5 | Resonance found in first scan. electron cooling current 100mA
|
16:45 | ? | 5.0e6 | 223439 | 671-672 | 8181 | 601.95 - 601.734 | 0.005 | 5s | 5 | electron cooling current 300mA
|
|
Width approximately the same with the higher electron current.
next we go to 208Bi |
91
|
Mon May 30 19:00:19 2022 |
Carsten | General | Scraper Settings and Parameters for the last measrements with thick target |
old Bunch frequency: 1.98777 MHz
Positions PL devices:
GE01DD2AG | -23
|
GE01DD2IG | 3
|
GE02DD2_G | -35
|
GE02DS3HG | 0
|
The voltages of the particle detectors were set to:
SA_SZ: 1500V
NA_SZ: 750V
But for the primatry beam measurements the detectors were still switched off
Set values for cooler:
SC3: 223513.377 + DeltaU = 160V
SC6: 223452.14 + DeltaU = 130V
SC9: 223452.14 + DeltaU = 130V
Electron current:
SC3: 300mA
SC6: 100mA (300mA in the second file)
SC9: 100ma (300mA in the second file)
Cooling in SC4: 550x
Cooling in SC7: 50x
Explanation of subchains:
SC4: Cooling at injection orbit
SC5: Ramp to central orbit
SC7: Cooling at central orbit
SC8: Scrapers /particle detectors in, XUV detector in, (~10s), bunching on
SC9: measurement
SC10: not used
SC11: Scrapers/particle detectors/XUV ectros out (~10s), bunching off |
Attachment 1: screenshot-2022-05-30_19-12-151030168345517073342_(002).png
|
|
92
|
Mon May 30 19:42:20 2022 |
Rodolfo & Kristian | Laser | Changing laser wavelength |
We have changed the laser wavelength, e.g. the dye for the Cobra to Fluorescein 27.
We get about 84 mJ out the main amplifier @ 548 nm.
We also changed the optics and put into operation the MRC stabilization system for this new wavelength regime.
Next step is to T-scrape the ion- and laser-beams, e.g. to make the overlap of both beams at the E-Cooler. |
93
|
Mon May 30 20:58:26 2022 |
Carsten | Accelerator | New Settings for 208Bi Beam |
Old SetParameters.C and old SetConditions.C were saved as SetParameters_209.C and SetConditions_209.C
The ion beam settings were changed to 208Bi82+:
SIS energy now: 554.6 MeV/u (was 551MeV/u) + 3.6MeV/u
Cooling voltages were increased by 1830V, i.e.
Delta U SC3: 1990V
DeltaU SC6 / SC9 : 1960V ???
The new frequency is 1.99236615 MHz
DD2AG xx
DD2IG xx
DD2_G xx
DS3_HG xx
SIS intensity is still only about 1e8 |
94
|
Mon May 30 21:52:08 2022 |
Wilfried, Danyal, David, Rodolfo | General | Position of T-Scrapers |
We have determined the position of the H-like 208Bi ion beam using the T-Scrapers. The position actually did not change in comparison to the position of H-like 209Bi.
Here we have the values where the beam was "gone"
device | move in dir. | gone (mm) | x0 (mm)
|
GECEDS1VU | up | 0.7 |
|
| | |
|
GECEDS1HA | right | -22 | -4.7
|
| left | -13.0 |
|
| | |
|
GECEDS2VU | up | 0.0 |
|
| | |
|
GECEDS2HA | right | -18.5 | 3.1
|
| left | -9.5 |
|
Below you can see a screenshot with the settings of the beam stabilization system. |
Attachment 1: MRC_208Bi_30-05-2022-10Uhr.png
|
|
96
|
Mon May 30 23:18:06 2022 |
Carsten, Rodolfo, Konstantin, Patrick, Ragan, Ken, Kristian, Max, Danyal | Runs | Runs shifts 31.05. |
These are the first runs with 208Bi.
Time | SIS-intensity | ESR-intensity after orbit change | cooler-HV | LMD-DAQ2 file nr | LMD-DAQ1 file nr | scan range(nm) | step width increment (nm) | dwell time(s) | n loops | Particle Detector | comments
|
23:11 | 2.6e8 | - | 225259 | 673-677 | 8182 | 548 - 549 | 0.005 | 2.97s | 4 | 139e3 | Resonance found in first scan.
|
00:09 | ? | - | 225259 | 678-679 | 8183 | 548 - 549 | 0.005 | 2.97s | 2 | 92e3 |
|
00:45 | 2.8e8 | - | 225260 | 680-681 | 8184 | 548 - 549 | 0.005 | 2.97s | 2 | 36e3 | In this run, the ions seemed to be not ejected with the new request, compare picture.
|
01:27 | 2.7e8 | - | 225260 | 684-685 | 8187 | 548 - 549 | 0.005 | 2.97s | 2 | 88e3 | Started delayed due to several issues with both DAQs.
|
01:53 | 2.7e8 | - | 225260 | 686-687 | 8188 | 548 - 549 | 0.005 | 2.97s | 2 | 93e3 |
|
02:20 | 2.7e8 | - | 225260 | 688-689 | 8189 | 548 - 549 | 0.005 | 2.97s | 2 | 87e3 |
|
02:55 | 2.1e8 | - | 225260 | 692-694 | 8190 | 548.335 - 548.535 | 0.0025 | 4.95s | 4 | 88e3 | Scan range changed
|
03:30 | 2.75e8 | - | 225260 | 696-697 | 8191 | 548.335 - 548.535 | 0.0025 | 4.95s | 3 | 95e3 | Number of loops reduced to 3
|
03:59 | 2.6e8 | - | 225260 | 698-699 | 8192 | 548.335 - 548.535 | 0.0025 | 4.95s | 3 | 89e3 |
|
04:30 | 2.7e8 | - | 225260 | 700-702 | 8194 | 548.335 - 548.535 | 0.0025 | 4.95s | 3 | 89e3 | DAQ1 needed to be restarted
|
04:52 | 2.55e8 | - | 225260 | 703-704 | 8195 | 548.335 - 548.535 | 0.0025 | 4.95s | 3 | 83e3 |
|
05:18 | 2.62e8 | - | 225260 | 706-707 | 8196 | 548.335 - 548.535 | 0.0025 | 4.95s | 3 | 89e3 | DAQ2 needed to be restarted
|
05:44 | ? | - | 225260 | 708-710 | 8197 | 548.335 - 548.535 | 0.0025 | 4.95s | 3 | ? |
|
06:18 | 2.1e8 | - | 225260 | 711-712 | 8200 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | 67e3 | we changed the timing by 20 ns. The laser pulse is later now. The file number of DAC1 is correct. I do not know why there is the gap to the previous scan
|
06:51 | 2.4e8 | 6e5 | 225260 | 713-714 | 8201 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | 67e3 | xuv-detector parameters were varied
|
07:09 | 2.4e8 | 6e5 | - | 715- | 8202 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | 68e3 | mbs did not start
|
07:15 | 2.4e8 | 6e5 | 225260 | 716-717 | 8203 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | 68e3 | xuv-detector walklevel and treshhold were lowered
|
07:35 | 2.4e8 | 6e5 | 225259 | 718-719 | 8204 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | 68e3 | we changed the timing by additional 20 ns. The laser pulse is later now. - no fluo. visible
|
08:01 | 2.4e8 | 6e5 | 225259 | 720-721 | no file opened | 548.43 - 548.44 | 0.00001 | ~20s | 3 | 71e3 | varying the delay with each laser step to find optimum - It was more a plateau between +-30ns (relative to the night shift's position). We now continue data taking at the same dealy as used by the night shift.
|
08:23 | 2.4e8 | 6e5 | 225258 | 722 | 8205 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | 68e3 | xuv-detector walklevel and treshhold were lowered
|
08:28 | 2.4e8 | 6e5 | 225258 | 724-725 | 8208 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | 68e3 |
|
08:48 | 2.4e8 | 6e5 | 225258 | 727-728 | 8209 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | ? | xuv-detector in Park-position just as a try
|
09:08 | 2.4e8 | 6e5 | 225259 | 729-730 | 8210 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | ? |
|
09:28 | 2.5e8 | 6e5 | 225259 | 731-732 | 8211 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | 73e3 |
|
09:54 | 2.5e8 | 6e5 | 225259 | 734-735 | 8212 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | 175e3 |
|
10:19 | 2.5e8 | 6e5 | 225258 | 737-738 | 8214 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | 175e3 |
|
10:38 | 2.5e8 | 6e5 | 225258 | 741-742 | 8215 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | 64e3 | DAQ2 started late. Missed the first 25 scan numbers Coasting beam measurement from now on
|
10:57 | 2.5e8 | 6e5 | 225258 | 743-744 | 8216 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | 87e3 |
|
11:17 | 2.5e8 | 6e5 | 225258 | 745 | 8217 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | e3 | MBS crashed
|
11:18 | 2.5e8 | 6e5 | 225257 | 746-747 | 8218 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | 87e3 |
|
11:37 | 2.5e8 | 6e5 | 225257 | 749-750 | 8219 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | 87e3 | DAQ2 started late. Missed the first 10 scan numbers
|
11:56 | 2.5e8 | 6e5 | 225257 | 751 | 8220 | 548.36 - 548.51 | 0.0025 | 4.95s | 3 | 78e3 |
|
12:59 | 2.5e8 | 6e5 | 225257 | 752 | 8221 | 548.385 - 548.485 | 0.0025 | 4.95s | 3 | 78e3 | RF off from now on, laser scan settings not correct. stopped
|
13:06 | 2.5e8 | 6e5 | 225257 | 753 | 8223 | 548.385 - 548.485 | 0.0025 | 4.95s | 3 | 87e3 |
|
13:26 | 2.5e8 | 6e5 | 225257 | 754 | 8224 | 548.385 - 548.485 | 0.0025 | 4.95s | 3 | - | MBS crashed
|
13:29 | 2.5e8 | 6e5 | 225257 | 755-756 | 8226 | 548.385 - 548.485 | 0.0025 | 4.95s | 3 | 93e3 | RF now really off (wrong cavity was turned off)
|
13:43 | 2.5e8 | 6e5 | 225257 | 757-758 | 8227 | 548.385 - 548.485 | 0.0025 | 4.95s | 3 | 67e3 |
|
14:08 | 2.5e8 | 6e5 | 225257 | 759 | 8228 | 548.385 - 548.485 | 0.0025 | 4.95s | 3 | 70e3 |
|
14:22 | 2.2e8 | 6e5 | 225257 | 760 | 8229 | 548.385 - 548.485 | 0.0025 | 4.95s | 3 | 56e3 |
|
14:35 | 2.2e8 | 6e5 | 225257 | 761 | 8230 | 548.385 - 548.485 | 0.0025 | 4.95s | 3 | 64e3 |
|
14:50 | 2.2e8 | 6.5e5 | 225256 | 762 | 8231 | 548.385 - 548.485 | 0.0025 | 4.95s | 3 | 59e3 |
|
15:04 | 2.0e8 | 7e5 | 225255 | 763 | 8232 | 548.385 - 548.485 | 0.0025 | 4.95s | 3 | 58e3 |
|
15:28 | 1.9e8 | ?e5 | 225272 | 764 | 8233 | 548.385 - 548.485 | 0.0025 | 4.95s | 2 | 66e3 | changed to 200mA cooler current, NTCAP stopped and started again folder: prob. ~31.5.22 13:??, loops decreased to 2
|
15:37 | 2e8 | 6e5 | 225272 | 765 | 8234 | 548.385 - 548.485 | 0.0025 | 4.95s | 2 | 70e3 |
|
15:47 | 2.5e8 | 6e5 | 225272 | 766 | 8235 | 548.385 - 548.485 | 0.0025 | 4.95s | 2 | 73e3 | laser gone at loop 2 scan 35 (15:56), Ecooler went also off
|
16:17 | ?e8 | 6e5 | 225272 | 767 | 8236 | 548.385 - 548.485 | 0.0025 | 4.95s | 2 | 48e3 | bad shot?, probably ecooler reset
|
16:27 | 2.2e8 | 6e5 | 225271 | 768 | 8237 | 548.385 - 548.485 | 0.0025 | 4.95s | 2 | 77e3 |
|
16:36 | 2.0e8 | 7e5 | 225272 | 769 | 8238 | 548.385 - 548.485 | 0.0025 | 4.95s | 2 | 65e3 |
|
16:52 | ?e8 | ?e5 | 225272 | 770 | 8239 | 548.385 - 548.485 | 0.0025 | 4.95s | 2 | 61e3 | we had to restart go4, it was very slow
|
17:02 | 2.0e8 | 7e5 | 225272 | 771 | 8240 | 548.385 - 548.485 | 0.0025 | 4.95s | 2 | 63e3 |
|
17:16 | 2.3e8 | 7e5 | 225248 | 772-773 | 8241 | 548.385 - 548.485 | 0.0025 | 4.95s | 4 | 45e3 | changed to 50mA cooler current, NTCAP stopped and started again folder: 31.5.22 15:18, loops increased to 4
|
17:36 | 2.7e8 | 7.5e5 | 225248 | 774-775 | 8242 | 548.385 - 548.485 | 0.0025 | 4.95s | 6 | 67e3 | loops increased to 6
|
18:05 | 2.5e8 | 7.5e5 | 225248 | 776-777 | 8243 | 548.385 - 548.485 | 0.0025 | 4.95s | 6 | 66e3 |
|
18:31 | 1.7e8 | 6e5 | 225247 | 778-779 | 8244 | 548.385 - 548.485 | 0.0025 | 4.95s | 6 | 44.6e3 | SIS pattern looked strange
|
|
Attachment 1: 2022-05-31_particles.png
|
|
97
|
Tue May 31 03:18:52 2022 |
Patrick, Konstantin | Laser | Laser timing |
The final timings are (in bins +-1):
PD NO: 103
PD SO: 138
PMT middle: 44
e-cooler = (PD NO + PD SO) / 2: 121
e-cooler - PMT middle: 77
roundtrip / 2: 75
roundtrip / 2 + 10ns: 78 |
98
|
Tue May 31 15:19:58 2022 |
Max, Carsten, Danyal | General | scans for different E-cool currents |
until 15:15 we have measured with I_e = 100 mA (3 loops per file)
E_cool HV = 225255 V
after that (at 15:26) we changed to I_e = 200 mA (2 loops per file)
E_cool HV = 225272 V
after that (at 17:15) we changed to I_e = 50 mA (first 4 then 6 loops per file)
E_cool HV = 225247 V |
99
|
Tue May 31 17:22:09 2022 |
Max, Carsten, Danyal, Rodolfo, Wilfried | General | change E-cooler current I_e = 50 mA |
At 17:15 we changed again the E-cooler current I_e = 50 mA
(4 laser scan loops per injection)
E-cool HV = 225248 V |
100
|
Tue May 31 19:32:56 2022 |
Carsten, Wilfried, Max | Calibration | electron cooler calibration voltage - frequency |
SetVoltage (DeltaU) | MeasVoltage | freq | Current
|
+1950V | 225247V | 245.06725 | 50 mA
|
+1950V | 225255.4V | 245.0595 | 100 mA
|
+1960V | 225266.4V | 245.062125 | 100 mA
|
+1970V | 225276.8V | 245.064185 | 100 mA
|
+1980V | 225286.6V | 245.066 | 100 mA
|
+1990V | 225296.1V | 245.06775 | 100 mA
|
+2000V | 225305.1V | 245.0695 | 100 mA
|
+1950V | 225255.5V | 245.06 | 100 mA
|
+1940V | 225246.0V | 245.058125 | 100 mA
|
+1930V | 225236.0V | 245.05625 | 100 mA
|
+1920V | 225226.0V | 245.0545 | 100 mA
|
+1910V | 225216.7V | 245.052625 | 100 mA
|
+1900V | 225205.8V | 245.050375 | 100 mA
|
+1850V | 225156.5V | 245.041 | 100 mA
|
+1800V | 225106.6V | 245.031375 | 100 mA
|
+1950V | 225256.1V | 245.060125 | 100 mA
|
+2000V | 225306.0V | 245.06975 | 100 mA
|
+2050V | 225355.8V | 245.079375 | 100 mA
|
+2100V | 225406.0V | 245.0890 | 100 mA
|
+1950V | 225256.2V | 245.060125 | 100 mA
| Change electron current and note down High Vltage and revolution frequency
NTCAP was restarted at the beginning and stopped at the end of the measuring period.
The NTCAP folder is 05-31_17-16-49 (system time 19:11) |
101
|
Tue May 31 19:37:30 2022 |
Carsten, Max, Wilfried | Detectors | SASZ and NASZ voltages switched off |
SASZ and NASZ voltages were switched off bevor we went back to 209Bi. Laser beam stabilization turned off. |
102
|
Tue May 31 19:59:49 2022 |
Carsten, Danyal | Accelerator | change in frequency mismatch 208Bi --> 209Bi |
time = 20:00
The RF has been adjusted so that it bunches at the correct frequency for 209Bi
For 208Bi the settings ("frequency mismatch") were:
-0.102 in SC5
-0,102 in SC11
For 209Bi the settings ("frequency mismatch") are (and were yesterday):
-0.83 in SC5
-0,83 in SC11 |
103
|
Tue May 31 21:08:04 2022 |
Carsten, Max | Detectors | XUV detector automation off |
We deactivated the automation of the XUV detector. It stays out now. |
104
|
Tue May 31 21:58:55 2022 |
Max, Rodolfo | Laser | MRC Settings for 209Bi |
We have change the laser settings for the spectroscopy of 209Bi.
We have now T-scraped the laser beam to the old position of the ion beam. The settings for the MRC system are shown in the screenshot below. |
Attachment 1: MRC_209Bi_31-05-2022_2157.png
|
|
105
|
Wed Jun 1 00:03:08 2022 |
Konstantin, Simon, Kristian | Runs | 209-Bi runs |
Time | SIS-intensity | ESR-intensity after orbit change | cooler-HV | cooler current (mA) | LMD-DAQ2 file nr | LMD-DAQ1 file nr | scan range(nm) | step width increment (nm) | dwell time(s) | n loops | comments
|
23:40 | - | - | 223432 | 100 | 781 | 8246 | 601.735 - 601.95 | 0.005 | 4.95s | 2 | resonance found but problems with go4
|
00:02 | - | 5.5e6 | 223432 | 100 | 783 | 8248 | 601.735 - 601.95 | 0.005 | 4.95s | 2 | resonance not in the middle of the scan range
|
00:14 | - | 4.5e6 | 223432 | 100 | 784 | 8249 | 601.7 - 601.9 | 0.005 | 4.95s | 2 | change the scan range
|
00:14 | - | 1.1e7 | 223432 | 100 | 785 | 8250 | 601.7 - 601.9 | 0.005 | 4.95s | 2 |
|
00:35 | - | 9e6 | 223432 | 100 | 786-787 | 8251 | 601.7 - 601.9 | 0.005 | 4.95s | 4 |
|
00:50 | - | 6.5e6 | 223432 | 100 | 788-789 | 8252 | 601.7 - 601.9 | 0.005 | 4.95s | 4 |
|
01:07 | 2.2e8 | 1.15e7 | 223432 | 100 | 790-791 | 8253 | 601.7 - 601.9 | 0.005 | 4.95s | 4 |
|
01:26 | 2.3e8 | 1.15e7 | 223448 | 200 | 792 | 8254 | 601.7 - 601.9 | 0.005 | 4.95s | 2 | switched to coasting beam, changed ESR current
|
01:37 | 2.2e8 | 1.15e7 | 223448 | 200 | 793 | 8255 | 601.7 - 601.9 | 0.005 | 4.95s | 2 |
|
01:48 | 2.2e8 | 1.15e7 | 223448 | 200 | 794 | 8256 | 601.7 - 601.9 | 0.005 | 4.95s | 2 |
|
01:58 | 2.2e8 | 1.15e7 | 223448 | 200 | 795 | 8257 | 601.7 - 601.9 | 0.005 | 4.95s | 2 |
|
02:08 | 2.2e8 | 1.15e7 | 223448 | 200 | 796 | 8258 | 601.7 - 601.9 | 0.005 | 4.95s | 2 |
|
02:19 | 2.15e8 | 1.15e7 | 223432 | 100 | 797-799 | 8259 | 601.7 - 601.9 | 0.005 | 4.95s | 6 | changed ESR current again
|
02:45 | 2.17e8 | 1.15e7 | 223432 | 100 | 800-802 | 8260 | 601.7 - 601.9 | 0.005 | 4.95s | 6 |
|
03:12 | 2.12e8 | 1.15e7 | 223423 | 50 | 803-805 | 8261 | 601.7 - 601.9 | 0.005 | 4.95s | 6 | changed cooler current again, restarted NTCAP folder 2022-05-31_19-33-57
|
03:38 | 2.2e8 | 1.15e7 | 223423 | 50 | 806-808 | 8262 | 601.7 - 601.9 | 0.005 | 4.95s | 6 |
|
04:05 | 2.13e8 | 1.15e7 | 223427 | 75 | 809-811 | 8263 | 601.7 - 601.9 | 0.005 | 4.95s | 6 | changed cooler current again, restarted NTCAP folder 2022-06-01_03-12-03
|
04:30 | 2.03e8 | 1.15e7 | 223427 | 75 | 812-814 | 8264 | 601.7 - 601.9 | 0.005 | 4.95s | 6 |
|
04:57 | 2.08e8 | 1.15e7 | 223440 | 150 | 815-817 | 8265 | 601.7 - 601.9 | 0.005 | 4.95s | 6 | changed cooler current again, restarted NTCAP folder 2022-06-01_04-04-32
|
05:21 | 2.1e8 | 1.15e7 | 223440 | 150 | 818-820 | 8266 | 601.7 - 601.9 | 0.005 | 4.95s | 6 |
|
05:57 | 2.08e8 | 1.15e7 | 223440 | 150 | 821-823 | 8267 | 601.7 - 601.9 | 0.005 | 4.95s | 6 | laser power reduced from 46.2mJ to 25mJ
|
06:25 | 1.5e8 | 9e6 | 223440 | 150 | 824-826 | 8268 | 601.7 - 601.9 | 0.005 | 4.95s | 6 |
|
06:56 | 2.1e8 | 1.15e7 | 223440 | 150 | 827-829 | 8269 | 601.7 - 601.9 | 0.005 | 4.95s | 6 | Laser power reset to 48mJ. Last ion injection!!!
|
07:18 | - | 4.7e6 | 223439 | 150 | 830-832 | 8270 | 601.7 - 601.9 | 0.005 | 4.95s | 6 | Last ion injection!!!
|
7:40 | - | 2.0e6 | 223439 | 150 | 833-834 | 8271 | 601.7 - 601.9 | 0.005 | 4.95s | 6 | old beam
|
8:02 | - | 1.0e6 | 223439 | 150 | 835-836 | 8272 | 601.7 - 601.9 | 0.005 | 4.95s | 6 | older beam
|
8:25 | - | 5e5 | 223439 | 150 | 837-8 | 8273 | 601.7 - 601.9 | 0.005 | 4.95s | 6 | very old beam
|
8:48 | - | 3e5 | 223439 | 150 | 839-840 | 8274 | 601.7 - 601.9 | 0.005 | 4.95s | 6 | very very old beam
|
9:10 | - | 2e5 | 223439 | 150 | 841-842 | 8275 | 601.7 - 601.9 | 0.005 | 4.95s | 6 | beam close to retirement - no signal anymore
|
9:33 beam retired. Turned laser off. Stopped NTcap
post beamtime change: replaced "ESR current" by "cooler current" in the comments column. (Wilfried) |
106
|
Wed Jun 1 00:16:02 2022 |
Konstantin, Simon | DAQ | Timing 209Bi thick target |
Timing for the final measurements on 209Bi was determined for the new frequency 1.93777MHz. Peak positions are
PD NO 106
PD SO 141.5
PMT MIDDLE 45 (due to the broad temporal structure difficult to determine)
Center between PDs is 123.75. Difference to PMT MIDDLE is 78.75. This is ~3 bins larger than the half period of 75. |
Attachment 1: Timing_209Bi_final.png
|
|
107
|
Wed Jun 1 08:39:50 2022 |
Kristian, Konstantin | Calibration | Wavemeter reading |
We recorded files with high wavemeter readout rate and saved it at the atplaser network drive (Q:) - Bismuth - wavemeter folder.
Could be used to calibrate the laser steps. The MBS readout rate is 4 Hz, here 30 Hz, so there are a few more values. |
108
|
Wed Jun 1 17:20:04 2022 |
Rodolfo | Laser | HeNe @ WS7 |
|
Attachment 1: HeNe_WS7_01-06-2022_1.png
|
|
109
|
Fri Jun 3 12:01:17 2022 |
Danyal | Detectors | switched off XUV detector on 1 June ~17:00 |
I have switched off the XUV detector on 1 June at about 17:00.
The high voltages of the MCP (in ESR laser lab) were turned off and inside the ESR cave the power supplies (coils and cathode) and the crate were turned off.
Also the new "control box" for the detector was switched off.
And I checked (visually) that the XUV detector (and the Cu detector too) were indeed "moved out".
Danyal |
110
|
Thu Jun 30 11:12:21 2022 |
Carsten | Analysis | Updated Go4 Analysis with small Bugfix (PMTOverWavelength SPectra) |
Here attached is a more recentversion of the Go4 Analysis Code with some smaller bugfixes.
For adaequate *.C files please have alook in 208Bi go4 directory on the atplaser account.
Please note, that there is also a (not fully up-to-date) description/manual somewhere here in the Elog. |
Attachment 1: 208Bi_20220629_fix.tgz
|
111
|
Fri Jan 13 17:05:22 2023 |
Rodolfo | Laser | Testing WS6 |
Testing the new Wavemeter (HighFinesse, WS6, SN3950) with the QRAY laser light @ 532 nm. Multimode fiber von High Finesse:FC/PC S (Corning, MM, OM2) |
Attachment 1: WS6_3950_QRayWavelength_13-01-2022.png
|
|
112
|
Wed Jan 18 13:02:12 2023 |
Rodolfo | Laser | Testing WS6 with Cobra |
Testing the WS6 (S.N. 3950) together with the Cobra.
Cobra operated with dye DCM in Ethanol + DMSO (Concentration 1:1)
- Oscillator concentration 0.3 g/l.
- Main amplifier concentration 0.0375 g/l (1/8 oscillator concentration).
- Laser linewidth: 6 GHz. Expansion factor: 10x. Grating: 2400 g/mm (40/2013)
Seed energy: 504 mJ @ 532 nm.
Cobra output energy: 112 mJ @ 640 nm.
Scan settings: 640.0 nm - 639.8 nm @ 0.005 nm / step.
Wavemeter settings: Pulsed (ext. trigg. 1 = QRay-Output: Lamp Sync). Precision: Fine.
- Wavemeter calibration. Reference source: Neon lamp.
- LTA-Data under ATPPC023 D:\WLM6 LTA data\D:\WLM6 (18.01.2023, 11.23, 640,10656 nm.lta) |
Attachment 1: WS6_640-639.8_0.005_18-01-2023_11.23.png
|
|
113
|
Tue Jun 6 09:33:00 2023 |
Rodolfo | Laser | Fiber coupler |
Cobra's new fiber-coupling unit for wavelength reading. |
Attachment 1: Cobra_FiberCoupler.jpg
|
|